SPECIFICATIONS FOR
CEDAR CREEK NORTH
GRADING IMPROVEMENT PROJECT
ALBERTVILLE, MINNESOTA
MEYER-ROHLIN, INC.
ENGINEERS AND LAND SURVEYORS
1111 HIGHWAY 25 NORTH
BUFFALO, MINNESOTA 55313
May 22, 1998
Project No. 98108
I hereby certify that this plan, specification,
or report was prepared by me, or under my direct
supervision and I am a duly Registered
Professional Engineer under the laws of the
State of Minnesota.
s~~
Scott A. Dahlke, Professional Engineer
Reg. No 24348
I
I
INSTRUCTIONS TO BIDDERS
I
In order for proposals to be entitled to consideration, they must be m accordance with the following
instructions:
I
A. GENERAL
All proposals shall be submitted on forms furnished by the Engineer. All information, lump sums and unit prices
requested shall be completely filled out by typewriter or in ink. All corporation bids shall bear the official seal of
the corporation. The bid shall be submitted on the unbound proposal forms.
I
I
I
A proposal may be withdrawn without prejudice to the bidder by written request prior to the hour of the letting.
Proposals so withdrawn may be re-submitted at any time prior to the time set for opening of proposals. The Owner
reserves the right to reject any or all proposals and to waive any informalities and irregularities in the bidding.
I
B. QUALIFICA nONS OF BIDDERS
All bidders shall submit information necessary to satisfy the Owner that the bidder is adequately prepared to fulfIll
the contract. Such information shall include past performance records, lists of available personnel, plants and
equipment, fInancial statements, or any other pertinent information.
I
C. PREP ARA nON OF PROPOSAL /
The bidder shall submit his proposal on the forms provided by the Engineer. The blank spaces on the proposal shall
be filled in correctly for every item for which a quantity is given, and the bidder shall state the prices for which he
proposes to do each item of work.
I
The bidder's proposal shall be signed correctly in ink. The signature acknowledges that the bidder is providing the
information required and has received all Addenda to the SpecifIcations.
I
I
D. SUBCONTRACTORS
The names and addresses of all subcontractors that the bidder intends to employ on the project shall be listed in the
spaces provided on the proposal form. No other subcontractors shall be used on the project without the written
approval of the Engineer.
I
I
I
I
I
I
1
I
.
.
.
F. PLANS AND SPECIFICATIONS
Copies of proposal forms, Plans and SpecifIcations, for use by contractors submitting a bid, may be obtained from
Meyer-Rohlin, Inc., 1111 Highway 25 North, Buffalo, MN 55313, on deposit of the sum of Thirty-fIve Dollars
($35.00). This deposit will not be refundable.
.
.
G. EXAMINATION OF SITE AND DOCUMENTS
Bidders shall satisfy themselves by a personal examination of the site as to all local conditions affecting the
performance of the Contract, such as the structure of the ground, the existence of surface and ground water,
availability of drainage, obstacles which may be encountered, means of approach to the site, and the manner of
delivery and handling of materials.
.
.
The bidder, in submitting his proposal, is deemed to accept all conditions as the same as are eventually found to
exist and to waive all claim for extra compensation arising from the encountering of unforeseen difficulties except as
the same are expressly provided for in either the SpecifIcations or the contract. Bidders shall also carefully examine
the Plans and read the SpecifIcations before submitting bids on the work to be done. If any bidder contemplating
submitting a bid for the proposed contract is in doubt as to the true meaning of any part of the Plans, SpecifIcations,
or other proposed contract documents, he may submit to the Engineer a written request for an interpretation
thereof. The clarifIcation of the proposed documents will be made only by an addendum duly issued. A copy of
such an addendum will be mailed, faxed, or delivered to each person receiving a copy of the Plans and SpecifIcations
or to such other prospective bidders as have requested that they be furnished with a copy of such an addendum.
.
.
All addenda issued to bidders prior to the date of receipt of proposals shall become a part of the contract documents,
and all proposals are to include the work therein described. Each proposal submitted shall list all addenda by
number which have been received prior to the time scheduled for receipt of proposals.
.
.
H. ADHERENCE TO SPECIFICATIONS
All work shall be done in strict accordance with the SpecifIcations and Plans and such addenda as may be issued
from time to time by the Engineer. Bidders shall be held strictly to the intent of the Plans and SpecifIcations.
.
.
1. RETECTION OF BIDS
The right is reserved to reject any or all bids or to accept such bid, as in the opinion of the Owner will be to the best
interests of the Owner. No bidder may withdraw his bid for at least thirty (30) days after the scheduled closing time
for the receipt of bids.
.
J. CONDITIONS IN BIDDER'S PROPOSAL
The bidder shall not stipulate in his proposal any conditions not provided for on the proposal form.
.
.
K. INTERPRETATION OF ESTIMATES
Bidders shall examine to their satisfaction the quantities of work to be done, as determined from the Plans and
SpecifIcations. The Engineer's estimate of quantities as shown on the proposal shall be used as a basis of calculation
upon which the award of contract will be made, but these quantities are not guaranteed to be accurate and are
furnished without any liability on the part of the Owner or Engineer. Bidders must rely on their own calculations
and shall be thoroughly familiar with the contract documents.
.
.
2
.
