2002-04 Technical Specification Manual1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 TECHNICAL SPECIFICATION MANUAL FOR SITE GRADING, SANITARY SEWER, WATERMAIN, STORM SEWER & PAVING IMPROVEMENTS OPPIDAN INVESTMENT COMPANY. ALBERTVILLE CROSSING ALBERTVILLE, MINNESOTA JOHN OLIVER & ASSOCIATES, INC. 580 DODGE AVENUE ELK RIVER, MINNESOTA 55330 (763) 441-2072 File: 7701.30-03 APRIL, 2002 MiNNESOTA DEPARTMENT OF HEALTH t) vision of Envirortnental Health 1rjis is to certify that this is a copy of the plan referred to in approval letter on wated improvements, datad � �°, 0 6 ZO_ I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly Licensed Professional Engineer under State of Minnesota Statutes Sections 326.02 to 326.16. Todd McLouth Date: April 18, 2002 Reg. No. 20383 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 GENERAL INDEX TITLE SHEET GENERAL INDEX INFORMATION FOR BIDDERS SECTION 02010 SUBSURFACE INVESTIGATION SECTION 02101 EROSION CONTROL SECTION 02200 EARTHWORK SECTION 02223 BACKFILLING FOR UTILITIES SECTION 02512 ASPHALTIC CONCRETE PAVING SECTION 02514 PORTLAND CEMENT CONCRETE WALKS, CURBS AND GUTTERS SECTION 02665 WATER SYSTEM SECTION 02720 STORM SEWAGE SYSTEM SECTION 02730 SANITARY SEWAGE SYSTEM r APPENDIX "A" JOINT POWERS WATER BOARD STANDARD REQUIREMENTS FOR DESIGN AND CONSTRUCTION OF WATERMAIN - FEBRUARY 1998 A it �iE50TA DEPARTMENT OF HEALTH D ylsien of ElvirOnrrent,al Health Vis s k +o certiry t4ct this is a copy of the plan referred to in approval letter on water. Improvements, dated a 6 Z02 INFORMATION FOR BIDDERS IB-01 BIDDING PROCESS The request for bids on this project, issuance of contract documents, receipt of bids, award of bids and any other part of the bidding process will be established by the Owner and/or the General Contractor. IB-02 BIDDING DOCUMENTS The following documents are available for bidders: This Technical Specification Manual Final Grading Plan, Final Utility Plan, Site Plan, and Landscape Plan Geotechnical Exploration Study by Independent Testing Technologies (Available on request from the Owner or General Contractor) IB-03 OWNER The Owner and Owner's representatives are: Dennis Crowe Oppidan Investment Company 5125 County Road 101 Suite 100 Minnetonka, MN 55345 952-294-0353 (Telephone) 952-294-0151 (Facsimile) IB-04 DESCRIPTION OF PROJECT This project consists of construction of site grading, watermains, sanitary sewers, storm sewer, pavement construction and turf restoration for the proposed ALBERTVILLE CROSSING development in Albertville, Minnesota. The various items of work are described as follows: Site Grading • Stripping topsoil and other materials unsuitable for foundation purposes. • Recompaction of existing materials as necessary. . • Replacing unsuitable materials and constructing embankments with materials mined from onsite and replacing mined materials with unsuitable materials. • Constructing subgrades for pavement and building pad areas. • Installing and maintaining erosion control measures and temporary erosion and siltation control devices. Sanitary Sewer • Onsite gravity pipe system. I13-1 of 2 SECTION 02010 SUBSURFACE INVESTIGATION PART GENERAL 1.01 INVESTIGATION REPORT A. A soil and subsurface investigation was conducted at the site, the results of which are to be found in a report from Independent Testing Technologies dated March 1,1.999. B. A copy of the report is available on request from the Owner or General Contractor C. The soil and subsurface investigation report is not apart of the Contract Documents,. but is included for information regarding the existing soil composition.- The Contractor is to assume responsibility for correcting any subsurface conditions for which recommendations are contained in the soil reports. PART 2 PRODUCTS NOT USED PART 3 EXECUTION NOT USED END OF SECTION 02010-1 M SECTION 02101 EROSION CONTROL PART GENERAL 1.01 SECTION INCLUDES A. Erosion Control requirements 1.02 RELATED SECTIONS A. Earthwork B. Bituminous Paving 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. 1.03 REGULATORY REQUIREMENTS A. The Contractor shall conform to all federal, state, and local laws and regulations governing the disposal of al material offsite PART 2 PRODUCTS 2.01 Materials A. Prefabricated silt fence: Silt fence shall conform to Mn/Dot Spec 3886.2, B. B. Bale checks: Bale checks shall conform to Mn/DOT Spec. 3882.2 Type 1. PART 3 EXECUTION 3.01 EROSION CONTROL A. The Contractor shall employ erosion control methods in accordance with Mn/Dot Spec. 1803.5, and 2573. 02101-1 IB. Erosion Control Sequencing ' 1. Silt fence and or straw bale checks shall be placed according to plan locations and details and at all perimeter areas where surface runoff leaves the site or in areas of concentrated flow. All silt fence and or straw bales shall be constructed ' before construction begins, except where they are installed within the proposed construction area. 2. Install other erosion control devices and/or seeding in proposed construction areas within 48 hours of completion of the grading within an area. ' C. All temporary stockpiled soil material shall be secured against wind and water erosion. D. Interim erosion control methods employed for the protection of the work shall be included in the Contractors Bid whether or not shown on the plan. The Contractor may be required to remove and replace sections of erosion control measures as part ' of the ordinary part of construction. E. The Contractor shall maintain all erosion control measures until such time the soil ' has been stabilized by vegetation. END OF SECTION 02101-2 SECTION 02200 EARTHWORK PART GENERAL 1.01 SECTION INCLUDES A. Finish grading: 1. Finish grade subsoil in non -landscaped areas 2. Compact subsoil (paved areas) 3. Finish grade topsoil in landscaped areas B. Site embankments C. Turf Establishment D. Compaction E. Testing 1.02 RELATED SECTIONS A. Backfilling for Utilities B. Bituminous Paving C. Portland Cement Concrete Paving D. Portland Cement Concrete Walks, Curbs and Gutters E. Drainage and Storm Sewer System F. Sanitary Sewer System 1.03 REFERENCES A. Divisions II and III Minnesota Department ofTransportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. 1.04 REGULATORY REQUIREMENTS A. The Contractor shall conform to all federal, state, and local laws and regulations governing the grading of the site. 1.05 TESTING A. The following tests or approvals shall be performed: 02200-1 1. Inspection and approval of subgrade material exposed to view after stripping, removal and grading as required by this Specification have been performed and prior to placing fill material. 2. Approval by the testing laboratory of material to be used as site fill. 3. Approval by the testing laboratory of material to be used as building backfill. 4. Field density tests of Engineered fill under walks, drives, pavements, structural slabs, curbs and gutters. 1.06 PROTECTION A. Identify required lines, levels, contours, and datum. B. Identify known underground, above ground, and aerial utilities. Stake and flag locations. Before any construction begins the contractor shall be responsible to contact Gopher One Call to locate, flag and identify all utilities in the field. C. Notify utility companies and city to remove and/or relocate utilities indicated. D. Protect above and below grade utilities which are to remain. E. Protect plant life, lawns and other features remaining as a portion of final landscaping. F. Protect bench marks, existing structures, fences, sidewalk, paving and curbs not removed as part of the site demolition. G. Protect excavations by sloping excavation sides, shoring, bracing, sheetpiling, underpinning, or other methods required to prevent cave-in or loose soil from falling into excavation. 1.07 SUBSURFACE CONDITIONS A. The Geotechnical Engineer's report is available on request from the Owner or General Contractor for informational purposes only. The results of borings are representative of those locations only and are not intended to represent conditions that may occur elsewhere on the site. 02200-2 U PART PRODUCTS ' 2.01 MATERIALS A. Topsoil: Reused. B. Select Granular Backfill: Select mineral soil in compliance liance with Mn/DOT g p 3149.2,13. C. Granular Backfill: Offsite borrow mineral soil in general compliance with Mn/DOT g p 3149.2, D, free of rocks larger than three inches. D. Common Backfill: On -site excavated soil free f o roots, stumps, rubbish, frozen material, organic and other similar materials whose presence in the backfill would cause excessive settlement. Acceptable soils shall meet ASTM D2487 designations for GW, SW, GP, SP, GM, SM, GC, and SC soils. All materials will be approved by the Geotechnical Engineer. E. Seed Mixtures: Mn/DOT Specification 3876 Mixture 60B 1 F. Mulch: Mn/DOT Spec. 3882, Type 1. 1 PART 3 EXECUTION 3.01 GENERAL A. Protection of Surface Structures: 1 1. All surface structures and features located outside the permissible excavation limits for underground installations, together with those within the construction areas which are indicated in the Plans as being saved', shall be properly protected against damage and shall not be disturbed or removed without approval of the General Contractor. Within the construction limits, as required, the removal of 1 improvements such as paving, curbing, walks, turf, etc., shall be subject to acceptable replacement after completion of underground work, with all expense of removal and replacement being borne by the Contractor to the extent that separate compensation is not specifically provided for in the contract. In the event of damage to any surface improvements, either privately or publicly owned, in the absence of construction necessity, the Contractor will be required 02200-3 to replace or repair the damaged property to the satisfaction of the Owner. 2. Obstructions such as street signs, guard posts, small culverts, and other items of prefabricated construction may be temporarily removed during construction provided that essential service is maintained in a relocated setting and that ' nonessential items are properly stored for the duration of construction. Upon completion of the underground work, all such items shall be replaced in their proper setting at the sole expense of the Contractor. B. Interference of Underground Structures: 1. When any underground structure interferes with the plan placement of the pipeline or appurtenances to such an extent that alterations in the work are necessary to eliminate the conflict or avoid endangering effects on either the existing or proposed facilities, the Contractor shall immediately notify the Owner of the affected structure. When any existing facilities are endangered, work shall cease at the site and such precautions shall be taken as may be necessary to protect the in place structure until a decision is made as to how the conflict will be resolved. 2. Without specific authorization from the Owner, no essential utility service shall be disrupted, nor shall any change be made in either the existing structures or the planned installations to overcome the interference. 3. Alterations in existing facilities will be allowed only to the extent that service will not be curtailed unavoidably and then only when the encroachment or relocation will satisfy all applicable regulations and conditions. 4. Wherever alterations are required as a result of unforeseen underground interferences not due to any fault or negligence of the Contractor, the Owner ' will issue a written order covering any additional or extra work involved and specifying the revised basis of payment, if any. Any alterations made strictly for the convenience of the Contractor, shall be subject to prior approval and shall be at the Contractor's expense. 5. No extra compensation will be allowed for delays caused by the interference of underground structures. 3.02 PREPARATION A. Identify and verify required lines, levels, contours and datum. IB. Before beginning construction each affected utility shall be notified and informed of 02200-4 1 1 the construction schedule. IC. Identify known below -grade utilities. Each affected utility shall locate in the field their respective utilities before excavation. D. Identify and flag above grade utilities. E. Upon discovery of unknown utility or concealed conditions, discontinue affected work; notify Owner. 3.03 FIELD QUALITY CONTROL ' A. Field inspection will be performed. tB. Provide for visual inspection of bearing surfaces. ' C. Oversizing excavation and backfilling will be observed by the Geotechnical Engineer. A 48-hour notice of the schedule is required for individual tasks. 3.04 PROTECTION A. Protect excavations by methods required to prevent cave in or loose soil from falling into excavation. B. Protect bottom of excavations and soil adjacent to and beneath foundation from freezing. C. Protect bench marks, existing structures, fences, sidewalk, paving and curbs from excavation equipment and vehicular traffic. ' D. Grade excavation top perimeter to prevent surface water run-off into excavation. 3.05 GENERAL EXCAVATION/EMBANKMENT A. All excavation and backfilling shall be made to the proper line and grade and in a manner that will ensure the final grades be as shown on the plans. B. All road or parking areas shall be subcut to an elevation that will allow the placement of the crushed rock base and bituminous pavement. All seeded or sodded areas shall ' be subcut to an elevation that will allow the placement of topsoil. C. The placement of embankment materials for structures or paved areas shall be made in maximum lifts of 8 inches. 02200-5 1 Ci I D. The moisture content of embankment materials shall be carefully controlled to obtain optimum compaction characteristics. This shall be accomplished by adding moisture to soils that are below optimum moisture or by placing soil in thin layers on a horizontal surface and disked and dried during warm weather before final placements fill material. All fill material shall be within 5 percent +/- of optimum moisture content when placed. All fill material with a moisture content greater than 5 percent above optimum shall be spread in thin layers and disked and dried before final placement and compaction as fill. Excavate subsoil required to accommodate building foundations, slabs -on -grade, paving and construction operations. E. Machine slope banks to angle of repose or less, until shored. F. Excavation cut not to interfere with normal 45 degree bearing splay of foundation. G. Grade top perimeter of excavation to prevent surface water from draining into excavation. H. Give timely notice to testing laboratory for observation of bearing surfaces upon completion of excavation. I. Secure stockpiles from sediment transport by encircling with silt fence. 3.06 TOLERANCES OF SUBGRADE A. Top Surface of Subgrade: Plus or minus 0.1 feet. 3.07 PLACING TOPSOIL A. Scarify subgrade to depth of 3 inches where topsoil is scheduled. Scarify in areas where equipment used for hauling and spreading topsoil has compacted subsoil. B. Place topsoil uniform thickness of a minimum of 4 inches in areas where seeding or sodding is to be done. C. Fine grade topsoil eliminating rough or low areas. Maintain levels, profiles, and contours of subgrade. D. Remove stone, roots, grass, weeds, debris, and foreign material while spreading. E. Leave stockpile area and site clean and raked, ready to receive landscaping. 02200-6 1 3.08 COMPACTION A. All compaction efforts shall obtain the following percentages of maximum dry density in accordance with the Modified Proctor procedures. 1. Fill used between 0 and 3 feet below paved areas. shall be compacted to a minimum of 98% of the Modified Proctor density. 2. Fill used below 3 feet under paved areas shall be compacted to a minimum of 95% of Modified Proctor density. 3. Compaction of all fill under building shall be compacted to 100% Modified Proctor Density. 4. All other areas shall be compacted to 95% of Modified Proctor density. B. Proof rolling will be required on the finished subgrade of all paved areas. Proof rolling shall consist of driving loaded a tandem axle dump truck or loaded large front end loader over subgrade. Proof roll shall be directed by the Geotechnical Engineer. ' Any deflection of two inches or greater shall be considered a failure. Subgrade will have to be corrected so that deflection is less than two inches. L� fl 1 3.09 TURF RESTORATION A. Seeding Areas 1. Seed mixture shall be Mn/DOT 60B at a rate of 100 pounds per acre. 2. The seeding shall not be done until the Engineer has inspected the area and approved the subgrade preparation and topsoil materials. 3. If so directed by the Engineer, the Contractor shall reseed at his cost any area on which the original seed has failed to grow, using the type of seed directed by the Engineer. 4. No fertilizer will be applied. 5. Type 1 mulch shall be applied to all seeded areas. 6. All seeding and mulching shall be done within 5 days after rough grading has been completed or as directed by regulatory agencies having jurisdiction. END OF SECTION 02200-7 1 SECTION 02223 BACKFILLING FOR UTILITIES PART GENERAL 1.01 SECTION INCLUDES A. Subgrade correction of utility trenches B. Backfilling all trenching operations for utility construction. C. Compaction requirements. 