2001-04-10 Draft Project ScheduleDRAFT PROJECT SCHEDULE — Concurrent with City Project Roden Property, Albertville, MN Darkenwald Real Estate RLK-Kuusisto, Ltd. Project No. 2001-239-M Date: April 10, 2001 PROJECT SCHEDULE ITEMS: City Proiect: City Council Authorize Preparation of Plans and Specifications May 7, 2001 SEH - Complete Construction Plans and Specifications for City Council June, 2001 Bidding Process July, 2001 Award Bid (City commits to Project) August 6, 2001 Start Construction August 15, 2001. Substantial Completion of Construction October 15, 2001 Roden Property Development: Development Agreement /Identify city participation/ negotiation items May 7-May 21, 2001 Coordination for Property Acquisition/ Transfer May — August 2001 Project Design (20+- acres): Coordinate with City Project for Infrastructure Design May 7-May 14, 2001 Complete Boundary Survey May 2001 Complete Topographic Survey . May 2001 Coordinate Geotechnical Investigation/ Borings May 14-21 Prepare Preliminary Plat/ Final Plat (With ROW for Public Road) May 7-21 Prepare Engineering and Wetland Plans for Site Plan: May 7-June 2 Preliminary Mass Grading, Erosion Control and Drainage Plans Wetland Engineering/ Mitigation Plans Finalize Preliminary Plat/ Final Plat and Submit to City June 6, 2001 Joint Staff Review at the City June 12, 2001 Planning Commission Public Hearing for Preliminary Plat/ Final Plat July 10, 2001 Wright County Review (Concurrent with City approval) July 10 —August 31 Prepare Final Construction Documents (ahead of Prelim Approval) July 10-31 Mass Grading, Erosion Control, Drainage and Wetland Plans Plan review and approval by City staff (contingent upon City Project) July 31-August 6 City Council Agenda for Preliminary Plat/ Final Plat/ Final Plans August 6, 2001 Performance Agreement/ Sureties Prepared by City and Signed by DRE Through August 8 City issues Permit for Grading and Site Improvements August 10, 2001 Construction- Mass Grading/ Erosion Control, Storm Pond,Wetlands August 10-31 Construction of Parcel Site Improvements Begin Sept, 2001 Complete Spring 2002 Possible Building Plan Development (by tenantsZ Preparation of Plans August 2001 Review by Building Department (assume a few weeks to review*) August/ Sept 2001 Issuance of Building Permit September 2001 Begin Construction of Buildings Sept/ Oct 2001