-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
PROPOSAL FORM
FOR
CEDAR CREEK NORTH
GRADING IMPROVEMENT PROJECT
ALBERTVILLE, MINNESOTA
Pilot Land Development Company
clo Meyer-Rohlin, Inc.
1111 Highway 25 North
Buffalo, MN 55313
The undersigned, as bidder, hereby proposes and, if this proposal is accepted, agrees to
furnish bonds as required and to enter into a contract with the Owner to furnish all mater-
ials, labor, skill, tools and equipment for the complete construction of streets and utilities,
including all accessories as called for by the Specifications herewith, as prepared by
Meyer-Rohlin, Inc., Engineers and Land Surveyors, 1111 Highway 25 North, Buffalo, MN,
55313, acting as and in these contract documents entitled as the Engineer for the
following estimated quantities and unit prices:
Bid A - Grading
Unit Total
No. Item Qty. Unit Price Price
1 Common Excavation 77,000 cy
1a Quantity range (77,000 - 100,000)
1b Quantity range (100,000 +)
2 Clearing & grubbing lump sum
3 Seed, mulch & disk anchor entire project 41.5 acre
4 Erosion control silt fence 2500 If
5 Wetland mitigation 0.30 acre
TOTAL BID "A" =
I
I
Subcontractors to be used in the work must be shown below.
Address
Address
If this proposal is accepted, the bidder agrees to commence work and to complete all work
according to the schedule in the special provisions.
.
.
This proposal is submitted after careful study of the plans and specifications and from a personal
knowledge of the conditions, both surface and subsoil, at the various sites, which knowledge was
obtained from the undersigned's own sources of information and not from any official or
employee of the Owner.
.
The undersigned does declare this proposal is made without improper connection with any
other person or persons making a proposal on this same contract and is in al respects fair and
without collusion or fraud and the undersigned does further declare that no person or persons
acting in any official capacity for the Owner is directly or indirectly interested in the proposal
herein or in the supplies or works to which it relates or in any portion of the profits thereof.
.
.
It is understood and agreed that this proposal cannot be withdrawn within thirty (30) days after
the opening of bids without the consent of the Owner and that the Owner has the right to
accept the lowest responsive-responsible bidder or reject any or all proposals.
.
.
ADDENDUM RECEIPT
The receipt of the following Addenda to the Specifications is acknowledged.
Addendum No._Date
Addendum No._Date
.
.
Legal Name of Person, Firm or Corporation
.
BY
.
ADDRESS
.
PHONE
.
.
2
.
1
.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONI'ENTS
~
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 6
1.01 Defined Terms ................................................... 00700 - 6
1.02 Terminology. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 8
ARTICLE 2 - PRELIMINARY MATTERS ': . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 9
2.01 Delivery of Bonds ................................................. 00700 - 9
2.02 Copies of Documents ............................................... 00700 - 9
2.03 Commencement of Contract Times; Notice to Proceed .......................... 00700 - 9
2.04 Starting the Work ................................................. 00700 - 9
2.05 Before Starting Construction .......................................... 00700 - 9
2.06 Preconstruction Conference ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 10
2.07 Initial Acceptance of Schedules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 10
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT, AMENDING, REUSE .................... 00700 - 10
3.01 Intent. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 10
3.02 Reference Standards .............................................. 00700 - 10
3.03 Reporting and Resolving Discrepancies. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 11
3.04 Amending and Supplementing Contract Documents ........................... 00700 - 11
3.05 Reuse of Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 11
ARTICLE 4 - AVAILABILITY OF LANDS; SUBSURFACE AND PHYSICAL CONDITIONS;
REFERENCE POINTS .............................................. 00700 - 11
4.01 Availability of Lands .............................................. 00700 - 11
4.02 Subsurface and Physical Conditions. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 12
4.03 Differing Subsurface or Physical Conditions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 12
4.04 Underground Facilities . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 13
4.05 Reference Points . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 13
4.06 Hazardous Environmental Condition at Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 14
ARTICLE 5 - BONDS AND INSURANCE . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 15
5.01 Performance, Payment, and Other Bonds ................................. 00700 - 15
5.02 Licensed Sureties and Insurers ........................................ 00700 - 15
5.03 Certificates of Insurance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00100 - 15
5.04 CONTRACI'OR's Liability Insurance .................................... 00700 - 15
5.05 OWNER's Liability Insurance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 16
5.06 Property Insurance ............................................... 00700 - 16
5.07 Waiver of Rights . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 11
5.08 Receipt and Application of Insurance Proceeds. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 18
5.09 Acceptance of Bonds and Insurance; Option to Replace ........................ 00700 - 18
5.10 Partial Utilization, AcJ.:71owledgment of Property Insurer. . . . . . . . . . . . . . . . . . . . . . . . 00700 - 18
ARTICLE 6 - CONTRACTOR'S RESPONSIBILITIES ................................... 00700 - 18
6.01 Supervision and Superintendence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 18
6.02 lAbor; Working Hours ............................................. 00700 - 19
6.03 Services, Materials, and Equipment. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 19
6.04 Progress Schedule .. . . . . . . . . . . . -. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 19
6.05 Substitutes and "Or-Equals" . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 19
6.06 Concerning Subcontractors, Suppliers, and Others. . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 20
6.07 Paten! Fees and Royalties ........................................... 00700 - 21
6.08 Permits. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00100 - 21
6.09 Laws and Regulations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 22
6.10 Taxes. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00100 - 22
6.11 Use of Site and Other Areas . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 22
6.12 Record Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .00700 - 22
6.13 Safety and Protection .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 23
6.14 Safety Representative .............................................. 00700 - 23
6.15 Hazard Communication Programs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00100 - 23
00700 - 3
6.16 Emergencies... . . . . . . . . . . . . . . . . . .: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 23
6.17 Shop Drawings and Samples. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 23