1.02 RELATED SECTIONS A. Testing Laboratory Services B. Earthwork. C. Drainage and Storm Sewage System D. Sanitary Sewer System 1.03 REFERENCES ' A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not 1 apply. B. Standard Utilities Specifications for Watermain and Service Line Installation and Sanitary Sewer and Storm Sewer Installation, City Engineers Association of Minnesota, 1999. ' 1.04 TESTING A. Soil and density testing will be performed by an independent Testing Agency. PART PRODUCTS ' 2.01 GRANULAR MATERIALS A. Granular materials furnished for foundation, bedding, encasement, backfill, or other purposes as may be specified shall consist of any natural or synthetic mineral aggregate such as sand, gravel, crushed rock, crushed stone, or slag, that shall be so ' graded as to meet the gradation requirements specified herein for each particular use. 1 02223-1 1. Granular Material Gradation Classification ' Percent Passing Material Use Designation Sieve Size Foundation Bedding Backfill 3 Inch ' 2 Inch Common 1 Inch 100 100 Backfill 3/4Inch 85-100 90-100 ' 3/8Inch 30-60 50-90 No. 4 0-10 35-80 No.10 20-65 No. 40 0-35 No. 200 0-10 2. Granular Material Use Designations Granular materials provided for Foundation, Bedding, Encasement, or Backfill use as required by the Contracts, either as part of the pipe item unit or as a separate contract item, shall be classified as to use in accordance with the following: Material Use Designation Zone Designation Granular Foundation Placed below the bottom of pipe grade as replacement for unsuitable or unstable soils, to achieve better foundation support. Granular Bedding Placed below the pipe midpoint, prior to pipe installation, to facilitate proper shaping ' and achieve uniform pipe support. Backfill Place above bedding. In each case above, unless otherwise indicated the lower limits of any particular zone shall be the top surface to the next lower course as constructed. The upper limits of ' each zone are established to define variable needs for material gradation and compaction or void content, taking into consideration the sequence of construction and other conditions. The material use and zone designations described above shall ' only serve to fulfill the objectives and shall not be construed to restrict the use of any particular material in other zones where the gradation requirements are met. 2.02 COMMON FILL MATERIALS I A. Subsoil: Reused; free of gravel larger than 3-inch size, and debris. 1 02223-2 PART 3 EXECUTION 3.01 PIPELINE BACKFILLING OPERATIONS A. In accordance with Mn/DOT 2451 and Section 02200 of this manual. 3.02 FIELD QUALITY CONTROL A. Compaction testing will be performed by an independent Testing Agency. B. Observation and testing of trench bottoms shall be made as the work progresses. C. If tests indicate work does not meet specified requirements, remove work, replace and retest at no cost to Owner. END OF SECTION 02223-3 SECTION 02512 BITUMINOUS PAVING PART GENERAL 1.01 SECTION INCLUDES A. Hot mix bituminous placement B. Gravel Base placement 1.02 RELATED SECTIONS A. Earthwork B. Portland Cement Concrete Walks, Curb and Gutters: Curbs 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. 1.04 SUBMITTALS A. Submittals required are: 1. Gradation for Aggregate Base. 2. Design Mix: Submit Mn/DOT certified formula for bituminous pavements. 1.05 QUALITY ASSURANCE A. Mixing Plant: Conform to Mn/DOT standards. i B. Obtain materials from same source throughout. 1.06 TESTS A. Analysis of Gravel Base and bituminous mix will be performed by an independent testing laboratory. 02512-1 1 IPART 2 PRODUCTS ' 2.01 MATERIALS A. Select Granular Borrow: Mn/DOT Spec. 3149. B. Class 5 Gravel Base: Mn/DOT Spec. 3138, recycled or virgin materials. C. Bituminous Non -Wear Course: Mn/Dot Spec. 2350. D. Bituminous Wearing Course: Mn/Dot Spec. 2350. PART 3 EXECUTION 3.01 COMPACTION REQUIREMENTS A. Subgrade soils from 0 to 3 feet below subgrade shall be compacted to 98% of maximum Modified Proctor density at not less than 95% or more than 105% of optimum moisture content. ' B. Select Granular Borrow and Aggregate Base Course shall be compacted to not less than 100% of maximum Modified Proctor density. Using conventional rolling equipment, moisture content shall not be less than 95% nor more than 105% of optimum moisture content. IC. Asphalt wearing and base courses shall be compacted by the Ordinary Compaction Method. Pavement smoothness shall be waived for this project. 3.02 SUBGRADE PREPARATION A. In accordance with Mn/DOT Spec. 2112. 3.03 SELECT GRANULAR BORROW CONSTRUCTION A. In accordance with Mn/DOT Spec. 2105. i 3.04 AGGREGATE BASE CONSTRUCTION A. Construct over the compacted subgrade or Select Granular Borrow in accordance ' with Mn/Dot Spec 2211. 3.05 BITUMINOUS NON -WEAR AND WEAR COURSES ' A. In accordance with Mn/DOT Spec. 2350. u 02512-2 1 B. Bituminous non -wear course shall be mixture type LV3 non -wearing course, LVNW35030A. C. Bituminous wear course shall be mixture type LV3 wearing course, LVWE 35030A. 3.06 TESTS AND SAMPLES A. Compaction testing and samples provided as follows: 1. Aggregate Base gradation before construction to verify compliance of the supplier, and during construction based on field observations. B. Should the samples fail the tests, corrections as required to comply with this Specification shall be made. C. The surface from which samples are taken shall be restored not later than the next succeeding day of plant operation. 3.07 ADJUSTMENT OF STRUCTURES A. All manholes, valve boxes and other structures within the pavement areas shall be adjusted to 0.05 feet below the adjacent finished surface. B. Fixtures shall be adjusted to finish grade before the final lift of pavement is placed adjacent to the fixture. END OF SECTION 02512-3 SECTION 02514 PORTLAND CEMENT CONCRETE WALKS, CURBS AND GUTTERS PART GENERAL 1.01 SECTION INCLUDES A. Curbs and gutters B. Surface finish C. Curing 1.02 RELATED WORK A. Earthwork B. Asphaltic Concrete Paving 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. 1.04 TESTS A. Two sets of concrete test cylinders, in accordance with ASTM C31, will be taken each day concrete is placed. B. One slump test will be taken for each set of test cylinders taken. C. One air content test, in accordance with ASTM C231, shall be taken for each set of test cylinders taken. Air content shall be maintained within the range of four to seven percent. 1.05 SIDEWALKS AND PEDESTRIAN RAMPS A. See Architectural Specification for Sidewalks and Pedestrian Ramp Locations. PART PRODUCTS 2.01 CONCRETE MATERIALS A. For curbing using manual placement use Concrete Mix No. 3A32 per Mn/DOT Specification 2461. 02514-1 1 ' B. For curbing using slip form placement use Concrete Mix No. 3A22 per Mn/DOT Spec. 2461. ' 2.02 OTHER MATERIALS A. Curing Compound shall conform to Mn/DOT Spec 3754. ' PART 3 EXECUTION 1 3.01 CURB WITH AND WITHOUT GUTTER A. In accordance with Mn/DOT Spec 2531, except joint filler is not required. 3.02 CONCRETE CURING AND PROTECTION ' A. After the finishing operations have been completed and as soon as the set of the concrete permits, the concrete shall be cured for a minimum of 72 hours. All surfaces exposed to air at the time of cure shall be coated with membrane curing ' compound. Apply the curing compound in accordance with the manufacturer's instructions and Mn/Dot Spec. 2301.3,M. During cold weather the Contractor shall protect the concrete from frost damage prior to and throughout the duration of the ' cure. 3.03 FIELD QUALITY CONTROL A. Field inspection and testing will be performed under provisions of Section 01410. iB. Maintain records of placed concrete items. Record date, location of pour, quantity, air temperature and test samples taken. END OF SECTION IF 02514-2 1 r, L SECTION 02665 WATER SYSTEM PART GENERAL 1.01 SECTION INCLUDES A. All aspects of construction of the water system outside of the proposed buildings. 1.02 GOVERNING SPECIFICATIONS A. Construction of the water system is in accordance with the Joint Powers Water Board, Standard Requirements for Design and Construction. of Watermain. A copy is included in Appendix A. 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. 1.04 REGULATORY REQUIREMENTS A. The Contractor shall conform to all federal, state, and local laws and regulations governing the grading of the site. 1.05 TESTING A. The following tests or approvals shall be performed: 1. Inspection and approval of subgrade material exposed to view after stripping, removal and grading as required by this Specification have been performed and prior to placing fill material. ` 2. Approval by the testing laboratory of material to be used as site fill. 3. Approval by the testing laboratory of material to be used as building backfill. 4. Field density tests of Engineered fill under walks, drives, pavements, structural slabs, curbs and gutters. 02665-1 0 ' 1.06 PROTECTION A. Identify required lines, levels, contours, and datum. B. Identify known underground, above ground, and aerial utilities. Stake and flag ' locations. Before any construction begins the contractor shall be responsible to contact Gopher One Call to locate, flag and identify all utilities in the field. C. Notify utility companies and city to remove and/or relocate utilities indicated. ' D. Protect above and below grade utilities which are to remain. E. Protect plant life, lawns and other features remaining as a portion of final ' landscaping. F. Protect bench marks, existing structures, fences, sidewalk, paving and curbs not ' removed as part of the site demolition. G. Protect excavations by sloping excavation sides, shoring, bracing, sheetpiling, underpinning, or other methods required to prevent cave-in or loose soil from falling into excavation. ' 1.07 SUBSURFACE CONDITIONS A. The Geotechnical Engineer's report is available on request from the Owner or General Contractor for informational purposes only. The results of borings are representative of those locations only and are not intended to represent conditions that may occur elsewhere on the site. PART PRODUCTS t2.01 MATERIALS A. Topsoil: Reused. B. Select Granular Backfill: Select mineral soil in general compliance with Mn/DOT ' 3149.2,B. C. Granular Backfill: Offsite borrow mineral soil in general compliance with Mn/DOT 3149.2, D, free of rocks larger than three inches. D. Common Backfill: On -site excavated soil free of roots, stumps, rubbish, frozen material, organic and other similar materials whose presence in the backfill would 02665-2 cause excessive settlement. Acceptable soils shall meet ASTM D2487 designations for GW, SW, GP, SP, GM, SM, GC, and SC soils. All materials will be approved ' by the Geotechnical Engineer. E. Seed Mixtures: ' Mn/DOT Specification. 3876 Mixture 60B ' F. Mulch: Mn/DOT S ecificaiton 3882 Type 1. P � Yp PART 3 EXECUTION ' 3.01 GENERAL A. Protection of Surface Structures: 1. All surface structures and features located outside the permissible excavation limits for underground installations, together with those within the construction areas which are indicated in the Plans as being saved, shall be properly protected against damage and shall not be disturbed or removed without approval of the General Contractor. Within the construction limits, as required, the removal of 1 improvements such as paving, curbing, walks, turf, etc., shall be subject to acceptable replacement after completion of underground work, with all expense of removal and replacement being borne by the Contractor to the extent that ' separate compensation is not specifically provided for in the contract. In the event of damage to any surface improvements, either privately or publicly ' owned, in the absence of construction necessity, the Contractor will be required to replace or repair the damaged property to the satisfaction of the Owner. 2. Obstructions such as street signs, guard posts, small culverts, and other items of prefabricated construction may be temporarily removed during construction i ' provided that essential service is maintained in a relocated setting and that nonessential items are properly stored for the duration of construction. Upon completion of the underground work, all such items shall be replaced in their proper setting at the sole expense of the Contractor. B. Interference of Underground Structures: t1. When any underground structure interferes with the plan placement of the pipeline or appurtenances to such an extent that alterations in the work are ' necessary to eliminate the conflict or avoid endangering effects on either the 02665-3 ' existing or proposed facilities, the Contractor shall immediately notify the Owner of the affected structure. When any existing facilities are endangered, work shall cease at the site and such precautions shall be taken as may be necessary to protect the in place structure until a decision is made as to how the conflict will be resolved. 2. Without specific authorization from the Owner, no essential utility service shall be disrupted, nor shall any change be made in either the existing structures or the ' planned installations to overcome the interference. 3. Alterations in existing facilities will be allowed only to the extent that service will not be curtailed unavoidably and then only when the encroachment or relocation will satisfy all applicable regulations and conditions. ' 4. Wherever alterations are required as a result of unforeseen underground interferences not due to any fault or negligence of the Contractor, the Owner will issue a written order covering any additional or extra work involved and specifying the revised basis of payment, if any. Any alterations made strictly for the convenience of the Contractor, shall be subject to prior approval and shall ' beat the Contractor's expense. 5. No extra compensation will be allowed for delays caused by the interference of ' underground structures. 3.02 PREPARATION 1 A. Identify and verify required lines, levels, contours and datum. ' B. Before beginning construction each affected utility shall be notified and informed of the construction schedule. C. Identify known below -grade utilities. Each affected utility shall locate in the field their respective utilities before excavation. ' D. Identify and flag above grade utilities. O E. Upon discovery of unknown utility or concealed conditions, discontinue affected work; notify Owner. 1 3.03 FIELD QUALITY CONTROL A. Field inspection will be performed. 02665-4 11 1 1 fl B. Provide for visual inspection of bearing surfaces. C. Oversizing excavation and backfilling will be observed by the Geotechnical Engineer. A 48-hour notice of the schedule is required for individual tasks. 3.04 PROTECTION A. Protect excavations by methods required to prevent cave in or loose soil from falling into excavation. B. Protect bottom of excavations and soil adjacent to and beneath foundation from freezing. C. Protect bench marks, existing structures, fences, sidewalk, paving and curbs from excavation equipment and vehicular traffic. D. Grade excavation top perimeter to prevent surface water run-off into excavation. 3.05 GENERAL EXCAVATION/EMBANKMENT A. All excavation and backfilling shall be made to the proper line and grade and in a manner that will ensure the final grades be as shown on the plans. B. All road or parking areas shall be subcut to an elevation that will allow the placement of the crushed rock base and bituminous pavement. All seeded or sodded areas shall be subcut to an elevation that will allow the placement of topsoil. C. The placement of embankment materials for structures or paved areas shall be made in maximum lifts of 8 inches. D. The moisture content of embankment materials shall be carefully controlled to obtain optimum compaction characteristics. This shall be accomplished by adding moisture to soils that are below optimum moisture or by placing soil in thin layers on a horizontal surface and disked and dried during warm weather before final placements fill material. All fill material shall be within 5 percent +/- of optimum moisture content when placed. All fill material with a moisture content greater than 5 percent above optimum shall be spread in thin layers and disked and dried before final placement and compaction as fill. Excavate subsoil required to accommodate building foundations, slabs -on -grade, paving and construction operations. E. Machine slope banks to angle of repose or less, until shored. 02665-5 U IF. Excavation cut not to interfere with normal 45 degree bearing splay of foundation. G. Grade top perimeter of excavation to prevent surface water from draining into excavation. H. Give timely notice to testing laboratory for observation of bearing surfaces upon completion of excavation. ' I. Secure stockpiles from sediment transport by encircling with silt fence. 3.06 TOLERANCES OF SUBGRADE ' A. Top Surface of Subgrade: Plus or minus 0.1 fee t. ' 3.07 PLACING TOPSOIL ' A. Scarify subgrade to depth of 3 inches where topsoil is scheduled. Scarify in areas where equipment used for hauling and spreading topsoil has compacted subsoil. I B. Place topsoil uniform thickness of a minimum of 4 inches in areas where seeding or sodding is to be done. IC. Fine grade topsoil eliminating rough or low areas. Maintain levels, profiles, and contours of subgrade. ' D. Remove stone, roots, grass, weeds, debris, and foreign material while spreading. E. Leave stockpile area and site clean and raked, ready to receive landscaping. ' 3.08 COMPACTION ' A. All compaction efforts shall obtain the following percentages of maximum dry density in accordance with the Modified Proctor procedures. ' 1. Fill used between 0 and 3 feet below paved areas shall be compacted to a minimum of 98% of the Modified Proctor density. ' 2. Fill used below 3 feet under paved areas shall be compacted to a minimum of 98% of Modified Proctor density. ' 3. Compaction of all fill under building shall be compacted to 100% Modified Proctor Density. 1 02665 ' 4. All other areas shall be compacted to 95% of Modified Proctor density. ' B. Proof rolling will be required on the finished subgrade of all paved areas. Proof rolling shall consist of driving loaded a tandem axle dump truck or loaded large front end loader over subgrade. Proof roll shall be directed by the Geotechnical Engineer. Any deflection of two inches or greater shall be considered a failure. Subgrade will have to be corrected so that deflection is less than two inches. 3.09 TURF RESTORATION A. Seeding: 1. Seed mixture shall be Mn/DOT 60B. 2. The seeding shall not be done until the Engineer has inspected the area and approved the subgrade preparation and topsoil materials. 