2002-05-06 MN Dept of Health Report on Plans*s
MINNESOTA DEPARTMENT OF HEALTH
Division of Environmental Health
REPORT ON PLANS
Plans and specifications on watermain: Albertville Crossing, Albertville, Wright County, Minnesota,
Plan No. 023077
OWNERSHIP: City of Albertville, c/o Ms. Linda Goeb, Clerk, Albertville City Hall, P.O. Box 9, Albertville,
Minnesota 55301-0009
SUBMITTER(S): John Oliver & Associates, Inc., 580 Dodge Avenue, Elk River, Minnesota 55330
Plans Dated:
Date Received: May 6, 2002, April 29, 2002
Date Reviewed: May 6, 2002
SCOPE: This report covers the design of this project insofar as the safety and sanitary quality of the water for
public consumption may be affected, and applies to this project only and not to the entire system or any other
part thereof. The examination of plans is based upon the supposition that the data on which the design is based
are correct, and that necessary legal authority has been obtained to construct the project. The responsibility for
the design of structural features and the efficiency of equipment must be taken by the project designer. Approval
is contingent upon satisfactory disposition of any requirements included with this report.
Water supply plans are examined with regard to the location, construction and operational features of the design
and maintenance of all parts of the system which may affect the safety and sanitary quality of the water.
Examination is based on the standards of this department.
This project consists of the installation of the following watermains:
1. 1,323 lineal feet of 6-inch C - 900 PVC watermain.
REQUIREMENT(S):
1. The disinfection of the watermain shall be performed according to AWWA Standard C 651. If the tablet or
continuous feed methods are used, the completed watermain shall be disinfected for 24 hours with at least
50 ppm available chlorine, with a residual of at least 10 ppm throughout the length of the main at the end of
the 24 hour period.
COMPLIANCE: No construction shall take place except in accordance with the approved plans. If it is desired
to make deviations from the approved plans, the State Department of Health should be consulted and approval of
the changes obtained before construction is started; otherwise, such construction is installed without proper
approval, and in addition may create dangers to public health.
Authorization for construction in accordance with the approved plans may be withdrawn if construction is not
undertaken within a period of two years. The fact that the plans have been approved does not necessarily mean
that recommendations or requirements for change will not be made at some later time when changed conditions,
additional information, or advanced knowledge make improvements necessary.
a
Albertville Crossing
Watermain
Plan No. 023077
Page 2
May 6, 2002
Approved:
AL'I
Brian A. Noma, P.E.
Public Health Engineer
Section of Drinking Water Protection
P.O. Box 64975
St. Paul, Minnesota 55164-0975
651/215-0947
BAN:DAR:cac
cc: City of Albertville ✓
John Oliver & Associates, Inc.
File
David A. Rindal
Public Health Engineer
Section of Drinking Water Protection
P.O. Box 64975
St. Paul, Minnesota 55164-0975
651/215-0788