6.18 Continuing the Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 24
6.19 CONTRACTOR's General Warranty and Guarantee. . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 25
6.20 Indemnification. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 25
ARTICLE 7 - OTHER WORK ................................................... 00700 _ 26
7.01 Related Work at Site. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
7.02 Coordination. . . . . . . ,". . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
ARTICLE 8 - OWNER'S RESPONSIBILITIES ........................................ 00700 _ 26
8.01 Communications to Contractor ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
8.02 Replacement of ENGINEER . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
8.03 Furnish Data ................................................... 00700 _ 26
8.04 Pay Promptly When Due . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
8.05 Lands and Easements; Repons and Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 26
8.06 Insurance. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 27
8.07 Change Orders .. . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 27
8.08 Inspections, Tests, and Approvals ...................................... 00700 _ 27
8.09 Limitations on OWNER's Responsibilities ................................. 00700 _ 27
8.10 Undisclosed Hazardous Environmental Condition ............................ 00700 _ 27
8.11 Evidence of Financial Arrangements. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . 00700 _ 27
ARTICLE 9 - ENGINEER'S STATUS DURING CONSTRUCTION. . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 27
9.01 OWNER'S Representative. . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 27
9.02 Visits to Site. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 27
9.03 Project Representative ............................................. 00700 _ 27
9.04 Clarifications and Interpretations ...................................... 00700 _ 28
9.05 Authorized Variations in Work ........................................ 00700 _ 28
9.06 Rejecting Defective Work .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 28
9.07 Shop Drawings, Change Orders and Payments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 28
9.08 Determinationsfor Unit Price Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 28
9.09 Decisions on Requirements of Contract Documents and Acceptability of Work .......... 00700 - 28
9.10 Limitations on ENGINEER's Authority and Responsibilities . . . . . . . . . . . . . . . . . . . . . . 00700 _ 28
ARTICLE 10 - CHANGES IN THE WORK; CLAIMS ................................... 00700 _ 29
10.01 Authorized Changes in the Work ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 29
10.02 Unauthorized Changes in the Work ..................................... 00700 _ 29
10.03 Execution of Change Orders . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 29
10.04 Notification to Surety .............................................. 00700 _ 29
10.05 Claims and Disputes. . . . . . . . . . . . . . . . . . . . . -. . .. . . . . . . . . . . . . . . . . . . . . . . 00700 _ 30
ARTICLE 11 - COST OF THE WORK; CASH ALLOWANCES; UNIT PRICE WORK . . . . . . . . . . . . . . 00700 _ 30
11.01 Cost of the Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 30
11.02 Cash Allowances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 32
11.03 Unit Price Work ................................................. 00700 _ 32
ARTICLE 12 - CHANGE OF CONTRACT PRICE; CHANGE OF CONTRACT TIMES ............. 00700 _ 33
12.01 Change of Contract Price ........................................... 00700- 33
12.02 Change of Contract Times . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 33
12.03 Delays Beyond CONTRACTOR's Control ................................. 00700 - 33
12.04 Delays Within CONTRACTOR's Control. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 -34
12.05 Delays Beyond OWNER's and CONTRACTOR's Control. . . . . . . . . . . . . . . . . . . . . . . . 00700 - 34
12.06 Delay Damages . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 34
ARTICLE 13 - TESTS AND INSPECTIONS; CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 34
13.01 Notice of Defects ................................................ 00700 _ 34
13.02 Access to Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 34
13.03 Tests and Inspections .............................................. 00700 _ 34
13.04 Uncovering Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 _ 35
13.05 OWNER May Stop the Work. . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .00700 _ 35
13.06 Correction or Removal of Defective Work .............................. .. 00700 - 35
00700 - 4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
I
I
I
1
1
1
1
1
1
1
I
1-
13.07 Correction Period .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .: . . . . . . . . 00700 - 35
13.08 Acceptance of Defective Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 36
13.09 OWNER May Correct Defective Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 36
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND COMPLETION . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 36
14.01 Schedule of Values . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 36
14.02~ Progress Payments. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 37
14.03 CONTRACTOR's Warranty of Title ..................................... 00700 - 38
14.04 Substantial Completion .. >'. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 38
14.05 Panial Utilization ................................................ 00700 - 39
14.06 Final Inspection ................................................. 00700 - 39
14.07 Final Payment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 39
14.08 Final Completion Delayed . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 40
14.09 Waiver of Claims . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 40
ARTICLE 15 - SUSPENSION OF WORK AND TERMINATION ............................ 00700 - 40
15.01 OWNER May Suspend Work. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 40
15.02 OWNER May Terminatefor Cause. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 40
15.03 OWNER May Terminate For Convenience. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 41
15.04 CONTRACTOR May Stop Work or Terminate. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 41
ARTICLE 16 - DISPUTE RESOLUTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 41
16.01 Methods and Procedures. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 41
ARTICLE 17 - MISCELLANEOUS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 42
17.01 Giving Notice . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 42
17.02 Computation of Times . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 00700 - 42
17.03 Cumulative Remedies ........... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . 00700 - 42
17.04 Survival of Obligations ...... . . . . . . . . . . . . . . . . . . . . . . . . . . . '.' . . . . . . . . . . 00700 - 42
17.05 Controlling Law ................................................. 00700 - 42
00700 - 5
I
GENERAL CONDITIONS
1
ARTICLE 1 - DEFINITIONS AND TERMINOLOGY
1.01 Defined Terms
A. Wherever used in the Contract Documents and
printed with initial or all capital letters, the terms listed
below will have the meanings indicated which are applicable
to both the singular and plural thereof.