3. If so directed by the Engineer, the Contractor shall reseed at his cost any area on which the original seed has failed to grow, using the type of seed directed by the Engineer. 4. No fertilizer will be applied. 5. Type 1 mulch shall be applied to all seeded areas. 6. All seeding and mulching shall be done within 5 days after rough grading has been completed or as directed by regulatory agencies having jurisdiction. END OF SECTION 02665-7 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 SECTION 02720 STORM SEWER SYSTEM PART GENERAL 1.01 SECTION INCLUDES A. Storm drainage structures, piping, fittings, and accessories. B. Excavation for trenches and structures. C. Connection of roof drainage system from building to storm sewer system 1.02 RELATED SECTIONS A. Earthwork. B. Backfilling for Utilities. 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. B. Standard Utilities Specifications for Water -main and Service Line Installation and Sanitary Sewer and Storm Sewer Installation, 1999, City Engineers Association of Minnesota. 1.04 REGULATORY REQUIREMENTS A. Conform to federal, state, local rules and regulations, governing authorities and applicable building codes for materials and installation of the work of this Section. 1.05 SUBMITTALS A. Submit shop drawings for pipe and structures. PART 2 PRODUCTS 2.01 SEWER PIPE MATERIALS A. Precast Concrete pipe in accordance with ASTM C76 with bell and spigot joints and R4 confined rubber "O" ring gaskets. B. High Density Polyethylene Pipe (HDPE) shall be Dual-Wall.Corrugated Polyethylene 02720-1 0 Pipe and shall conform to the requirements of AASHTOM-294 and Design 18 of the AASHTO Standard Specifications for Highway Bridges for storm sewer pipe sizes ' 12-inch through 36-inch. Joints shall be water -tight. Pipe manufacture, water -tight joint testing, and installation shall conform to current Mn/DOT requirements and/or as indicated in the Plans, Specifications, and Special Provisions. 2.02 PRECAST CONCRETE MANHOLE AND CATCH BASIN SECTIONS ' A. Precast concrete riser sections and appurtenant units (grade rings, top and base slabs, special sections, etc.) used in the construction of manhole and catch basin structures shall conform with the requirements of ASTM C-478, subject to the following ' supplementary provisions: ' 1. The precast sections and appurtenant units shall conform to all requirements shown on the detailed drawings. 2. Joints of manholes riser sections shall be tongue and groove with rubber "O" ring joints. Sewer inlet and outlet pipes shall be joined to the manhole with a gasketed, flexible, watertight connection or any watertight connection ' arrangement that allows differential settlement of the pipe and manhole wall to take place. E n 11 L 3. Air -entrained concrete shall be used in the production of all units. Air content shall be maintained within the range of five to seven percent. 4. Lift holes will be permitted in precast manholes only for purposes of manhole placement. Upon placement of the structures, all lift holes shall be properly filled to a watertight condition. B. Metal Sewer Castings Metal castings for sewer structures such as manhole frames and covers, catch basin frames, grates, and curb boxes shall conform to the requirements of ASTM A-48 (Gray Iron Castings), subject to the following supplementary provisions: 1. Casting assemblies or dimensions, details, weights, and class shall be as indicated in the detailed drawings for the design designation specified. Unless otherwise specified, the castings shall be class 30 or better. 2. Lid -to -frame surface on round casting assemblies shall be machine milled to provide true bearing around the entire circumference. 02720-2 I C. Concrete Concrete for cast -in -place masonry construction shall be produced and furnished in accordance with the requirements of Mn/DOT Spec. 2461. The requirements for Grade B concrete shall be met unless otherwise specified on plans. Type 3 (air - entrained) concrete shall be furnished and used in all structures having weather exposure. 2.03 MANHOLE STEPS A. Manhole steps shall be provided for all catch basins and manholes greater than three feet in depth, including adjusting rings, as indicated in plan details. Manhole steps shall be placed in the manhole to allow easy access to the bottom of the structure. 2.04 RIPRAP A. Riprap shall be Class IV conforming to Mn/DOT Specification 3601. PART 3 EXECUTION 3.01 INSTALLATION A. Pipe: Mn/DOT Specification 2503 B. Structures: Mn/DOT Specification 2506 C. Riprap: Mn/DOT Specification 2511 END OF SECTION 02720-3 SECTION 02730 SANITARY SEWAGE SYSTEMS PART GENERAL 1.01 SECTION INCLUDES A. Sanitary drainage piping, fittings, and accessories B. Connection of building sanitary drainage system to sanitary sewer 1.02 RELATED SECTIONS A. Earthwork B. Backfilling for Utilities 1.03 REFERENCES A. Divisions II and III Minnesota Department of Transportation Standard Specifications for Construction, 2000 Edition and Supplemental Specifications thereto, except English units will be used and Method Measurement and Basis of Payment do not apply. B. Standard Utilities Specifications for Water Main and. Service Line Installation and Sanitary Sewer and Storm Sewer Installation, 1999 City Engineers Association of Minnesota. 1.04 REGULATORY REQUIREMENTS A. Conform to applicable federal, state and local regulations for materials and installation of the work of this section. 1.05 SUBMITTALS A. Submit shop drawings for concrete structures. PART PRODUCTS 2.01 SEWER PIPE MATERIAL A. Smooth walled polyvinyl chloride pipe and fittings shall conform with the requirements of ASTM D-3034 for the size, standard dimension ratio (SDR), and strength requirements indicated on the Plans, Specifications, and Special Provisions. 02730-1 LI r L The grade used shall be resistant to aggressive soils or corrosive substances in accordance with the requirements of ASTM D-543. 1. Unless otherwise specified, all pipe and fittings shall be SDR 35 and connections shall be push -on with elastomeric gasketed joints which are bonded to the inner wall of the gasket recess of the bell socket. B. Fittings: Same material as pipe, molded or formed to suit pipe size and end design, in required 'T', bends, elbows, cleanouts, reducers, traps, and other configurations required. ' PART 3 EXECUTION ' 3.01 INSTALLATION - PIPE A. Inspection and Handling 1. Proper and adequate implements, tools, and facilities satisfactory to the Architect shall be provided and used for the safe and convenient prosecution of the work. During the process of unloading, all pipe and accessories shall be inspected for damage. All damaged material shall be clearly marked and promptly removed from the site. All materials shall be handled carefully, as will prevent damage to ' protective coatings, linings, and joint fillings; preclude contamination of interior areas; and avoid jolting contact, dropping, or dumping. i 2. All work and materials are subject to tests by the Owner at such frequency as may be determined by the Engineer. Such tests shall be paid for by the Owner. ' 3. While suspended and before being lowered into laying position, each pipe section and appurtenant unit shall be inspected to detect damage or unsound conditions ' that may need corrective action or be cause for rejection. The Engineer shall be notified of any defects discovered and the Engineer will prescribe the required corrective actions or order rejection. ' 4. Immediately before placement, the joint surfaces of each pipe section and fitting shall be inspected for the presence of foreign matter, coating blisters, rough edges or projections, and any imperfections so detected shall be corrected by cleaning, ' trimming, or repair as needed. ' B. Pipe Laying Operations 1. Trench excavation and bedding preparations shall proceed ahead of pipe ' placement as will permit proper laying and joining of the units at the prescribed 1 02730-2 Igrade and alignment without unnecessary deviation or hindrance. ' 2. All foreign matter or dirt shall be removed from the inside of the pipe and fittings before they are lowered into position in the trench and they shall be kept clean by approved means during and after laying. The sewer materials shall be carefully ' lowered into laying position by the use of suitable restraining devices. Under no circumstances shall pipe be dropped into the trench. 3. At the time of pipe placement, the bedding conditions shall be such as to provide uniform and continuous support for the pipe between bell holes. Bell holes shall ' be excavated as necessary to make the joint connections, but they shall be no larger than would be adequate to support the pipe throughout its length. No pipe material shall be laid in water nor when the trench or bedding conditions are ' otherwise unsuitable or improper. 4. When placement or handling precautions prove inadequate, in the Engineer's opinion, suitable plugs or caps effectively closing the open ends of each pipe section shall be provided and installed before it is lowered into laying position, and they shall remain so covered until removal is necessary for connection of an ' adjoining unit. 5. Unless otherwise permitted by the Engineer, bell and spigot pipe shall be laid with the bell ends facing upgrade and the laying shall start on the downgrade end and proceed upgrade. As each length of bell and spigot pipe is placed in laying position, the spigot end shall be centered in the bell and the pipe forced home and ' brought to correct line and grade. The pipe shall be secured in place with approved backfill material, which shall be thoroughly compacted by tamping around the pipe to a height of at least 12 inches above the top with hand operated ' mechanical tamping devices or by hand. The joint areas shall remain exposed and precautions shall be taken to prevent the soil from entering the joint space, until the joint seal is effected. Backfill in the bell area shall be left loose. 6. Connection of pipe to existing lines or previously constructed manholes or catch ' basins shall be accomplished as shown in the Plans or as otherwise approved by the Engineer. Where necessary to make satisfactory closure or produce the required curvature, grade or alignment deflections at joints shall not exceed that ' which will assure tight joints and comply with any limitations recommended by the pipe manufacturer. ' 7. Entrance of foreign matter into pipeline openings shall be prevented at all times to the extent that suitable plugs or covering can be kept inplace over the openings without interfering with the installation operations. 02730-3 I n 8. A system of dewatering wells or points shall be installed and operated to maintain pipe trenches free of water wherever necessary or as directed by the Engineer to meet the intent of these specifications. Unless otherwise specified in the Plans and Specifications, such work shall be considered incidental with no additional compensation provided therefore. C. Connection and Assembly of Joints 1. Smooth wall and corrugated wall PVC pipe and fittings - assembled push -on gasketed joints shall pass performance tests as listed in ASTM D-3212. Solvent welds shall not be permitted. D. Manhole and Catch Basin Structures 1. Manholes, catch basins, and other special access structures shall be constructed at designated locations as required by the Plans and in accordance with any standard detail drawings or special design requirements given therefore. 2. Unless otherwise specified or approved, manholes and catch basins shall be constructed on a cast -in -place concrete base and the barrel riser sections, cone section and top adjusting rings shall all be of precast concrete. All units shall be properly fitted and sealed to form a completely watertight structure. Barrel and cone height shall be such as to permit placement of at least two and not more than six standard two-inch precast concrete adjusting rings immediately below the casting assembly which shall be set in a mortar bed. Each adjusting ring shall also be set in mortar. 3. Unless otherwise specified or approved, manholes and catch basins shall have an inside barrel diameter at the bottom of 48 inches minimum and the inside diameter at the top of the cone section and of all adjusting rings shall be of the same size and shape as the casting frame. casting assemblies shall be as specified ' in the plans. Catch basin grate elevation shall be adjusted as necessary to maintain the required dip below normal gutter grade. H 4. The concrete cast -in -place base shall be poured on undisturbed or firmly compacted foundation material which shall be trimmed to proper elevation. The bottom riser section shall be set in fresh concrete or mortar and all other riser section joints of the tongue and groove design shall be sealed with rubber gaskets. 5. Wherever special designs so require or permit, and as otherwise may be approved by the Engineer, the structure may be constructed with solid sewer brick or block units or with cast -in -place concrete constructed on top of a precast concrete base. 02730-4 I �I [l F', 17 A combination of cast -in -place concrete and brick or block mortar construction may be required where it is impossible to complete the construction with standard precast manhole sections. 6. All annular wall space surrounding the inplace sanitary sewer pipes shall be completely filled with mortar or concrete, and the inside bottom of each manhole and catch basin shall be shaped with fresh concrete to form free flow through invert troughs as directed. E. Sanitary Sewer Leakage Testing 1. All sanitary sewer lines, including service connections, shall be substantially watertight and shall be tested for excessive leakage upon completion and before connections are made to the service by others. Each test section of the sewer shall be subjected to exfiltration testing by the air test method as described below. The requirements set forth for maximum leakage shall be met as a condition for acceptance of the sewer section represented by the test. . F. Low Pressure Air Testing Upon completion of the sewer and before any house services are connected to the pipeline, after the line has been backfilled and cleaned, the Contractor shall furnish all equipment and personnel necessary to conduct a "pipeline acceptability test" using low pressure air. This test shall be performed for every section of pipe between two manholes. The pipeline shall be sealed with plug, such as manufactured by Cherne Industries, Inc., of Hopkins, Minnesota, whose sealing length is greater than the diameter of the pipe and constructed in such a nature that it will not require external blocking or bracing and maintain a seal against the line's test pressure. All wyes, tees, outlets or ends of lateral streets shall be suitably capped and braced to withstand the internal pressures. Such caps or plugs shall be easily removable. One plug shall be tapped for the air supply hose and the return air pressure hose. The air supply hose, connected from the compressor to the plug shall be a throttling valve, bleeding valve and shut off valve for control. The air pressure tap shall have a sensitive pressure gauge, 0 to 10 psi range, protected by a gauge cock and a pressure relief valve set at 10 psi. In performing the test, air is added slowly to the pipeline until pressure inside the pipeline reaches 4.0 psi. If air is added too rapidly the test accuracy will decrease because a change in temperature also has an effect on the change in pressure. When 02730-5 17 11 the air pressure inside the pipeline reaches 4.0 psig above external hydrostatic pressure the supply air is stopped. A time interval is allowed for the temperature difference to stabilize before the actual test is performed. If the air pressure drops below 3.5 psig during this time interval, more air will be supplied to the pipeline and throttled to maintain a pressure between 3.5 psig and 4.0. psig for a minimum of two minutes after which time the supply air will be shut off. The portion of line being tested shall be accepted if the portion under test does not lose air at a rate greater than 0.003 cfm per square foot in interval pipe at an average pressure of 3.0 psig greater than any back pressure exerted by groundwater that may be over the pipe at the time of test. The test shall be accomplished by determining the time in minutes for the pressure to decrease from 3.5 psig to 2.5 psig greater than the average groundwater that my be over the pipe. That time shall not be less than the time shown for the given diameter in the following table. Pine Diameter in Inches Minutes ' 4 1.9 6 2.8 8 3.8 ' 10 4.7 12 5.7 15 7.1 18 8.5 21 9.9 If the pipeline intersection fails to meet the requirements of the test, the Contractor shall, at his own expense, determine the source of leakage and then repair or replace all defective material and/or workmanship. In determining the pressure greater than the average groundwater, the groundwater height in feet above the pipeline must be measured. When the water elevation has been established the height in feet above the pipeline shall be divided by 2.31 and that pressure added to gauge pressure of test. 02730-6 A for height table converting water to gauge pressure is as follows: ' Added Pressure to be Groundwater Level Over Applied to Gauge Ton of Pipeline Pressure Readings ' 1 Foot 0.43 psig 2 Feet 0.86 psig 3 Feet 1.29 psig ' 4 Feet 1.72 psig 5 Feet 2.16 psig ' 6 Feet 7 Feet 2.59 psig 3.01 psig 8 Feet 3.44 psig ' 9 Feet 10 Feet 3.87 psig 4.30 psig Low pressure air testing shall be considered incidental to the sewer pipe installation unless a specific payment item appears on the bid proposal. G. DEFLECTION TESTING The Contractor shall perform deflection testing on all PVC sewer lines after backfill ' is complete and in place for a minimum of 30 days. The maximum