2001-04-10 Draft Project ScheduleDRAFT PROJECT SCHEDULE — Concurrent with City Project
Roden Property, Albertville, MN
Darkenwald Real Estate
RLK-Kuusisto, Ltd. Project No. 2001-239-M
Date: April 10, 2001
PROJECT SCHEDULE ITEMS:
City Proiect:
City Council Authorize Preparation of Plans and Specifications
May 7, 2001
SEH - Complete Construction Plans and Specifications for City Council
June, 2001
Bidding Process
July, 2001
Award Bid (City commits to Project)
August 6, 2001
Start Construction
August 15, 2001.
Substantial Completion of Construction
October 15, 2001
Roden Property Development:
Development Agreement /Identify city participation/ negotiation items May 7-May 21, 2001
Coordination for Property Acquisition/ Transfer May — August 2001
Project Design (20+- acres):
Coordinate with City Project for Infrastructure Design May 7-May 14, 2001
Complete Boundary Survey May 2001
Complete Topographic Survey . May 2001
Coordinate Geotechnical Investigation/ Borings May 14-21
Prepare Preliminary Plat/ Final Plat (With ROW for Public Road) May 7-21
Prepare Engineering and Wetland Plans for Site Plan: May 7-June 2
Preliminary Mass Grading, Erosion Control and Drainage
Plans
Wetland Engineering/ Mitigation Plans
Finalize Preliminary Plat/ Final Plat and Submit to City June 6, 2001
Joint Staff Review at the City June 12, 2001
Planning Commission Public Hearing for Preliminary Plat/ Final Plat July 10, 2001
Wright County Review (Concurrent with City approval) July 10 —August 31
Prepare Final Construction Documents (ahead of Prelim Approval) July 10-31
Mass Grading, Erosion Control, Drainage and Wetland Plans
Plan review and approval by City staff (contingent upon City Project) July 31-August 6
City Council Agenda for Preliminary Plat/ Final Plat/ Final Plans August 6, 2001
Performance Agreement/ Sureties Prepared by City and Signed by DRE Through August 8
City issues Permit for Grading and Site Improvements August 10, 2001
Construction- Mass Grading/ Erosion Control, Storm Pond,Wetlands August 10-31
Construction of Parcel Site Improvements Begin Sept, 2001
Complete Spring 2002
Possible Building Plan Development (by tenantsZ
Preparation of Plans August 2001
Review by Building Department (assume a few weeks to review*) August/ Sept 2001
Issuance of Building Permit September 2001
Begin Construction of Buildings Sept/ Oct 2001