1. Addenda-~ Written or graphic instruments issued
prior to the opening of Bids which clarify, correct, or
change the Bidding Requirements or the Contract
Documents.
2. -A.greement-~ The written instrument which is
evidence of the agreement between OWNER and
CONTRACTOR covering the Work.
3. Applicationfor Payment-The form acceptable to
ENGINEER which is to be used by CONTRACTOR
during the course of the Work in requesting progress or
fInal payments and which is to be accompanied by such
supporting documentation as is required by the Contract
Documents .
4. Asbestos~-Any material that contains more than
one percent asbestos and is friable or is releasing asbestos
fIbers into the air above current action levels established
by the United States Occupational Safety and Health
Administration.
5. Bid--The offer or proposal of a bidder submitted
on the prescribed form setting forth the prices for the
Work to be performed.
6. Bidding Documents-- The Bidding Requirements
and . the proposed Contract Documents (including all
Addenda issued prior to receipt of Bids).
7. Bidding Requirements-The Advertisement or
Invitation to Bid, Instructions to Bidders, Bid security
form, if any, and the Bid form with any supplements.
8. Bonds--Performance and payment bonds and
other instruments of security.
9. Change Order--A document recommended by
ENGINEER which is signed by CONTRACTOR and
OWNER and authorizes an addition, deletion, or revision
in the Work or an adjustment in the Contract :Price or the
00700 - 6
Contract Times, issued on or after the Effective Date of
the Agreement.
I
10. Claim--A demand or assertion by OWNER or
CONTRACTOR seeking an adjustment of Contract Price
or Contract Times, or both, or other relief with respect to
the terms of the Contract. A demand for money or
services by a third party is not a Claim.
1
I
11. Contract-- The entire and integrated written
agreement between the OWNER and CONTRACTOR
concerning the Work. The Contract supersedes prior
negotiations, representations, or agreements, whether
written or oral.
I
I
12. Contract Documents-- The Contract Documents
establish the rights and obligations of the parties and
include the Agreement, Addenda (which pertain to the
Contract Documents), CONTRACTOR's Bid (including
documentation accompanying the Bid and any post Bid
documentation submitted prior to the Notice of Award)
when attached as an exhibit to the Agreement, the Notice
to Proceed, the Bonds, these General Conditions, the
Supplementary Conditions, the Specifications and the
Drawings as the same are more specifically identified in
the Agreement, together with all Written Amendments,
Change Orders, Work Change Directives, Field Orders,
and ENGINEER's written interpretations and
clarifIcations issued on or after the Effective Date of the
Agreement. Approved Shop Drawings and the reports
and drawings of subsurface and physical conditions are
not Contract Documents. Only printed or hard copies of
the items listed in this paragraph are Contract Documents.
Files in electronic media format of text, data, graphics,
and the like that may be furnished by OWNER to
CONTRACTOR are not Contract Documents.
1
I
1
I
1
1
1
13. Contract Price--The moneys payable by OWNER
to CONTRACTOR for completion of the Work in
accordance with the Contract Documents as stated in the
Agreement (subject to the provisions of paragraph 11.03
in the case of Unit :Price Work).
I
14. Contract Times--The number of days or the dates
stated in the Agreement to: (i) achieve Substantial
Completion; and (ii) complete the Work so that it is ready
for final payment as evidenced by ENGINEER's written
recommendation of final payment.
1
I
15. CONTRACTOR--The individual or entity with
whom OWNER has entered into.the Agreement.
I
I
1
1
1
1
1
1
I
1
1
I
1
I
1
1
1
I
I
1
I
16. Cost of the Work--See paragraph' 11.01.A for
defInition.
17 . Drawings-That part of the Contract Documents
prepared or approved by ENGINEER which graphically
shows the scope, extent, and character of the Work to be
performed by CONTRACTOR. Shop Drawings and
other CONTRACTOR submittals are not Drawings as so
defmed.
18. Effective Date of the Agreement-~The date
indicated in the Agreement on which it becomes effective,
but if no such date is indicated, it means the date on
which the Agreement is signed and delivered by the last
of the two parties to sign and deliver.
19. ENGINEER--The individual or entity named as
such in the Agreement.
20. ENGINEER's Consultant--An individual or entity
having a contract with ENGINEER to furnish services as
ENGINEER's independent professional associate or
consultant with respect to the Project and who is
identified as such in the Supplementary Conditions.
21. Field Order--A written order issued by ENGI-
NEER which requires minor changes in the Work but
which does not involve a change in the Contract Price or
the Contract Times.
22. General Requirements--Sections of Division I of
the SpecifIcations. The General Requirements pertain to
all sections of the SpecifIcations.
23. Hazardous Environmental Condition--The
presence at the Site of Asbestos, PCBs, Petroleum,
Hazardous Waste, or Radioactive Material in such
quantities or circumstances that may present a substantial
danger to persons or property exposed thereto in
connection with the Work.