allowable deflection shall be 5%. ' If the deflection test is to be run using a rigid ball or mandrel, it shall have a diameter equal to 95% of the pipe inside diameter. The test shall be performed without mechanical pulling devices. ' Deflection testing shall be considered incidental to the sewer pipe installation unless a specific payment item appears on the bid proposal. END OF SECTION 1 02730-7 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 APPENDIX "A" 1 1 1 1 1 1 1 INDEX WATERMAIN CONSTRUCTION REQUIREMENTS Page 1. DESCRIPTION 14 2. MATERIALS 14 A. Water Main 14 B. Fire Hydrants 16 C. Valves 17 D. Water Service Pipe and Appurtenances 18 E. Polyethylene Encasement Material 19 F. Steel Casing Pipe 19 G. Piling 20 H. Granular Materials 20 I. Insulation 21 3. CONSTRUCTION REQUIREMENTS 21 A. Maintenance 21 B. Work Limits 22 C. Establishing Line and Grade 23 D. Protection of Surface Structures 24 E. Interference of Underground Structures 24 F. Removal of Surface Improvements 25 G. Excavation and Trench Preparation 26 H. Installation of Pipe and Fittings 29 I. Polyethylene Encasement of Pipeline 34 J. Jack -Bore Steel Casing Pipe 34 K. Placement of Insulation 35 L. Water Service Installations 35 M. Setting Valves, Hydrants, Fittings and Special 38 N. Pipeline Backfilling Operations - 39 O. Restoration of Surface Improvements 39 P. Maintenance and Final Cleanup 40 SPEC-745.000 Index 3-i 745000m 4. TESTING 40 A. Disinfection of Water Mains 40 B. Hydrostatic Testing of Water Mains 44 C. Electrical Conductivity Test - Ductile Iron Water Main 46 D. Trace Wire Test - PVC Water Main 47 E. Operational Inspection 47 5. METHOD OF MEASUREMENT 48 A. Water Main 48 B. Valves 48 C. Hydrant with Valve 48 D. Fittings 48 E. Granular Material 50 F. Boring 50 G. Water Service Connection 50 H. Service Lines 50 I. Insulation 50 J. Raise Valve Box 50 6. BASIS OF PAYMENT 51 A. Water Main 51 B. Valves 51 C. Hydrant with Valve 51 D. Fittings 51 E. Granular Material 51 F. Boring 51 G. Water Service Connection 51 H. Service Lines 51 I. Insulation 52 J. Raise Valve Box 52 SPEC-745.000 Index 3-ii 745000M WATERMAIN CONSTRUCTION REQUIREMENTS 1. DESCRIPTION ■ This work shall consist of the construction of the water mains, hydrants, services and other appurtenances in accordance with the Plans and these General Requirements, except as ' modified by the Specific Requirements or the Special Provisions. All work shall comply with the requirements of the Minnesota Department of Health, the Minnesota Plumbing Code and all applicable codes and ordinances. All references to Mn/DOT specifications, other specifications, standards or designations ' such as ASTM, ANSI, AWWA, shall mean the latest published edition available on the date of advertisement for bids on the project. 1 All manufactured products shall conform in detail to such standard design drawings as may be referenced or furnished in the contract documents. The Owner may require advance approval of material suppliers, product design, or other unspecified details as deemed ' necessary to insure conformance to the contract documents: Where specific manufactured products are referenced it is to indicate a product preference of the Owner. Other manufactured products of an "equivalent" kind, type, and quality may be used if approved ' in writing by the Engineer. Product information, shop drawings or other information to describe the product shall be submitted to the Engineer in a timely manner such that their review does not delay the project. At the request of the Engineer, the Contractor shall submit in writing, a list of materials q g g, and suppliers for approval. ' 2. MATERIALS The materials used in this work shall be new, conforming with the requirements of the ' referenced specifications for class, kind, type, size and grade of material as specified below and other details indicated in the contract. ' A. Water Main PVC water main shall be used unless Ductile Iron water main has been approved by the Joint Powers Water Board Engineer. A. l Ductile Iron Pine: Ductile iron pipe for water mains shall be Class 52 for pipe less than 12 inches in diameter, Class 50 for pipe 12 inches or larger in diameter, and shall conform to the requirements of AWWA C151 (ANSI A21.51). ISPEC-745.000 3-1 745000m A. La Fitting : Fittings shall be Gray Iron or Ductile Iron, manufactured in the United States, having a minimum working pressure rating of 150 psi, and shall conform to the requirements of AWWA C110 (ANSI A21.10), Ductile -Iron and Gray -Iron Fittings or AWWA C153 (ANSI 21.53), Ductile -Iron Compact Fittings. A- Lb Lining and Coating: All pipe and fittings shall be furnished with cement mortar lining meeting the requirements of AWWA C104 (ANSI A21.4) for standard thickness lining. All interior and exterior surfaces of the pipe and fittings shall have a tar or bituminous seal coating at least one mil thick. Spotty or thin seal coating, or poor coating adhesion, shall be cause for rejection. A. Lc Joints: Pipe three inches and larger in diameter shall have push -on joints. Fittings shall have mechanical joints. The rubber gasket shall conform to AWWA C111 (ANSI A21.11). A. Ld Electrical Conductivity: Copper straps shall be welded or otherwise permanently affixed to each pipe or appurtenance to provide a positive means of conveying electricity from pipe or fitting, to pipe or fitting. Conductive pipe gaskets may be used on pipe to pipe connections if approved by the Engineer. Size and method of affixing strap shall be subject to the approval of the Engineer and shall be sufficient to meet or exceed the criteria for conductivity testing set forth in this specification. A.2 Polyvinyl Chloride Pipe: Polyvinyl chloride pipe (PVC) for water main shall conform to AWWA C 900 for pipe 4" through 12" -in diameter, and shall conform to AWWA C905 for pipe 14" or larger in diameter. All pipe 4" through 12" in diameter. shall have a minimum dimension ratio (DR) of 18 corresponding to a working pressure of 150 psi for PVC type 1120 pipe. All pipe 14" or larger in diameter shall have a minimum dimension ration (DR) of 25 corresponding -to a working pressure of 165 psi for PVC type 1120 pipe. A.2.a Fittings: Fittings shall be Gray Iron or Ductile Iron, manufactured in the United States, having a minimum working pressure rating of 150 psi, and shall conform to the requirements of AWWA C110 (ANSI A21.10), or AWWA C153 (ANSI 21.53) Ductile -Iron Compact Fittings. A.2.b aims: Joints in plastic pipe shall be bell -end elastomeric-gasket type. SPEC-745.000 3-2 745000m A.2.c Restraints: Restraints for C900 and C905 PVC pipe shall be Megalug Series 2000PV, Uni-Flange Series 1300, 1350, 1390 as may apply or equal. Restraints shall be manufactured in the United States. A.2.d Trace Wire: Trace wire shall be installed along the top of the pipe prior to backfilling. The wire shall be 12 gauge standard plastic type TW or THW. Inline compression butt splice with 3M cast kit shall be used when splicing of wire is required. Splicing shall not be more frequent than 1 per 250 feet of piping. Wire nut splices will not be allowed. At each appurtenance such as a valve box or hydrant, the wire shall be securely fastened to the metal box or hydrant on an approved stand-off (quick bolt) readily visible. Wiring shall be connected to the appurtenance in such a way that a low voltage circuit can be completed without excavation of the structure. B. Fire Hydrants Fire hydrants shall be a 5'/ -inch Medallion as manufactured by Clow Valve Company, or a Pacer Model WB 67-250 as manufactured by Waterous Company, and shall conform to AWWA C502. The hydrants shall be rated for high pressure use. Hydrants shall be furnished in conformance with the following supplementary requirements: B.1 Five -inch (nominal diameter) main valve opening of the type that opens against water pressure with a pentagonal operating nut with one -inch sides (nominal 1.5 inches from point of pentagon to opposite side), and opening counterclockwise (left). B.2 Barrels shall be one piece with a traffic safety flange above finished grade. There shall be approximately 17 -24 inches for the Clow Medallion and approximately 21244 inches for the Waterous Pacer hydrant, from the flange to the center of the nozzles, and wM each hydrant shall have a mechanical joint connection at the hub end for joining a 6 ductile iron branch pipe. B.3 Hydrant bury depth, measured from the top of the branch pipe connection to the finished ground line at the hydrant, shall be 8'-0" (According to Waterous definition of "Bury"; hydrants with a bury of 8'-6" shall be furnished). SPEC-745.000 3 - 3 745000M B.4 Hydrants shall have two outlet nozzles for 2-1/2 inch (I.D.) hose connection and one outlet nozzle for 4-1/2 inch (I.D.) pumper connection. Threads shall conform to NFPA No. 194 (ANSI B26) and shall be: hose connection - 7-1/2 threads per inch, 3.062" nominal outside diameter (National Standard Thread); pumper connection - 4 threads per inch, 5.750" nominal outside diameter (National Standard Thread). Nozzle caps shall be nut type with chain. B.5 Hydrant operating mechanisms shall be provided with "O" ring seals preventing entrance of moisture and shall be lubricated through an opening in the operating nut or bonnet. B.6 Drain holes shall be left open unless indicated otherwise, if so indicated the hydrant shall be tagged "Pump After Use". B.7 The Contractor shall provide the Owner with one hydrant wrench for every ten (10) hydrants supplied or portion thereof. Cost of the wrenches shall be incidental to the project. B.8 Every fire hydrant shall be supplied with a Hydra Finder five foot (5') location flag. C. Valves Six inch to twelve inch valves shall be resilient seated gate valves, larger than twelve inches shall be butterfly. Tapping tees shall have resilient seated gate valves. All valves shall be for buried service. C.1 Butterfly Valves: Butterfly valves shall be manufactured in the United States, and shall conform to the requirements of AWWA C504 and the following requirements: a. Working pressure rating of 150 psi minimum. b. Two inch square operating nut opening counterclockwise (left). C. Double "O" ring or split V type stem seal. d. Traveling nut type operator permanently. sealed and lubricated. e. Manufacturers: Dresser, Pratt, or equal. SPEC-745.000 3-4 745000m C.2 Gate Valves: Gate valves shall be manufactured in the United States and shall conform to AWWA C509 for Resilient Seated Valves, and shall comply with the following supplementary requirements: a. Working pressure rating of 200 psi for all sizes. b. Two inch square operating nut opening counterclockwise (left). C. Double "O" ring stem seal, one above and below the stem seal. d. Weather seal on bonnet cover. e. Non -rising stem. f. Mechanical joints. g. Manufacturers: American, Mueller, Kennedy, or equal. C.3 Valve Boxes: Valve boxes shall be 5-1/4" diameter shaft suitable for 7.5' of cover over the top of the water main. Boxes shall be cast iron screw type two piece boxes with the word "WATER" on the lid. Valve boxes shall be manufactured in the United States. Valve boxes shall be Tyler -- 6850 with 5-1/4" drop lid, or equal. a. Valve Box Extension Stem: Provide each gate valve with a teffiien stem of the s one- or two- piece shaft, adjustable extension stem. Extension stem shall be provided with a coupling for use with non -rising stem valves. Extension stem shall be supported at the upper end. Length of extension stem shall bring the top of the square wrench nut to within six to twelve inches from the top of the valve box lid. Non - rising extension stem shall be Mueller A-26441, or equal. Extension stem shall be manufactured by Mueller or approved equal. D. Water Service Pine and Appurtenances D.1 : Water service pipe with inside diameter larger than 2 inches shall conform to the requirements of Ductile Iron Pipe or Polyvinyl Chloride Pipe. Water service pipe 1 to 2 inches inside diameter shall be Type K, seamless copperwater tubing, soft annealed temper and conform to the requirements of ASTM B 88. ' SPEC-745.000 3-5 745000m D.2 Appurtenances: a. Corporation SW: For use with flared copper service pipe, and the inlet threaded with the standard AWWA taper thread. b. Curb St For use with flared copper service pipe both ends, inverted key, and Minneapolis pattern. C. Curb Box: Minneapolis pattern base, 78"-81" stationary rod, 12 inch box adjustment from 7' to 8, lid with pentagon plug, and 1-1/4" I.D. upper section. d. Service Saddle: Double strap bronze stainless steel type. Service saddle shall be Cascade Style CSC-2, Smith -Blair nylon coated Style 317.42-2-, Ford Style FS 303, or approved equal. e. Wrenches and Keys: The Contractor shall provide the Owner with one 3' curb box shutoff rod and pentagon key for every 20 curb boxes supplied or portion thereof, minimum of 3. Cost of keys shall be incidental to the project. f. Manufacturers: Service Manufacturer's Number Appurtenance Diamete Mueller McDonald Ford Corporation Stop 1" - 2" H-15000 4701 F-600 Curb Stop 1" - 2" Mark 11 Oriseal 6104 B22-333M-3/4" H-15154 B22444M-1 " B22-666M-1-1/2" B22-777M-2" Curb Box 1 " H-10300 5614 1-1/2" - 2" H-10300/H10344 5615 Shutoff Rod H-10321 305 Pentagon Key H-10325 304K SPEC-745.000 3-6 745000m E. Polyethylene Encasement Material Polyethylene encasement material shall conform to AWWA C105 Type A for tube type installation and 8 mil nominal film thickness. F. Steel Casing Pipe Steel casing pipe for jack -boring shall have a wall thickness of 0.375 inches for casing pipe up to 24 inch diameter, and a wall thickness of 0.500 inches for casing pipe 26 to 32 inches in diameter. G. PU ng Piling shall be constructed in accordance with the provisions 'of Mn/DOT Specification 2452. Piles for pipelines shall be Treated Timber, in accordance with Mn/DOT 3471. H. Granular Materials Granular materials furnished for foundation, bedding, encasement, backfill or other purposes as may be specified shall consist of any natural or synthetic mineral aggregate such as sand, gravel, crushed rock, crushed stone, or slag, that shall be so graded as to meet the gradation requirements specified herein for each particular use. H.1 Granular Material Gradation Classifications: Granular materials furnished for use in Foundation, Bedding, Encasement, or Backfill construction shall conform to the following requirements: Percent Passing Sieve Size Foundation* Bedding Encasement Backfill 3 Inch 2 Inch 100 1Inch 100 100 100 3/4 Inch 85-100 90-100 90-100 3/8Inch 30-60 50-90 50-90 No.4 0-10 35-80 35-80 35-100 No.10 20-65 20-65 20-100 No.40 0-35 0-35 0-35 No.200 0-10 0-10 0-10 * 3/4" to 1-1/2" material may be used in lieu of Foundation specified SPEC-745.000 3-7 745000rn I. H.2 Granular Material Use Desig an tion: Granular materials provided for Foundation, Bedding, Encasement, or Backfill use as required by the Contract, either as part of the pipe item work unit or as a BID item, shall be classified as to use in accordance with the following: Material Use Designation Zone Designatio Granular Foundation Placed below the bottom of pipe grade as replacement for unsuitable or unstable soils, to achieve better foundation support. Granular Bedding Placed below the pipe midpoint, prior to pipe installation, to facilitate proper shaping and achieve uniform pipe support. Granular Encasement Placed from pipe midpoint to one foot above the top of pipe, after pipe installation, for protection of the pipe and to assure proper filling of voids and thorough consolidation of backfill. Granular Backfill Placed below subgrade, if any, as the second stage of backfill, to minimize trench settlement and provide support for surface improvements. In each case above, unless otherwise indicated, the lower limits of any particular zone shall be the top surface of the next lower course as constructed. The upper limits of each zone are established to define variable needs for material gradation and compaction or void content, taking into consideration the sequence of construction and other conditions. The material use and zone designations described above shall not be construed to restrict the use of any particular material in other zones where the gradation requirements are met. Irwulatio Main insulation shall be extruded rigid board material having a maximum thermal conductivity of 0.23 BTU/hour/square foot/degree Fahrenheit/per inch thickness, at 40OF mean, a compressive strength of 35 psi minimum, and water absorption of 0.25 percent by volume maximum. Insulation shall be DOW Styrofoam HI-40, Minnesota Diversified Products Certiforam brand insulation or equal. Unless otherwise specified in the Plans, Specifications, and Specific Requirements, board dimensions shall measure 8 feet long, 4 feet wide, and 1-1/2 inches thick or greater. SPEC-745.000 3-8 745"m ��,ok 0 4 A. Maintenance Maintenance of the project site, and any other area affected by construction, shall be in accordance with Mn/DOT specifications including Sections: 1404 Maintenance of Traffic 1514 Maintenance During Construction 1515 Control of Haul Roads Appendix B Minnesota Manual on Uniform Traffic Control Devices Maintenance -of streets and any detours, by-passes, equipment, stockpile, or storage areas provided in conjunction with the project shall be required and shall be the responsibility of the Contractor. Said maintenance shall include but not be limited to keeping the streets free of obstacles, parked equipment, unused barricades, blading the traveled ways, controlling the dust in the construction area and on detours, and maintenance of all barricades and flashers. The Contractor shall keep the portions of the project being used by public traffic, whether it be through or local traffic, in such condition that the traffic will be adequately accommodated at all times. The Contractor shall provide and maintain temporary approaches, crossings, and intersections with trails, roads, streets, businesses, parking