24. Hazardous Waste-The term Hazardous Waste
shall have the meaning provided in Section 1004 of the
Solid Waste Disposal Act (42 USC Section 6903) as
amended from time to time.
25. Laws and Regulations; Laws or Regulations-Any
and all applicable laws, rules, regulations, ordinances,
codes, and orders of any and all governmental bodies,
agencies, authorities, and courts having jurisdiction.
26. Liens--Charges, security interests, or
encumbrances upon Project funds, real property, or
personal property.
00700 - 7
27. Milestone--A principal event specifIed in the
Contract Documents relating to an intermediate comple-
tion date or time prior to Substantial Completion of all the
Work.
28. Notice of Award--The written notice by OWNER
to the apparent successful bidder stating that upon timely
compliance by the apparent successful bidder with the
conditions precedent listed therein, OWNER will sign and
deliver the Agreement.
29. Notice to Proceed--A written notice given by
OWNER to CONTRACTOR fIxing the date on which the
Contract Times will commence to run and on which
CONTRACTOR shall start to perform the Work under
the Contract Documents.
30. OWNER-The individual, entity, public body, or
authority with whom CONTRACTOR has entered into
the Agreement and for whom the Work is to be
performed.
31. Partial Utilization--Use by OWNER of a substan-
tially completed part of the Work for the purpose for
which it is intended (or a related purpose) prior to
Substantial Completion of all the Work.
32. PCBs--Polychlorinated biphenyls.
33. Petroleum--Petroleum, including crude oil or any
fraction thereof which is liquid at standard conditions of
temperature and pressure (60 degrees Fahrenheit and 14.7
pounds per square inch absolute), such as oil, petroleum,
fuel oil, oil sludge, oil refuse, gasoline, kerosene, and oil
mixed with other non-Hazardous Waste and crude oils.
34. Project--The total construction of which the
Work to be performed under the Contract Documents
may be the whole, or a part as may be indicated
elsewhere in the Contract Documents.
35. Project Manual--The bound documentary
information prepared for bidding and constructing the
Work. A listing of the contents of the Project Manual,
which may be bound in one or more volumes, is
contained in the table(s) of contents.
36. Radioactive Material-Source, special nuclear, or
byproduct material as defmed by the Atomic Energy Act
of 1954 (42 USC Section 2011 et seq.) as amended from
time to time.
37. Resident Project Representative-- The authorized
. representative of ENGINEER who may be assigned to the
Site or any part thereof.
38. Samples--Physical examples of materials,
equipment, or workmanship that are representative of
some portion of the Work and which establish the
standards by which such portion of the Work will be
judged.
39. Shop Drawings--All drawings, diagrams, illustra-
tions, schedules, and other data or informjition which are
specifically prepared or assembled by or for CON-
TRACTOR and submitted by CONTRACTOR to
illustrate some portion of the Work.
40. Site--Lands or areas indicated in the Contract
Documents as being furnished by OWNER upon which
the Work is to be performed, including rights-of-way and
easements for access thereto, and such other lands
furnished by OWNER which are designated for the use of
CONTRACTOR.
41. ,Specifications-- That part of the Contract
Documents consisting of written technical descriptions of
materials, equipment, systems, standards, and
workmanship as applied to the Work and certain
administrative details applicable thereto.
42. Subcontractor--An individual or entity having a
direct contract with CONTRACTOR or with any other
Subcontractor for the performance of a part of the Work
at the Site.
43. Substantial Completion-- The time at which the
Work (or a specified part thereof) has progressed to the
point where, in the opinion of ENGINEER, the Work (or
a specified part thereof) is sufficiently complete, in
accordance with the Contract Documents, so that the
Work (or a specified part thereof) can be utilized for the
purposes for which it is intended. The terms
"substantially complete" and "substantially completed" as
applied to all or part of the Work refer to Substantial
Completion thereof.
44. Supplementary Conditions-- That part of the
Contract Documents which amends or supplements these
General Conditions.
45. Supplier--A manufacturer, fabricator, supplier,
distributor, materialman, or vendor having a direct
contract with CONTRACTOR or with any Subcontractor
to furnish materials or equipment to be incorporated in
the Work by CONTRACTOR or any Subcontractor.
46. Underground Facilities--AlI underground
pipelines, conduits, ducts, cables, wires, manholes,
vaults, tanks, tunnels, or other such facilities or
attachments, and any . encasements containing such
facilities, including those that convey electricity, gases,
00700 - 8
1
steam, liquid petroleum products, telephone or other
communications, cable television, water, wastewater,
storm water, other liquids or chemicals, or traffic or
other control systems.
I
I
47. Unit Price Work--Work to be paid for on the
basis of unit prices.
1
48. Work-- The entire completed construction or the
various separately identifiable parts thereof required to be
provided under the Contract Documents. Work includes
and is the result of performing or providing all labor,
services, and documentation necessary to produce such
construction, and furnishing, installing, and incorporating
all materials and equipment into such construction, all as
required by the Contract Documents.
1
I
1
49. Work Change Directive--A written statement to
CONTRACTOR issued on or after the Effective Date of
the Agreement and signed by OWNER and recommended
by ENGINEER ordering an addition, deletion, or revision
in the Work, or responding to differing or unforeseen
subsurface or physical conditions under which the Work
is to be performed or to emergencies. A Work Change
Directive will not change the Contract Price or the
Contract Times but is evidence that the parties expect that
the change ordered or documented by a _ Work Change
Directive will be incorporated in a subsequently issued
Change Order following negotiations by the parties as to
its effect, if any, on the Contract Price or Contract
Times.
I
I
I
1
.50. Written Amendment--A written statement
modifying the Contract Documents, signed by OWNER
and CONTRACTOR on or after the Effective Date of the
Agreement and normally dealing with the nonengineering
or nontechnical rather than strictly construction-related
aspects of the Contract Documents.
I
I
1
1.02 Terminology
A. Intent of Cenain Terms or Adjectives
1. Whenever in the Contract Documents the terms
"as allowed," "as approved," or terms of like effect or
import are used, or the adjectives "reasonable, "
"suitable," "acceptable," "proper," "satisfactory," or
adjectives of like effect or import are used to describe an
action or determination of ENGINEER as to the Work, it
is intended that such action or determination will be solely
to evaluate, in general, the completed Work for
compliance with the requirements of and information in
the Contract Documents and conformance with the design
concept of the completed Project as a. functioning whole
as shown or indicated in the Contract Documents (unless
there is a specific statement indicating otherwise). The
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
use of any sucn term or adjective shall not be effective to
assign to ENGINEER any duty or authority to supervise
or direct the performance of the Work or any duty or
authority to undertake responsibility contrary to the
provisions of paragraph 9.10 or any other provision of the
Contract Documents.
B. Day
1. The word "day" shall constitute a calendar day
of 24 hours measured fro~ midnight to the next midnight.
C. Defective
1. The word "defective," when modifying the word
"Work," refers to Work that is unsatisfactory, faulty, or
deficient in that it does not conform to the Contract
Documents or does not meet the requirements of any
inspection, reference standard, test, or approval referred
to in the Contract Documents, or has been damaged prior
to ENGINEER's recommendation of final payment
(unless responsibility for the protection thereof has been
assumed by OWNER at Substantial Completion in accor-
dance with paragraph 14.04 or 14.05).
D. Furnish, Install, Perform, Provide
1. The word "furnish," when used in connection
with services, materials, or equipment, shall mean to
supply and deliver said services, materials, or equipment
to the Site (or some other specified location) ready for use
or installation and in usable or operable condition.
2. The word "install," when used in connection
with services, materials, or equipment, shall mean to put
into use or place in fmal position said services, materials,
or equipment complete and ready for intended use.
3. The words "perform" or "provide," when used
in connection with services,/ materials, or equipment,
shall mean to furnish and install said services, materials,
or equipment. complete and ready for intended use.
4. When "furnish," "install," "perform," or "pro-
vide" is not used in connection with services, materials,
or equipment in a context clearly requiring an obligation
of CONTRACTOR, "provide" is implied.
E. Unless stated otherwise in the Contract Documents,
words or phrases which have a well-known technical or
construction industry or trade meaning are used in the
Contract Documents in accordance with such recognized
meaning.
ARTICLE 2 - PRELIMINARY MATTERS
2.01 Delivery of Bonds
A. When CONTRACTOR delivers the executed
Agreements to OWNER, CONTRACTOR shall also deliver
to OWNER such Bonds as CONTRACTOR may be required
to furnish.
2.02 Copies of Documents
A. OWNER shall furnish to CONTRACTOR up to ten
copies of the Contract Documents. Additional copies will be
furnished upon request at the cost of reproduction.
2.03 Commencement of Contract Times; Notice to Proceed
A. The Contract Times will commence to run on the
thirtieth day after the Effective Date of the Agreement or, if
a Notice to Proceed is given, on the day indicated in the
Notice to Proceed. A Notice to Proceed may be given at any
time within 30 days after the Effective Date of the
Agreement. In no event will the Contract Times commence
to run later than the sixtieth day after the day of Bid opening
or the thirtieth day after the Effective Date of the Agreement,
I whichever date is earlier.
2.04 Staning the Work
A. CONTRACTOR shall start to perfonn the Work on
the date when the Contract Times commence to run. No
Work shall be done at the Site prior to the date on which the
Contract Times commence to run.
2.05 Before Staning Construction
A. CONrRAcrOR's Review of Contract Documents:
Before undertaking each part of the Work, CONTRACTOR
shall carefully study and compare the Contract Documents
and check and verify peninent figures therein and all
applicable field measurements. CONTRACTOR shall
promptly report in writing to ENGINEER any conflict, error,
ambiguity, or discrepancy which CONTRACTOR may
discover and shall obtain a written interpretation or
clarification from ENGINEER before proceeding with any
Work affected thereby; however, CONTRACTOR shall not
be liable to OWNER or ENGINEER for failure to report any
conflict, error, ambiguity, or discrepancy in the Contract
Documents unless CONTRACTOR knew or reasonably
should have known thereof.
B. Preliminary Schedules: Within ten days after the
Effective Date of the Agreement (unless otherwise specified
00700 - 9
in the General Requirements), CONTRACTOR shall submit
to ENGINEER for its timely review:
1. a preliminary progress schedule indicating the
times (numbers of days or dates) for starting and
completing the various stages of the Work, including any
Milestones specified in the Contract Documents;
2. a preliminary 'schedule of Shop Drawing and
Sample submittals which will list each required submittal
and the times for submitting, reviewing, and processing
such submittal; and
3. a preliminary schedule of values for all of the
Work which includes quantities and prices of items which
when added together equal the Contract Price and subdi-
vides the Work into component parts in sufficient detail
to serve as the basis for progress payments during
performance of the Work. Such prices will include an
appropri,ate amount of overhead and profit applicable to
each item of Work.