lots, residences, garages, farms, and other abutting property in acceptable condition. The Contractor shall maintain essential services during the course of the project. Essential services shall include emergency vehicles, buses, mail delivery, garbage collection, drainage and public utility services. The Contractor shall coordinate his work with all appropriate agencies and utility companies during construction. During construction it shall be the Contractor's responsibility to see that all existing drainage structures, ditches, gutters and utilities in the working area are kept clean. Gutters shall be cleaned and free of dirt and other materials at the end of each working day to ensure proper drainage. Bales, silt fence or other erosion control measures acceptable to the Engineer shall be used to prevent materials from washing into drainage ways or storm sewers. There shall be an inspection of the sanitary sewer, storm sewer and water main utilities prior to the start of construction. The Contractor shall notify the Engineer 24 hours in advance to aid in accomplishing this inspection. All deficiencies in these existing systems prior to beginning construction must be immediately brought to the attention of the Engineer. SPEC-745.000 3-9 745000m C. During construction, the Contractor shall maintain the streets and control dust as directed by the Engineer. Dust control shall be provided in the same manner to stockpiles of topsoil, dirt, or other materials throughout the period of construction. Payment for maintaining streets and controlling dust shall be incidental to this project and no separate payment made unless provided for on the BID. Work Limits The Owner has obtained permanent and temporary easements for all construction on private property, as shown on the plan sheets. The remaining construction is within the right-of-way of dedicated streets. The Contractor shall limit his operations to the street right-of-way or easement unless he makes a separate arrangement with the landowner for the use of additional land. B.1 Work on Existing Right -of -Ways: In the case of construction on a railroad, state or county highway right-of-way, a permit for such construction will be obtained by the Owner. The Contractor shall comply with all requirements specified by the permit with respect to limits,_ safety precautions, method of construction, etc., and shall furnish to the state or county highway department or the railroad the required supplemental bonds or insurance coverage's as stipulated in the permits without additional cost to the Owner. Establishing Line and Grade The primary line and grade will be established by the Engineer. Line and grade stakes will be set parallel to the proposed pipeline at an appropriate offset and interval as will serve the Contractor's operations wherever practical; at each change in line or grade; and as needed for pipeline appurtenances and service lines. The Contractor shall arrange his operations to avoid unri cessary interference with the establishment of the primary line and _grade stakes; and shall render whatever assistance may be required by the Engineer to accomplish the staking. The Contractor shall be responsible for preservation of the primary stakes and. shall bear the full cost of any restaking necessitated by his negligence. The Contractor shall be solely responsible for the correct transfer of the primary line and grade from the stakes to all working points and for construction of the work to the prescribed lines and grades. Unless otherwise specified in the Plans, Specifications, and Specific Requirements, all water main shall generally be placed with 7-1/2 feet of cover. However, a greater depth may be required to clear storm and sanitary sewers and sewer services, and no additional compensation shall be provided for such adjustments. SPEC-745.000 3 - 10 745000m II In certain locations where water main is in direct conflict with storm or sanitary ' sewer, the water main shall be constructed under the sewer. Where it is necessary to use vertical bends to avoid sewer mains, no extra compensation will be made for this construction with the exception of payment for fittings used. ' No deviation shall be made from the required line or grade except with the consent q g P of the Engineer. ' In areas of conflict between wa ter mains, house sewers, storm sewers, or sanitary sewers, a separation of at least 18 inches between the water main and the sewer shall be provided. When local conditions prevent a vertical separation as described, the following construction shall be used: 1. Sewers passing over or under water mains shall be constructed of material equal to water main standards of construction for a distance of at least 9 feet on either side of the water main. 2. Water main passing under sewers shall, in addition, be protected by 1 providing: a. Adequate structural support for the sewers to prevent excessive deflection of joints and settling on and breaking of the water mains; and b. That the length of water pipe be centered at the point of crossing so that the joints will be equidistant and as far as possible from the ' sewer. Watermains shall be laid at least 10 feet horizontally from any sanitary sewer, ' storm sewer or sewer manhole, whenever possible. When local conditions prevent a horizontal separation of 10 feet a water main may be laid closer to a storm or sanitary sewer provided that: ' 1. The bottom of the water main is at least 18 inches above the top of the ' sewer; 2. Where this vertical separation cannot be obtained, the sewer shall be constructed of materials and with joints that are equivalent to water main standards of construction and shall be pressure . tested to assure water- tightness prior to backfilling. SPEC-745.000 3 - 11 745000m M E. Protection of Surface Structure All surface structures and features located outside the excavation limits for underground installations, together with those within the construction areas which are indicated in the Plans as being saved, shall be properly protected against damage and shall not be disturbed or removed without approval of the Engineer. Within the construction limits, as required, the removal of improvements such as paving, curbing, walks, turf, etc., shall be subject to acceptable replacement after completion of underground work, with all expense of removal and replacement being borne by the Contractor unless separate compensation is specifically provided for in the Contract. Obstructions such as street signs, mailboxes, guard posts, culverts, and other items of prefabricated construction may be temporarily removed during construction provided essential service is maintained in a relocated setting as approved by the Engineer and nonessential items are properly stored - for the duration of construction. Upon completion of the underground work, all such items shall be replaced in their proper setting by and at the sole expense of the Contractor. In the event of damage to any surface improvements, either privately or publicly owned, the Contractor will be required to replace or repair _the damaged property to the satisfaction of the Engineer and by the Contractor at his expense. Interference of Underground Structures When any underground structure interferes with the planned placement of pipe or appurtenances and requires alterations in the work to eliminate the conflict or avoid endangering effects on either the existing or proposed facilities, the Contractor shall immediately notify the Engineer and the Owner of the affected structures. When any existing facilities are endangered by the Contractor's operations, he shall cease his operations at the site and take such precautions as may be necessary to protect the inplace structures until a decision is made as to how the conflict will be resolved. Without specific authorization from the utility owner, no essential utility service shall be disrupted, nor shall any change be made in either the existing structures or the planned installations to overcome the interference. Alterations to existing facilities will be allowed only when that service will not be curtailed unavoidably and then only when the encroachment or relocation will satisfy all applicable regulations and conditions. SPEC-745.000 3 - 12 745000m F. G. Wherever alterations are required as a result of unforeseen underground interference's not due to any fault or negligence of the Contractor, the Engineer will issue a written change order covering any additional or extra work involved and specifying the revised basis of payment, if any. Any alterations made strictly for the convenience of the Contractor shall be subject to prior approval and shall be at the Contractor's expense. No extra compensation will be allowed for delays caused by the interference of underground structures unless approved by the Engineer and included in a change order. Removal of Surface L=rovements Removal of surface improvements in connection with trench excavation shall be limited to actual needs for installation of the pipeline and appurtenances. Removal operations shall be coordinated effectively with the excavation and installation operations as will cause the least practical disruption of traffic or inconvenience to the public. Removed debris shall not be deposited at locations that will restrict access to fire hydrants, private driveways, or other essential service areas. Removal and final disposal of debris shall be accomplished as a single operation wherever possible and the debris shall be removed from the site before starting the excavating operations. Removal of concrete or bituminous structures shall be by methods producing clean-cut breakage that will preserve the remaining structure without damage. Concrete or bituminous paving shall be removed so when the trench is excavated there will be a six inch wide minimum undisturbed subgrade and aggregate base course lip. Removal equipment shall not be operated in a manner that will cause damage to the remaining or adjoining property. Where not removed to an existing joint, concrete structures shall be sawed along the break lines to a minimum depth of one-third of the structure depth. Any reusable materials or materials for recycling, such as asphalt, concrete, aggregate, sod or topsoil, shall be segregated from other waste materials and be stockpiled so as to maintain suitability and permit proper reuse. Excavating operations shall proceed only so far in advance of pipe laying as will satisfy the needs for construction of work and permit advance verification of unobstructed line and grade as planned. Where interference with existing structures is possible or in any way indicated, and where necessary to establish SPEC-745.000 3 - 13 745000m elevation or direction for connections to inplace structures, the excavating shall be done at those locations in advance of the main operation so actual conditions will be exposed in sufficient time to make adjustments without resorting to extra work or unnecessary delay. All installations shall be accomplished by open trench construction except where boring and jacking or tunnel construction methods shall be employed as specifically required by the Plans or approved by the Engineer. Surface structures must be properly supported and the backfill restored to the satisfaction of the Engineer. The excavation operations shall be conducted to carefully expose all inplace underground structures without damage. Wherever the excavation extends under or approaches close to an existing structure as to endanger it in any way, precautions and protective measures shall be taken as necessary to preserve the structure and provide temporary support. Hand methods of excavating shall be utilized to probe for and expose- such critical or hazardous installations as gas pipe and power or telephone cables. G.1 Classification and Disposition of Materials: All materials encountered in the excavations, with the exception of items classified for payment as structure removals, will be considered as Unclassified Excavation. Unclassified materials shall include muck, rubble, wood debris, boulder stone, masonry or concrete fragments less than one (1) cubic yard in volume, together with other miscellaneous matter that can be removed effectively with power operated excavators. Excavated materials will be classified for reuse as being either Suitable or Unsuitable for backfill or other specified use, subject to selective controls. All suitable materials shall be reserved for backfill to the extent needed, and any surplus remaining shall be utilized for other construction on -the project as may be specified or, ordered by the Engineer. To the extent practical, granular materials and topsoil shall •be segregated from other materials during the excavating and stockpiling operations so as to permit best use of the available materials at the time of backfilling. All excavated materials reserved for backfill or other use on the project shall be stored at locations approved by the Engineer that will cause a minimum of nuisance or inconvenience to public travel, adjacent properties, and other special interests. The material shall not be deposited so close to the edges of the excavations as would create hazardous conditions, nor shall any material be placed so as to block the access to emergency services. All materials considered unsuitable by the Engineer, for any use on the project, shall be immediately removed from the project and be disposed of as arranged for by the Contractor. SPEC-745.000 3 - 14 745000m 1 G.2 Excavation Limitations_ and Requirements: Trench excavating shall be to a depth that will permit preparation of the foundation, as specified, and installation of the pipeline and appurtenances at the prescribed line and grade except where alterations are specifically authorized. Trench widths shall be sufficient to permit the pipe to be laid and joined properly and the backfill to be placed and compacted as specified. Extra width shall be provided as necessary to permit convenient placement of sheeting and shoring and to accommodate placement of appurtenances. Excavations shall be extended below the bottom of structure grade as ' necessary to accommodate any required Granular Bedding material. When unstable foundation materials are encountered at the established grade, additional materials shall be removed as specified or ordered -by the Engineer to produce an acceptable foundation. All excavations below grade shall be to a minimum width equal to the outside pipe diameter plus two (2) ' feet. Where no other grade controls are indicated or established for the pipeline, the excavating and foundation preparations shall provide a minimum cover over the top of the pipe of 7.5 feet to the proposed final grade as indicated on the plans. Trench widths shall allow for at least six inches of clearance on each side of the joint hubs. The maximum allowable width of the trench at the top rof pipe level shall be the outside diameter of the pipe plus two (2) feet, subject to the considerations for alternate pipe loading set forth below. The width of the trench at the ground surface shall be held to a minimum to ' prevent unnecessary destruction of the surface structures while maintaining safe working conditions. The maximum allowable trench width at the level of the top of pipe may be exceeded only by approval of the Engineer, after consideration of pipe 1 strength and loading relationships. Any alternate proposals made by the Contractor shall be in writing, giving the pertinent soil weight data and proposed pipe strength alternate, and shall be made in a timely manner so as not to delay the project. Approval of alternate pipe designs shall be with the understanding that there will be no extra compensation will be allowed for any increase in material or construction costs. 1 - G.3 Sheeting and Bracing Excavations: All excavations shall be sheeted, shored, and braced as will meet all requirements of the applicable safety codes and regulations; comply with any specific requirements of the Contract; and prevent disturbance or settlement of adjacent surfaces, foundations, structures, utilities, and other properties. Any damages to the SPEC-745.000 3 - 15 745000m work under contract or to adjacent structures or property caused by settlement, water or earth pressures, slides, cave-ins, or other causes due to failure or lack of sheeting, shoring, or bracing or through negligence or fault of the Contractor in any manner shall be repaired by the Contractor at his expense and without delay. Where conditions warrant extreme care, the Contractor shall exercise special precautions to protect life or property. This may include the installation of sheet piling of the interlocking type or shall include other safety measures be taken as the Contractor deems necessary. The Contractor shall at all times be responsible for protection of life, property, and the work on the project. The Contractor shall assume full responsibility for proper and adequate placement of sheeting, shoring, and bracing, wherever and to such depths that soil stability may dictate the need for support to prevent displacement. Bracing shall be so arranged as to provide ample working space and so as not to place stress or strain on the inplace structures to any extent that may cause damage. Sheeting, shoring and bracing materials shall be removed only when and in such manner as will assure adequate protection of the inplace structures and prevent displacement of supported grounds. Sheeting and bracing shall be left in place only as required by the Contract. Otherwise, sheeting and bracing may be removed as the backfilling reaches the level of respective support. Wherever sheeting and bracing is left in place, the upper portions shall be cut and removed to an elevation of three (3) feet or more below the established surface grade or as the Engineer may direct. All costs of furnishing, placing and removing sheeting, shoring and bracing materials, including the value of materials left in place as required by the Contract, shall be included in the prices bid for pipe installation and will not be compensated for separately. When any sheeting, shoring, or bracing materials are left in place by written order of the Engineer, payment may be made for those materials as an extra work item, including waste material resulting from upper cut-off requirements. GA Preparation and Maintenance of Foundations: Foundation preparations shall be conducted to produce a stable foundation and provide continuous and uniform pipe bearing between bell holes. Where Class C bedding is specified, the initial excavating or backfilling operations shall produce a subgrade level slightly above finished grade to permit hand shaping to finished grade by trimming of high spots and without the need for filling of low spots to grade. SPEC-745.000 3 - 16 745000M In excavations made below grade to remove unstable materials, the backfilling to grade shall be made with Granular Foundation material. Placement of the backfill shall be in relatively uniform layers not exceeding eight (8) inches in loose thickness. Each layer of backfill shall be compacted thoroughly, by means of approved mechanical compaction equipment, to produce uniform pipe support throughout the full pipe length and facilitate proper shaping of the pipe bed. Where the foundation soil is found to consist of materials that the Engineer considers to be so unstable as to preclude removal and replacement to a reasonable depth to achieve solid support, a suitable foundation shall be constructed as the Engineer directs in the absence of special requirements therefore in the Contract. The Contractor shall be required to fiunish and drive piling and construct concrete or timber bearing supports or other work as provided for in an extra work order. Care shall be taken during final subgrade shaping to prevent any over -excavation. Should any low spots develop, they shall only be filled with Granular Foundation material, which shall be compacted thoroughly, without additional compensation provided to the Contractor. The finished subgrade shall be maintained free of water and shall not be disturbed during pipe lowering operations except as necessary to remove pipe slings. The discharge of trench dewatering pumps shall be directed to natural drainage channels or storm water drains in a manner which does not cause damage to private or public property. Any debris left by dewatering operations shall be cleaned up immediately by the Contractor. Draining trench water into sanitary sewers or combined sewers will not be permitted. The Contractor shall install and operate a dewatering system of wells or points to maintain pipe trenches free of water wherever necessary or as directed by the Engineer to meet the intent of these specifications. Unless otherwise specified in the Plans, Specifications, or Specific Requirements, such work shall be considered incidental with no additional compensation provided therefore. All costs of excavating below grade and placing foundation or bedding aggregates as required shall be included in the bid prices for pipe items to the extent that the need for such work is indicated in the Contract provisions and the BID does not provide for payment therefore under separate BID items. If examination by the Engineer reveals the need for placement of foundation aggregates was caused by the Contractor's manipulation of the soils in the presence of excessive moisture or lack of proper dewatering, the cost of the corrective measures shall be borne by the Contractor. SPEC-745.000 3 - 17 745000m H. Installation of Pipe and Fittings Inspection, handling, and all aspects of the installation of pipe, services, and appurtenances shall be in accordance with the applicable sections of the AWWA specifications, the manufacturer's recommendations, and as supplemented as follows. H.I Innspection and Handling: Proper and adequate implements, tools, and facilities shall be provided and used by the Contractor for the safe and convenient prosecution of the work. Unloading, distribution, and storage of pipe and appurtenant materials on the job site shall be at a location approved by the Engineer. All materials shall be handled carefully, as will prevent damage to protective coatings, linings, and joint fittings; preclude contamination of interior areas; and to avoid jolting contact, dropping or dumping. Before being lowered into laying position, the Contractor shall make a thorough visual inspection of each pipe section and appurtenant units to detect damage or unsound conditions that may need corrective action or be cause for rejection. Inspection procedure shall be as approved by the Engineer, with special methods being required as he deems necessary to check out suspected defects more definitely. The Contractor shall inform the Engineer of any defects discovered and the Engineer will prescribe the required corrective action or order rejection. Immediately before placement, the joint surfaces of each pipe section and fitting shall be inspected for the presence of foreign matter, coating blisters, rough edges or projections, and any imperfections so detected shall be corrected by cleaning, trimming, or repairs as needed. H.2 Pipe Laying r tions: Trench excavation and bedding preparations shall proceed ahead of pipe placement as will permit proper laying and joining of the units at the prescribed grade and alignment without unnecessary deviation or hindrance. All foreign matter or dirt shall be removed from the inside of the pipe and fittings before they are lowered into position in the trench and they shall be kept clean by approved means during and after laying. The watermain materials shall be carefully lowered into laying position by the use of suitable restraining devices. Under no circumstances shall the pipe be dropped into the trench. SPEC-745.000 3 - 18 745000m ii I At the time of pipe placement, the bedding conditions shall be such as to provide uniform and continuous support for the pipe between bell holes. Bell holes shall be excavated as necessary to make the joint connections, but they shall be no larger than would be adequate to support the pipe throughout its length. No pipe material shall be laid in water nor when the trench or bedding conditions are otherwise unsuitable or improper. ' When placement or handling precautions prove inadequate, in the Engineer's opinion, the Contractor shall provide and install suitable plugs or caps effectively closing the open ends of each pipe section before it is lowered into laying position, and they shall remain so covered until removal is necessary for connection of an adjoining unit. It shall be the sole responsibility of the Contractor for the removal of any debris found in the water main at any time during the project. As each length of bell and spigot pipe is placed in laying position, the spigot end shall be centered in the bell and the pipe forced home and brought to correct line and grade. The pipe shall be secured in place with approved backfill material, which shall be thoroughly compacted by tamping around the pipe. Connection of pipe to existing or previously constructed lines shall be accomplished as shown in the Plans or as otherwise approved by the Engineer. ' At all times when pipe laying is not in progress, including noon hour and ' overnight periods, all open ends of the. pipe line shall be closed by watertight plugs or other means approved by the Engineer. If water is present in the trench, the seals shall remain in place until the trench is 1 pumped completely dry. Unless otherwise noted in the Specific Requirements, Class B pipe bedding shall be used for PVC water main and Class C pipe bedding shall be used for Ductile Iron water main. I H.3 Ductile Iron Pipe Joi H.3.a Push -On Joints: The circular rubber gasket shall be flexed inward and inserted in the gasket recess,. of the bell socket. A thin film of approved gasket lubricant shall be applied to either the inside surface of the gasket or the outside surface of the spigot end. Care shall be taken to prevent introduction of contaminants. The joint shall be completed by forcing the spigot end to the bottom of the socket by the use of suitable prybar or jack type equipment. Spigot ends which do not have depth marks shall be marked before SPEC-745.000 3 - 19 745000m 1 assembly to insure full insertion. Field cut pipe shall be filled or ground at the spigot edge to resemble the manufacturer's fabricated detailing. The use of the bucket on the excavation equipment shall not be used to force pipe into socket. H.3.b Mechanical Joints: The last eight inches of the outside spigot surface and the inside bell surface of each pipe and appurtenance joint shall be painted with a soap solution, after being thoroughly cleaned. The cast iron gland shall then be slipped on the spigot end with the lip extension toward the socket or bell end. The rubber gasket shall be painted with soap solution and be placed on the spigot end with the thick edge toward the gland. An approved lubricant provided by the pipe manufacturer may be used in lieu of the soap solution. After the spigot end is inserted into the socket to full depth and centered, the gasket shall be pressed into place within the bell y' evenly around the entire joint. After the gland is positioned behind the gasket, all bolts shall be installed and the nuts tightened alternately to the specified torque, such as to produce equal pressure ' on all parts of the gland. Unless otherwise specified, the bolts shall be tightened in r' I accordance with AWWA C-600 by means of a suitable torque -limiting wrench within a foot-pound range of: , Pipe Size Bolt Size Torque Inch Inch ft�l ' 3 5/8 45-60 4-24 3A 75-90 30-36 1 100-120 , After tightening, all exposed. parts of the bolts and nuts shall be completely coated with an approved bituminous rust preventive coal tar material such as Koppers, Bitumastic Super Service Black or Tnemec 46-457 Tnemecol. HA Polyvinyl Chloride Pipe Joints: Jointing shall be in accordance with g AWWA Manual No. M23. H.5 Aligning and Fitting of Pipe: The cutting of pipe for inserting valves, fittings, or closure pieces shall be done in a neat and workmanlike manner without damage to the pipe and shall leave a smooth square -cut end. Pipe shall be cut with approved mechanical cutters. SPEC-745.000 3 - 20 745000m SPEC-745.000 Wherever it is necessary to deflect the pipe from a straight line either in the vertical or horizontal plane, to avoid obstructions, plumb stems, or produce a long radius curve when permitted, the amount of deflection allowed at each joint shall not exceed the allowable limits for maintaining satisfactory joint seal as given in AWWA C600 for mechanical joints and push -on joints, or as otherwise allowed by the pipe manufacturer. MECHANICAL JOINT Offset Radius Pipe Size Deflection Angle Inch Feet Inca Degrees 18' 20' 18' 20' 3-4 8-18 31 35 125 140 6 7-07 27 30 145 160 8-12 5-21 20 22 195 220 14-16 3-35 13.5 15 285 320 18-20 3-00 11 12 340 380 24-30 2-23 9 10 450 500 Offset Radius Pipe Size Deflection Angle Inch Feet nc Degrees 18' 20' 18' 20' 3-12 5 19 21 205 230 14 - 36 3 11 12 340 380 H.6 Blocking and Anchoring of Pine: All plugs, caps, tees, bends, and other thrust points shall be provided with reaction backing, or movement shall be prevented by attachment of suitable restraining devices, in accordance with the requirements of the Plans, Specific Requirements and typical details. 'n the absen of other- a fied a ,..°,sent+ The following provisions In uav uv�aacv n= � shall apply for reaction blocking or restraining devices. Megalug type restraining devices shall be used unless other suitable restraining devices or reaction blocking have been approved by the Joint Powers Water Board Engineer. a. Megalug Series 1100 Retainer glands for ductile -iron watermain, Megalug Series 2000PV retainer glands for PVC watermain, or cast in place concrete blocking or rodding shall be used for joint restraint on all horizontal and vertical bends exceeding 20 degrees 3 - 21 745000m deflection, and all caps, plugs, branch tees, crosses, valves at the end of a line, all hydrant valves, and all hydrants. Restrained joints cast onto the pipe by the manufacturer (Lok-Tyton, Fastite, etc.) will be considered as being equivalent to the use of retainer glands. Retainer glands equivalent in function and form to the Megalug Series 1100 for ductile iron watermain or Megalug Series 2000PV for PVC watermain may be used only if it is approved by the Joint Powers Water Board Engineer. Plugged tees and crosses in a straight run do not require restraint. For restrained joints, the number of feet of tied pipe required shall be in accordance with the table below. FEET OF RESTRAINED OR TIED PIPE REQUIRED ON EACH SIDE OF THE BEND NOTE: (1) Table based on sand excavation, for silt increase 50% (2) If Polyethylene wrapping is used increase value by 100 % N.R. = Not Recommended 4' Cover 6' Cover 8' Cover Pipe Size Bend Sizes Bend Sizes Bend Sizes 221h- 45° 671i4° 1 90° 221k° 45° 671h° 90° 221k° 450 671fi° 900 3" N.R. N.R. N.R. N.R. I 3' 4' 8' 1' 2' 3' 4' 4" N.R. N.R. N.R. N.R. 2' 4' 5' 8' 1' 3' 4' 5' 6" N.R. N.R. N.R. N.R. 3' 6' 8' 9' 2' 4' 5' 6' 8" N.R. N.R. N.R. N.R. 4' 7' 9' 11' 3' 5' 7' 9' 12" N.R. N.R. N.R. N.R. 6' 10' 14' 17' 5' 8' 1 10' 12' 16" N.R. N.R. N.R. N.R. 7' 13' 18' 21' 6' 10' 14' 17' 20" 12' 22' 30' 37' 9' 15' 22' 27' T 12' 17' 20' 24" 14' 25' 37' 43' 10' 1 18' 26' 30' N.R. N.R. N.R. N.R. 30" 17' 30' 45' 52' 12' 21' 30' 37' N.R. N.R. N.R. N.R. 36" 19' 35' 50' 61' 14' 25' 35' 43' N.R. N.R. N.R. N.R. 42" 22' 1 39' 56' 69' 16' 28' 40' 49' N.R. N.R. N.R. N.R. 48" 24' 43' 63' 77' 18' 31' 45' 1 55' N.R. N.R. N.R. N.R. Table is from "Standards For The Installation Of Water Mains" St. Paul Water Utility. b. Offset bends made with standard offset fittings need not be strapped or buttressed. t C. Tie rods and tie harnesses shall be of the same size as the required , bolt, torqued to the requirements of Section H.3.b. After installing the tie rods and harnesses and prior to the backfill operations, they shall be coated with a brush applied tar coating. This coating i shall be Koppers Bitumastic Super Services Black or Tnemec 46-457 Tnemecol, or equal, and shall be applied to the manufacturer's specifications. Hot dipped galvanized parts need not be tar coated. i SPEC-745." 3-22 745"m ' I. All necessary fittings, bands, tie rods, nuts, and washers, and all labor and excavation required for installation of reaction restraints shall be furnished by the Contractor at his expense and without direct compensation. Hardwood blocking shall only be used as temporary reaction backing until acceptable permanent reaction blocking or restraining devices have been installed. Blocking shall be nominal 2-inch timber having an area equivalent to at least four times the area of the surface of the cap or plug it restrains. Concrete buttresses shall be poured against firm, undisturbed ground and shall be formed in such a way that the joints will be kept free of concrete and remain accessible for repairs. The concrete mix used in buttress construction shall meet the requirements for Grade B (3400 psi) of Mn/DOT 2461. _ Buttress dimensions shall be as indicated on the Plans or as approved by the Engineer. Contractors are instructed to size concrete buttress blocking on fittings and dead ends where the blocking must withstand the pressure of larger main line fittings equipped with reducers, for the larger sized main line thrust and not for smaller fitting size only. This is of particular importance on tees and crosses where the main size is reduced on the run from large to small size by use of reducers. Polyethylene Encasement of Pipeline Ductile iron pipe and/or valves, fittings, and appurtenances, shall be fully encased in polyethylene film of 8 mil nominal thickness. The filin shall be furnished in tube form for installation on pipe and all pipe -shaped appurtenances such as bends, reducers, offsets, etc. Sheet film shall be provided and used for encasing all odd -shaped appurtenances such as valves, tees, crosses, etc. Installation shall be in accordance with AWWA C105, Type A. Jack -Bore Steel Casing Pipe The Contractor shall jack -bore steel casing pipe in place as specified and as located on the Plans. In granular native soils, a 1-1/2" pipe shall be forced along the top of the casing pipe. The end of this 1-1/2" pipe shall be 18" back from the lead edge of the SPEC-745.000 3 - 23 745000M jacking pipe. Bentonite grout under pressure shall be forced through this pipe at all times during the jacking operation to fill any voids that might develop above the casing. The water pipe shall then be installed in the casing and the annular space between the water pipe and casing shall be densely filled with sand and the ends sealed with concrete or mortar. The Contractor shall be responsible for obtaining or paying any special permit fees for bonds, etc. required. K. Placement of Insulation Rigid insulation board shall be placed within the pipe .encasement zone, six (6) inches above the pipe. Prior to placement of the insulation, encasement material shall be compacted until there is no further visual evidence of increased consolidation or the density of the compacted layer conforms to the density requirements specified in the Specific Requirements, then leveled and lightly scarified to a depth of 1h inch. Encasement zone material placed below the insulation shall be free of rock or stone fragments measuring 1-1/2 inches or greater. Insulation boards shall be placed on the scarified material with the long dimension _ parallel to the centerline of the pipe. Boards placed in a single layer shall be overlapped at least 6 inches on all sides to eliminate continuous joints for the full depth of the