C. Evidence of Insurance: Before any Work at the Site
is started, CONTRACTOR and OWNER shall each deliver
to the other, with copies to each additional insured identified
in the Supplementary Conditions, certificates of insurance
(and other evidence of insurance which either of them or any
additional insured may reasonably request) which
CONTRACTOR and OWNER respectively are required to
purchase and maintain in accordance with Article 5.
2.06 Preconstruction Conference
A. Within 20 days after the Contract Times start to run,
but before any Work at the Site is started, a conference
attended by CONTRACTOR, ENGINEER, and others as
appropriate will be held to establish a working understanding
among the parties as to the Work and to discuss the schedules
referred to in paragraph 2.05.B, procedures for handling
Shop Drawings and other submittals, processing Applications
for Payment, and maintaining required records.
2.07 Initia/Acceptance of Schedules
A. Unless otherwise provided in the Contract Docu-
ments, at least ten days before submission of the first
Application for Payment a conference attended by CON-
TRACTOR, ENGINEER, and others as appropriate will be
held to review for acceptability to ENGINEER as provided
below the schedules submitted in accordance with paragraph
2.05.B. CONTRACTOR shall have an additional ten days to
make corrections and adjustments and to complete and
resubmit the schedules. No progress payment shall be made
to CONTRACTOR until acceptable schedules are submitted
to ENGINEER.
1. The progress schedule will be acceptable to
ENGINEER if it provides an orderly progression of the
Work to completion within any specified Milestones and
the Contract Times. Such acceptance will not impose on
ENGINEER responsibility for the progress schedule, for
sequencing, scheduling, or progress of the Work nor
interfere with or relieve CONTRACTOR from
CONTRACTOR's full responsibility therefor.
1
I
I
I
I
I
1
I
2. CONTRACTOR's schedule of Shop Drawing and
Sample submittals will be acceptable to ENGINEER if it
provides a workable arrangement for reviewing and
processing the required submittals.
3. CONTRACTOR's schedule of values will be
acceptable to ENGINEER as to form and substanee if it
provides a reasonable allocation of the Contract Price to
component parts of the Work.
ARTICLE 3 - CONTRACT DOCUMENTS: INTENT,
AMENDING, REUSE
3.01 Intent
I
I
A. The Contract Documents are complementary; what
is called for by one is as binding as if called for by all.
B. It is the intent of the Contract Documents to describe
a functionally complete Project (or part thereof) to be
constructed in accordance with the Contract Documents.
Any labor, documentation, services, materials, or equipment
that may reasonably be inferred from the Contract Docu-
ments or from prevailing custom or trade usage as being
required to produce the intended result will be provided
whether or not specifically called for at no additional cost to
OWNER.
I
I
I
1
I
I
I
I
I
C. Clarifications and interpretations of the Contract
Documents shall be issued by ENGINEER as provided in
Article 9.
3.02 Reference Standards
A. Standards, Specifications, Codes, Laws, and
Regulations
1. Reference to standards, specifications, manuals,
or codes of any technical society, organization, or
association, or to Laws or Regulations, whether such
reference be specific or by implication, shall mean the
standard, specification, manual, code, or Laws or Regula-
tions in effect at the time of opening of Bids (or on the
Effective Date of the Agreement if there were no Bids),
00700 - 10
I
I
1
I
except as may be otherwise specifically stated in the
Contract Documents.
2. No provision of any such standard, specification,
manual or code, or any instruction of a Supplier shall be
effective to change the duties or responsibilities of
OWNER, CONTRACTOR, or ENGINEER, or any of
their subcontractors, consultants, agents, or employees
from those set forth in the Contract Documents, nor shall
any such provision or instruction be effective to assign to
OWNER, ENGINEER, or any of ENGINEER's
Consultants, agents, or employees any duty or authority
to supervise or direct the performance of the Work or any
duty or authority to undertake responsibility inconsistent
with the provisions of the Contract Documents.
I
I
I
I
I
I
I
1
I
I
I
I
I
1
I
3.03 Reporting and Resolving Discrepancies
A. Reporting Discrepancies
1. If, during the performance of the Work,
CONTRACTOR discovers any conflict, error, ambiguity,
or discrepancy within the Contract Documents or between
the Contract Documents and any provision of any Law or
Regulation applicable to the performance of the Work or
of any standard, specification, manual or code, or of any
instruction of any Supplier, CONTRACTOR shall report
it to ENGINEER in writing at once. CONTRACTOR
shall not proceed with the Work affected thereby (except
in an emergency as required by paragraph 6.16.A) until
an amendment or supplement to the Contract Documents
has been issued by one of the methods indicated in
paragraph 3.04; provided, however, that CONTRACTOR
shall not be liable to OWNER or ENGINEER for failure
to report any such conflict, error, ambiguity, or dis-
crepancy unless CONTRACTOR knew or reasonably
should have known thereof.