insulation. If two or more layers of insulation boards are used, each layer shall be placed to cover the joints of the layer immediately below with an overlap of at least 6 inches. The Contractor shall exercise caution to insure that all joints between boards are tight during placement and backfilling with only extruded ends placed end to end or edge to edge. Broken or damaged material shall be removed and replaced. The first layer of material placed over the insulation shall be twelve (12) inches in depth, free of rock or stone fragments measuring 1-1/2 inches or greater. The material shall be placed in such a manner that construction equipment does not operate directly on the insulation and shall be compacted with equipment which exerts a contact pressure of less than 80 psi. The first layer shall be compacted until there is no further visual evidence of increased consolidation or the density of the compacted layer conforms to the density requirements specified. SPEC-745.000 3 - 24 745000m T , 1 L. Water Service Installations Water service lines complete with all required appurtenances, shall be installed in accordance with all pertinent requirements for main line installations and as supplemented as follows. It shall be the responsibility of the Contractor to keep an accurate record of the location, depth and size of each service connection and other pertinent data such as the location of curb stops and pipe endings. Tap locations shall be recorded in reference to survey line stationing. Curb boxes shall be tied to definable land marks such as building comers, fire hydrants, manholes and telephone pedestals. Pipe terminals at the property line shall be marked on the ground surface with a 2" i 4" x 8' wood post extending 3' above grade with the top 2' painted blue. Water service lines shall be installed in accordance with Minnesota Department of Health standards. Where water service lines are installed alongside of sanitary or storm sewer service lines, installation shall maintain the minimum specified clearances between pipelines and provide proper and adequate bearing for all pipes and appurtenances. For separate installation, the trench width shall be not less than two feet. Subject to minimum clearances, the water lines may be laid in a common trench excavated principally for sewer installation, either by widening the trench as necessary or by providing a shelf in the trench wall where ground stability will permit. Unless otherwise specified, installation of water service lines shall provide for not less than seven and one-half feet of cover over the top of the pipe and for not less than 18 inches of clearance between pipelines. Also, at least 6 inches of clearance shall be maintained in crossing over or under other structures. Where the service pipe may be exposed to freezing due to insufficient cover or exposure from other underground structures, the water pipe shall be insulated as directed by the Engineer. Service trenches shall be restored and compacted as specified for pipelines. L.I Tap Service Lines: Tap service piping shall be Seamless Copper Water Tube of the size and type specified. Pipe size for tap service installations shall be from 1 inch to 2-112 inch nominal inside diameter. Unless otherwise indicated, tap service piping may be .laid directly on any solid foundation soil that is relatively free of stones and hard lumps. Tap service piping shall be installed in one piece without intermediate joint couplings between the corporation stop at the water main tap and the curb stop. All pipe and appurtenances shall be joined by means of approved flared type threaded couplings. ' SPEC-745.000 3 - 25 745000m Connection of tap service lines to the water main shall be made with an approved corporation stop, with the water main tap being made from horizontal to an angle of not more than 15 degrees from the horizontal. (2:30 and 9:930 o'clock). Expansion loops shall be directed horizontally, not vertically from the tap. A minimum of 3 full threads of the corporation stop must engage in ductile iron water main or a saddle must be used for the connection (see chart below). All tap service lines to polyvinyl chloride water main shall have a saddle used with the connection. DUCTILE -IRON PIPE SADDLE REQUIREMENTS Class 52 Class 50 Pipe Size 4 ' 6 8 10 12 14 16 18 20 24 Inches Wall Thickness .29 .31 .33 .35 Inches .31 .33 .34 .35 .36 .38 Corp. Stop Pipe Thickness Required for 3 Corporation Stop Threads Inches Inches 1 .38 .34 .32 .31 .30 .29 .29 .28 .28 1-1/4 .45 .39 .36 .34 .33 .32 .31 .30 .30 1-1/2 .44 .40 .37 .35 .34 2 .48 .44 .41 .39 ABOVE LINE -W/O SADDLE BELOW LINE-W/SADDLE .33 .32 .32 .27 .30 31 .37 .36 (_ .35 .33 The flaring of copper tubing ends shall be accomplished only with the use of the proper size and type of tools as designated for the purpose, and will provide accurate sizing and rounding of the ends. Tubing shall be cut squarely and all edge roughness shall be removed prior to flaring. All couplings shall be tightened securely, so the flared end fits snugly against the bevel of the fitting without leakage. The flared joint couplings shall be made up without the use of jointing compounds. SPEC-745.000 3 - 26 745000M 1 Unless otherwise indicated, tap service lines shall be installed on a straight line at right angles to the water main or property line. The service line shall be terminated with a curb stop and box at the property line. The service pipe and curb stop coupling depth shall be such as to maintain not less than 7-1/2' minimum cover, or in locations where conflict may occur with storm sewer, service pipe shall be placed at least 3 feet below the storm sewer invert or shall be insulated in accordance with the Plans, Specifications, and Special Provisions to prevent freezing. In any case the Contractor shall make every effort to provide for a standard depth service ' box installation where practicable. The service box shall be screwed onto the curb stop coupling and be firmly supported on a concrete block. Service boxes shall be installed plumb and be braced effectively to remain vertical during and after completion of backfilling. The service boxes shall be brought to final surface grade when the final ground surface has been established. M. betting Valves. Hydrants, Fittin sg and S cia Valves, hydrants, fittings and specials shall be provided and installed as required ' by the plans and detail plates, and with each installation accomplished in accordance with the requirements for installation of mainline pipe to the extent applicable. Support blocking, thrust blocking, and anchorage devices shall be ' provided as required by the plans and detail plates. ' Hydrants shall be installed plumb, with the height and orientation of nozzles as shown on the detail plates. Hydrants shall be connected to the mainline pipe with a 6 inch diameter branch pipe, controlled by an independent valve. A concrete reaction block shall be installed between the hydrant shoe and undisturbed soil for ' all hydrants. Branch piping shall be restrained using Mega -Lug retainer glands unless another method of joint restraint has been previously approved. ' A drainage pit one-half cubic yard in volume shall be installed around the hydrant base and shall be filled with coarse gravel firmly compacted under and around the ' hydrant base and 6" above the drain outlet. The course -gravel shall be covered with at least two layers of tar paper or six (6)mil polyethylene prior to placing backfill thereon. Drain holes shall be normally left open when specified. ' Hydrants located where the groundwater table is above the drain outlet shall have _. the outlet plugged and shall be equipped with a tag stating, "Pump After Use". Hydrants shall be set so that the bottom of the traffic flange is 2 to 4 inches above finished grade. ' SPEC-745.000 3 - 27 745000m N. Valve boxes shall be centered over the wrench nut of the valve and be installed plumb, with the box cover flush with the surface of landscaped areas. In streets, valve boxes shall be set at 'fi inch below the finished surface of bituminous or concrete pavement or 6 inches below the surface of a gravel surfaced road. Valves installed below g-r-oundwatef shall have 6 mil polyethylene, 4' x 4', placed tightly over the valve prior to the box assembly to prevent corrosion and soil migration into the valve box assembly. Valve boxes shall not be installed so as to transmit shock or stress to the valve. Valve boxes installed outside the paved roadway shall have a 4"x4"x6' wood post installed, adjacent to the box, with two (2) feet above the ground surface. Post is not required when the valve box is installed with a hydrant. AW All valves finished er-ade shall incorporate a valve stem extension that places the operating nut at -7 6 to 8-fee8-feei 12 inches below finished grade. Special appurtenances shall be provided and installed as required by the Plans and Special Provisions. All dead ends shall be closed with approved plugs or caps and restrained by rodding or thrust blocking. If line size is reduced at the end of the line, restraints shall be sized for the line size prior to reduction. Install a 4"x4" wood post vertically from the pipe end invert to two (2) feet above the ground surface. Pipeline Backf lling Operations All pipeline excavations shall be backfllled to restore pre-existing conditions as the minimum requirement, and fulfill all supplementary requirements indicated in the Plans and Specifications. The backfilling operations shall be started as soon as conditions will permit on each section of pipeline, so as to provide continuity in subsequent operations and restore normal public service as soon aszpracticable on a section -by -section basis. All operations shall be pursued diligently, with proper and adequate equipment,, as will assure acceptable results. Backflling shall be accomplished with the use of Suitable Materials selected from the excavated materials to the extent available and practical. Suitable Material shall be defined as a mineral soil reasonably free of foreign materials (rubbish, debris, etc.), frozen clumps, organic matter, stone, rock, concrete, or bituminous chunks larger than 4", and other unsuitable materials that may damage the pipe installation or prevent thorough compaction, :taking into consideration particular needs of different backfill zones. Unsuitable material shall only be utilized where and to the extent there will be no detrimental effects and with the approval of the Engineer. SPEC-745.000 3 - 28 745000m M Backfill materials shall be carefully placed in relatively uniform depth layers spread over the full width and length of the trench section to provide simultaneous support on both sides of the pipeline. Each layer shall be compacted effectively, by approved mechanical methods before placing material for a succeeding layer thereon. Within the pipe bedding zone compaction shall be in a minimum of three lifts: invert to spring line, spring line to top of pipe, and top of pipe to 1.0 foot over top of pipe. Maximum thickness of any lift shall be eight (8) inches compacted thickness. Compaction requirements are: 95 % Standard Proctor maximum dry density from the pipe zone to within 3 feet of the ground surface, and 100 % Standard Proctor maximum dry density in the final 3 feet. All surplus or waste materials remaining after completion of the backfilling operations shall be disposed of in an acceptable manner after completing the backfill work. Disposal at any location within the project limits shall be as specified, or as approved in writing by the Engineer; otherwise, disposal shall be accomplished outside the project limits at the Contractor's own dump site. Restoration of Surface Improvements Wherever any surface improvements such as pavement, curbing, pedestrian walks, fencing or turf have been removed, damaged or otherwise disturbed by the Contractor's operations, they shall be repaired or replaced in kind and structure to the pre-existing condition or better. Each item of restoration work shall be done as soon as practical after completion of installation and backfilling operations on each section of pipeline. In the absence of specific payment provisions, as separate BID items, the restoration work shall be compensated as part of the work required under those BID items which necessitated the destruction and replacement of repair, and there will be no separate payment therefore. If separate pay items are provided for restoration work, only that portion of the repair or reconstruction which was necessitated by the Contract work will be measured for payment. Any improvements removed or damaged unnecessarily shall be replaced or repaired by the Contractor at his expense. A proper foundation shall be prepared before reconstructing concrete or bituminous improvements. Unless otherwise directed, granular material shall be placed to a depth of at least four (4) inches under all concrete and bituminous items. No direct compensation will be made for furnishing and placing this material even though such course was not part of the original construction. SPEC-745.000 3 - 29 745000M Existing concrete and bituminous surfaces at the trench wall shall be sawed or cut with a cutting wheel to form a neat edge in a straight line before surfaces are to be restored. Sawing or cutting may be accomplished as a part of the removal or prior to restoration at the option of the Contractor. However, all surface edges shall be inspected prior to restoration. P. Maintenance and Final Cleanup All subgrade surfaces shall be maintained acceptably until the start of surface construction or restoration work. Additional materials shall be provided and placed as needed to compensate for trench settlement and to serve until completion of the final surface improvements. Final disposal of debris, waste materials, and other remains or consequences of construction, shall be accomplished prior to final acceptance of all work. Final acceptance of each BID item can only be made when the cleanup associated with each item is completed. The Engineer may withhold partial payments until such work is satisfactorily pursued or he may deduct the estimated cost of its performance from the partial estimate value. 4. TESTING A. Disinfection of Water Mains Before being placed in service, the completed water main installation shall be disinfected and flushed, and after the final flushing the water shall be tested for bacteriologic quality and found to meet the standards prescribed by the Minnesota Department of Health. The disinfection materials and procedures and the collection and testing of water samples shall at a minimum be in accordance with the provisions of AWWA C651, Disinfecting Water Mains, and as will meet the requirements of the Minnesota Department of Health. Where an existing water main is cut for the installation of a hydrant, for lowering the water main, or for reasons determined by the Engineer, the pipe and fittings proposed to be installed shall be disinfected prior to installation as follows: 1. The interior of the pipe and fittings shall be cleaned of all dirt and foreign material. 2. The interior of the pipe and fittings shall be thoroughly swabbed or sprayed with a 1 percent minimum hypochlorite solution. SPEC-745.000 3 - 30 745000m 11 Unless otherwise indicated in the Plans, Specifications, and Specific Requirements, the Contractor shall furnish all materials and perform the disinfecting, flushing, and testing as necessary for meeting the water quality requirements. The AWWA C651 provisions for disinfection of water mains are reproduced for informational purposes as follows: A.1 Tablet Method Tablet Method may Y be used only when scrupulous cleanliness has been practiced to exclude all foreign materials and ground water during pipe ' installation. If ground water has entered pipe during pipe installation, the water main shall be flushed and the Chlorine -Water solution method shall be used. Placing Calcium Hypochlorite Granules During construction, calcium hypochlorite granules shall be placed at the upstream end of the first section of pipe, at the upstream end of each ' branch main, and at 500 foot intervals along the main. The quantity of granules shall be in accordance with the following table: ' Ounces of Calcium Hypochlorite Granules to be placed at beginning of main and at each 500 foot interval: Pipe Dia. (in.Calcium Hypochlorite Granules (oz.) 4 0.5 6 1.0 8 2.0 ' 10 3.0 12 4.0 16 and larger 8.0 Placing Calcium Hvuochlorite Tablets 1 Attach tablets on the top of the main using an adhesive such as Permatex No. 1, product of Loctite Corp, or equal. If tablets are not attach to the top ' and water contacts them they will react prior to the disinfection period. The table below gives tablets required per pipe size and length to achieve ' 25 mg/l. 0 I SPEC-745.000 3 - 31 745000M Number of 5-g Hypochlorite Tablets Required for Dose of 25 mg/1 Pipe Length of Pipe, feet Diameter nch 13 or less 18 20 30 40 4 1 1 1 1 1 6 1 1 1 2 2 _ 8 1 2 2 3 4 10 2 3 3 4 5 12 3 4 4 6 7 16 4 6 7 10 13 Number of 5-g tablets = .0012 d2L d = pipe diameter, inches L = pipe length, feet Based on 3.25 grams (65 %) available chlorine per tablet The main shall be filled with water at a rate no greater than 1 fps. Precautions shall be taken to assure that air pockets are eliminated. The use of additional curb stops to bleed air through at high points may be necessary. Chlorination Residual of 25 mg/L chlorinated water shall be retained in the pipe for a minimum of 24 hours, 48 hours when the water temperature is below 41oF. Valves and hydrants shall be operated to ensure disinfection. A.2 Continuous Feed Method Continuous feed method consists of.completely filling the main, removing all air pockets, flushing to remove particulates, then filling the main with potable water chlorinated so that after a 24 hour holding period in the main there will be a free chlorine residual of not less than 10 mg/L. Flushing velocity shall not be less than 2.5 fps, see table below. SPEC-745.000 3 - 32 745000m 1 1 1 1 1 1 Required Flow and Openings to Flush Pipelines* (40 psi Residual Pressure in Water Mainl Flow Required Size of Hydrant Outlets Pipe to Produce 2.5 fps Tap on Diameter Velocity in Main Main** Numbe Size N 4 100 15/16 1 2-1/2 6 220 1-3/8 1 2-1/2 8 390 1-7/8 1 2-1/2 10 610 2-5/16 1 2-1/2 12 880 2-13/16 1 2-1/2 16 1565 3-5/8 2 2-1/2 * With a 40-psi pressure in the main with the hydrant flowing to atmosphere, a 2-1/2-in. hydrant outlet will discharge approximately 1000 gpm and a 4-1/2-in. hydrant nozzle will discharge approximately 2500 gpm. ** Size of tap on main, with no significant length of discharge piping. Water from the existing system or other approved source shall be made to flow at a constant measured rate in the new main. At a point not much more than 10 feet downstream from beginning the new main, water entering the new main shall receive a dose of chlorine fed at a constant rate such that the water will have not less than 25 mg/L free chlorine. Measure the chlorine concentration at regular intervals in accordance with Standard Methods, AWWA M12, or using appropriate chlorine test kits. The following Table gives the amount of chlorine required for various pipes: Chlorine Required to Produce 25 mg/L Concentration in 100 ft of Pine - by Diameter Pipe 100 1 percent Diameter Chlorine Chlorine Solutions Inch lb. 11L 4 .013 0.16 6 .030 0.36 8 .054 0.65 10 .085 1.02 12 .120 1.44 16 .217 2.60 1 % chlorine solution requires 1 lb. of calcium hypochlorite in 8 gallons of water. SPEC-745.000 3 - 33 745000m 7 Strong' chlorine solution ui the main being treated shall not flow into mains in service. The chlorinated water shall be retained in the main for at least 24 hours, during which time all valves and hydrants shall be operated in I order to disinfect the appurtenances. At the end of the 24 hour period the treated water in all portions of the main shall have a residual of not less ' 1 than 10 mg/L free chlorine. Preferred equipment for applying liquid chlorine is a solution feed vacuum operated chlorinator in combination with a booster pump for injecting the chlorine gas solution water into the main to be disinfected. f A.3 ' Flushing After the applicable retention period, heavily chlorinated water shall not remain in prolonged contact with the pipe. Chlorinated water shall be flushed from the main until chlorine concentration is no higher than generally in the system for domestic use. The environment to which the chlorinated water is to be discharged shall ' be inspected. The Contractor shall be responsible to ensure that the receiving area is not damaged by the chlorinated water and shall use a reducing agent for neutralization when necessary.' A.4 Bacteriological Test After final flushing and before the water main is placed in service, samples of water shall be collected from the end of the main and each branch line for testing for bacteriological quality in accordance with Standard Methods, for the Examination of Water and Wastewater, and shall show the absence of coliform organisms. Samples shall be at a rate of one per every 1000 Ak feet of pipe. If water in the pipe does not meet the Minnesota Department ' of Health requirements, disinfection procedure shall be repeated until meeting the requirements. Acceptance forms from the governing agency , shall be furnished to the Engineer. B. Hydrostatic Testing of Water Main 1 Each valved section shall be subjected to the pressure test and, if required, the leakage test prescribed herein. Testing for the two (2) hour duration shall be with , hydrants closed, and valves on hydrant leads and dead end water lines open. Once this portion of the test is completed, the valve on the hydrant leads and dead end water lines shall be closed and hydrants opened. The specified test pressure shall ' be applied, and the test repeated for 15 minutes to establish the condition of the hydrant lead valves. I SPEC-745.000 3-34 745000m ' This shall apply to both the pressure and leakage test. The Engineer or Owner may require the Contractor to test the first section of pipe installed to demonstrate the Contractors ability to install the pipe in an acceptable manner. When the connection to the existing system is not made with a valve, the Contractor shall test the existing section to the first available valve(s) to determine the condition of the existing system, or the Contractor may make provisions to test his work separately, prior to connection to the existing system, in a manner acceptable to the Engineer. The Contractor shall furnish the pump, pipe connections, gauges, and measuring equipment, and shall perform the testing in the presence of the Engineer. The pressure gauge for the test shall be an Ashcroft Model 1082 with 4-1/2 inch dial face at 1 psi increments. Where permanent air vents are not provided, the Contractor shall provide and install corporation cocks at the high points as needed for release of air as the line is filled with water. Where concrete reaction blocking is placed, the water main shall not be subjected to hydrostatic pressure until at least 5 days have elapsed after the concrete placement, with the exception that this period may be reduced to 2 days where high early strength concrete is used. At the option of the Engineer, the pressure and leakage tests may be conducted simultaneously. Any defective joints, pipe, fittings, valves, or hydrants, revealed during the testing or before final acceptance of the work shall be satisfactorily corrected and the tests shall be repeated until the specified requirements have been met. B.1 Pressure Test: The section being tested shall be slowly filled with water and the specified test pressure shall be applied after all air has been expelled from the pipe. A hydrostatic pressure of 150 pounds per square inch, gauge pressure, measured at the lowest point of elevation, shall be applied by means of a pump connected to the pipe in a satisfactory manner. The gauge pressure shall be checked after a minimum of two (2) hours. A pressure drop of 1 psi or less will be cause to accept the test section. Several attempts must be made to satisfy the Engineer the pressure test will not be successful. If the drop is more than 2 psi after these attempts, the Engineer may authorize the leakage test in writing for acceptance. Service Pipe may be tested at the time of the foregoing test, if installed, at the Contractor's option. However, testing of service pipes may be completed as a separate operation from main testing, and if so, the test pressure shall be 100 p.s.i. Service pipe testing, if done separately, shall be done with the corporation stop open. ' SPEC-745.000 3 - 35 745000m B.2 Deakage Test: After an unsatisfactory pressure test, and if authorized in writing by the Engineer a leakage test shall be performed on each valved section of water main to determine the quantity of water that must be supplied into the section to maintain a test pressure of 150 pounds per square inch, after the air in the pipeline has been expelled and the pipe has been filled with water. The water added shall be recorded to the nearest fluid ounce. After filling the pipe with water and expelling all air in the line, a pressure of 150 psi shall be applied in the same manner as prescribed for the pressure test, and sufficient water shall be measured and supplied into the pipe section to maintain the pressure for a test duration of two (2) hours. Each pipe section tested will be accepted if the leakage does not exceed the quantity determined by the formula as shown in the table below, based on an allowable leakage of 11.65 gpd/mile/nominal diameter inch at 150 psi. L = SD4P 133,200 L = Maximum permissible leakage in gallons per hour S = Length of pipe tested D = Nominal diameter of pipe in inches P = Average test pressure during the test, in pounds per square inch, gauge pressure. ALLOWABLE LEAKAGE PER 1000 FEET OF PIPE GALLONS PER HOUR Avg.Test Pressure Nominal Pipe Diameter - in. psi 4 . $ 10 12 14 :y 16 1$ 200 0.43 0.64 0.85 1.06 1.28 1.48 1.70 1.91 2.12 2.55 175 0.40 0.59 0.80 0.99 1.19 1.39 1.59 1.79 1.98 2.38 150 0.37 0.55 0.74 0.92 1.10 1.29 1.47 1.66 1.84 2.21 125 0.34 0.50 0.67 0.84 1.01 1.18 1.34 1.51 1.68 2.01 100 0.30 0.45 0.60 0.75 0.90 1.05 1.20 1.35 1.50 1.80 . 70 0.25 0.38 0.50 0.63 0.75 0.88 . 1.00 1.13 1.26 1.51 If the pipe section under test contains pipe of various diameters, the allowable leakage will be the sum of the computed leakage for each size. �j sPEc-745.000 3 - 36 745000m When requested, the Contractor shall furnish a written report of the results ' of leakage tests, which shall identify the specific test section, the average pressure, the duration of test, and the amount of leakage. ' C. Electrical Conductivity Test - Ductile Iron Watermain The Contractor shall perform a conductivity test within one week after completion of pressure testing of the main on all iron pipe water mains. The Engineer or owner may require the Contractor to test the first section of pipe installed to demonstrate the Contractors ability to install the pipe in an acceptable manner. When the connection to the existing system is not made with a valve, the Contractor shall test the existing section to the first available valve(s) to determine the condition of the existing system, or the Contractor may make provisions to test his work separately, prior to connection to the existing system, in a manner ' acceptable to the Engineer. The system (pipeline, valves, fittings and hydrants) shall be tested for electrical ' continuity and current capacity. The electrical test shall be made after the hydrostatic pressure test and while the line is at normal operating pressure. Backfilling shall have been completed. The line may be tested in sections of convenient length as approved by the Engineer. ' Direct current of 350 amperes plus or minus 10 %, shall be passed through the pipeline for 5 minutes. Current flow through the pipe shall be measured continuously on a suitable ammeter and shall remain steady without interruption or fluctuation throughout the 5-minute test period. Insufficient current or intermittent current or arcing, indicated by large fluctuation of the ammeter needle, shall be evidence of defective contact in the pipeline. The cause shall be isolated and corrected. Thereafter, the section in which the defective test occurred shall be retested as a unit and shall meet the requirements. ' Sources of D.C. for these tests may be motor generators, are welding machines, or other approved sources. All such equipment shall be furnished by the ' Contractor. ' Cables from the power source to the section of system under test should be of sufficient size to carry the test current without overheating or excessive voltage drop. Note: After the test, the hydrant shall be shut off and a cap loosened to allow hydrant drainage. Tighten cap after drainage. SPEC-745.000 3 - 37 745000m D. Trace Wire - PV Waterm ain ' The Contractor shall perform a conductivity test on all trace wire prior to acceptance of the watermain system. A low voltage circuit shall be completed with the use of a suitable voltage source and meter to ensure continuity of the trace wire. In the event that a closed clamp circuit cannot be completed, the cause shall be ' isolated and corrected. Thereafter, the section in which the defective test occurred shall be retested as a unit and shall meet the requirements. E. D-Mratio I Insmetion At the completion of the project and in the presence of the Engineer and the ' Contractor, representatives of the Owner shall operate all valves, hydrants, and water services to ascertain that the entire facility is in good working order; that all ' valve boxes are centered and valves are opened; that all hydrants operate and drain properly; that all curb boxes are plumb and centered; and that water is available at all curb stops. ' DUI / UI l; ul ►Y A. Watermain W ' atermam of each type and diameter shall be measured separately m linear feet. Measurements shall be made along the pipe centerline without deductions in length for fittings, valves and other specials. Lengths of branches shall be measured from y' the centers of connecting pipes to centers of valves or fittings. in the case of hydrant leads, the compensation length shall be from the center of the connecting main to the center of the valve. All length shall be measured in a .horizontal plane unless the grade of the pipe exceeds fifteen percent. B. Valves Valves of each kind and size shall be measured separately as complete units ' including the valve box setting. C. Hydrant With Valve. , Hydrant with valve shall be measured on a per unit basis. The unit includes ' hydrant, 6" valve and valve box, 6" pipe between valve and hydrant, crushed rock, and blocking or restraining devices and hydrant flag. SPEC-745.000 3 - 38 745000m ' D. Fittings Fittings shall be measured on a pound basis of standard weight of fittings as published in AWWA C110 excluding the weight of glands, gaskets, bolts or other accessories. If the Contractor chooses to use compact ductile iron fittings, AWWA C153, measurement compensation for material price and weight differences shall be per AWWA C110. The fitting weights for payment purposes are provided in the following table: DUCTILE -IRON & GRAY -IRON MECHANICAL -JOINT FITTINGS Weight in Pounds per AWWA C110 Bends 01-M ) 90 45 2- 2 11-1/4 Sleeves C= 4" 55 50 50 50 35 15 15 6" 85 75 75 75 45 25 25 8" 125 110 110 110 65 45 45 10" 180 155 160 160 85 60 65 12" 255 215 220 220 110 80 85 14" 340 270 275 275 165 130 120 16" 430 340 345 345 200 175 155 18" 545 420 430 430 240 225 220 20" 680 530 535 540 275 285 255 24" 1025 755 765 770 360 400 390 Reducers (MJ-MJ) X4 X6 X8 XQ X12 XX114. Xl X18 X20 6" 60 - - - - - - - - 8" 80 95 - - - - - - - 10" 105 115 135 - - - - - - 12" 135 150 165 190 - - - - - 14" - 190 210 230 255 - - - - 16" - 230 250 280 305 335 - - - 18" - - 295 325 350 380 415 - - 20" - - - 375 405 430 470 510 - 24" - - - - 550 575 615 660 705 SPEC-745.000 3 - 39 745000M Tees 611 8" 10" 12" 14" 16" 18" 20" 24" Crosses Lall _ Jl 6" 8" loft 1211 14" 16" 1811 20" 24" E. F. G. X4 115 165 235 315 X44 140 189 260 340 Y¢ M M M X14 X16 M X24 125 - 175 185 250 260 325 340 435 450 540 550 590 605 725 735 985 1000 —. 160 - 205 235 285 310 360 385 475 500 575 605 625 655 760 790 1025 1045 310 - - 390 410 - 465 540 585 570 590 710 620 640 755 755 775 795 1020 1030 1055 740 - - - 905 945 - - 945 1140 1185 - 1075 1400 1720 1815 X10 X12 X14 2U_6 M X24 380 - - 460 495 - 540 630 710 645 685 830 685 725 870 820 860 905 1085 1110 1155 895 - - 1060 1130 - - 1085 1330 1415 - 1200 1590 1965 2155 Granular Material Granular material used as specified shall be measured on a per ton basis. Weight slips shall be required. Boring Borings shall be measured in linear feet as specified on the plans or approved by the Engineer. The water main carrier pipe shall be measured under the water main item. Water Service Connection Water service connections shall be measured on a unit basis for each size and type. The connection shall include the corporation stop, tapping saddle where required, curb stop, and curb box. SPEC-745.000 3 - 40 745000M H. Service Lines Service lines shall be measured in lineal feet horizontally from the centerline of the water main to the end of the service line. Separate measurements shall be made for each size of service line required. I. Insulation Insulation shall be measured by the square foot for the specified thickness. J. Raise Valve Box Raising valve boxes for the final lift of bituminous paving shall be measured per each. 6. BASIS OF PA S�MENT A. Water Main Water main shall be paid for at the contract unit price per linear foot for each type and diameter. Payment for the excavation and backfilling of the trench shall be included in the payment for the water main and testing, as well as any required dewatering, sheeting or shoring for which separate payment is not provided. B. Valves Valves of each type and size shall be paid for at the unit contract price per each, including installation, valve box and adjustment of the valve box- C. Hvdrant with Valve Hydrant with valve shall be paid for at the unit contract price per each including installing hydrant, connecting piece of pipe (between valve and hydrant), valve, valve box, concrete base, coarse gravel and blocking, hydrant flag, and adjustment of the hydrant and auxiliary gate valve. D. Fittings Fittings shall be paid for at the unit contract price per pound including installation and blocking. SPEC-745.000 3 - 41 745000M E. Granular Material Granular material shall be paid for at the contract unit price per ton based on weight tickets collected at the project site. The price shall include all costs for delivery, placement and compaction. F. Borin Borings shall be paid for at the contract unit price per linear foot of boring for each type and size of casing pipe specified. The payment per linear foot shall include the payment for furnishing and installing the casing pipe. The water main carrier pipe shall be paid for under the appropriate bid item. G. Water Service Connec Water service connection shall be paid for at the contract unit price per each type and size including corporation stop, curb stop, curb box and tapping saddle where required. H. Service Lines Service lines shall be paid for at the contract unit price per linear foot for each type and size of service line installed. 1. Insulation Insulation shall be paid for at the contract unit price per square foot. J. Raise Valve Box Raising valve boxes shall be paid for at the contract unit price per each. Payment shall be compensation for all materials, equipment, and labor to raise the valve box to final grade for the final lift of bituminous paving. END OF CHAPTER 3 SPEC-745.000 3 - 42 745000m