B. Resolving Discrepancies
1. Except as may be otherwise specifically stated in
the Contract Documents, the provisions of the Contract
Documents shall take precedence in resolving any
conflict, error, ambiguity, or discrepancy between the
provisions of the Contract Documents and:
a. the provisions of any standard, specification,
manual, code, or instruction (whether or not specifi-
cally incorporated by reference in the Contract
DOCUIIi.ents); or
b. the provisions of any Laws or Regulations
applicable to the performance of the Work (unless
such an interpretation of the provisions of the
Contract Documents would result in violation of such
Law or Regulation).
3.04 Amending and Supplementing Contract Documents
A. The Contract Documents may be amended to provide
for additions, deletions, and revisions in the Work or to
modify the terms and conditions thereof in one or more of the
following ways: (i) a Written Amendment; (ii) a Change
Order; or (iii) a Work Change Directive.
B. The requirements of the Contract Documents may be
supplemented, and minor variations and deviations in the
Work may be authorized, by one or more. of the following
ways: (i) a Field Order; (ii) ENGINEER's approval of a
Shop Drawing or Sample; or (iii) ENGINEER's written
interpretation or clarification.
3.05 Reuse of Documents
A. CONTRACTOR and any Subcontractor or Supplier
or other individual or entity performing or furnishing any of
the Work under a direct or indirect contract with OWNER:
(i) shall not have or acquire any title to or ownership rights
in any of the Drawings, Specifications, or other documents
(or copies of any thereof) prepared by or bearing the seal of
ENGINEER or ENGINEER's Consultant, including
electronic media editions; and (ii) shall not reuse any of such
Drawings, Specifications, other documents, or copies thereof
on extensions of the Project or any other project without
written consent of OWNER and ENGINEER and specific
written verification or adaption by ENGINEER. This
prohibition will survive final payment, completion. and
acceptance of the Work, or termination or completion of the
Contract. Nothing herein shall preclude CONTRACTOR
from retaining copies of the Contract Documents for record
purposes,
ARTICLE 4 - AVAILABILITY OF LANDS;
SUBSURFACE AND PHYSICAL CONDmONS;
REFERENCE POINTS
4.01 A vailability of Lands
A. OWNER shall furnish the Site. OWNER sba11 notify
CONTRACTOR of any encumbrances Or restrictions not of
general application but specifically related to use of the Site
with which CONTRACTOR must comply in performing the
Work. OWNER will obtain in a timely manner and pay for
easements for permanent structures or permanent changes in
existing facilities. If CONTRACTOR and OWNER are
unable to agree on entitlement to or on the amount or extent,
if any, of any adjustment in the Contract Price or Contract
Times, or both, as a result of any delay in OWNER's
furnishing the Site, CONTRACTOR may make a Claim.
therefor as provided in paragraph 10.05.
00700 - 11
B. Upon reasonable written request, OWNER shall
furnish CONTRACTOR with a current statement of record
legal title and legal description of the lands upon which the
Work is to be performed and OWNER's interest therein as
necessary for giving notice of or fIling a mechanic I s or
construction lien against such lands in accordance with
applicable Laws and Regulations.
C. CONTRACTOR shall provide for all additional lands
and access thereto that may be required for temporary
construction facilities or storage of materials and equipment.
4.02 Subsurface and Physical Conditions
A. Repons and Drawings:
Conditions identify:
The Supplementary
1. . those reports of explorations and tests of
subsurface conditions at or contiguous to the Site that
ENGINEER has used in preparing the Contract Docu-
ments; and
2. those drawings of physical conditions in or
relating to existing surface or subsurface structures at or
contiguous to the Site (except Underground Facilities) that
ENGINEER has used in preparing the Contract
Documents.
B. Limited Reliance by CONFRACI'OR on Technical
Data Authorized: CONTRACTOR may rely upon the
general accuracy of the "technical data" contained in such
reports and drawings, but such reports and drawings are not
Contract Documents. Such "technical data" is identified in
the Supplementary Conditions. Except for such reliance on
such "technical data," CONTRACTOR may not rely upon or
make any Claim against OWNER, ENGINEER, or any of
ENGINEER's Consultants with respect to:
1. the completeness of such reports and drawings
for CONTRACTOR's purposes, including, but not
limited to, any aspects of the means, methods,
techniques, sequences, and procedures of construction to
be employed by CONTRACTOR, and safety precautions
and programs incident thereto; or
2. other data, interpretations, OplDlOns, and
information contained in such reports or shown or
indicated in such drawings; or
3. any CONTRACTOR interpretation of or
conclusion drawn from any "technical data" or any such
other data, interpretations, opinions, or information.
00700 - 12
I
I
4.03 Differing Subsurface or Physical Conditions
I
A. Notice: If CONTRACTOR believes that any subsur-
face or physical condition at or contiguous to the Site that is
uncovered or revealed either:
I
1. is of such a nature as to establish that any
"technical data" on which CONTRACTOR is entitled to
rely as provided in paragraph 4.02. is materially
inaccurate; or
I
2. is of such a nature as to require a change in the
Contract Documents; or
I
3. differs materially from that shown or indicated in
the Contract Documents; or
I
I
4. is of an unusual nature, and differs materially
from conditions ordinarily encountered and generally
recognized as inherent in work of the character provided
for in the Contract Documents;
I
then CONTRACTOR shall, promptly after becoming aware
thereof and before further disturbing the subsurface or
physical conditions or performing any Work in connection
therewith (except in an emergency as required by paragraph
6.16.A), notify OWNER and ENGINEER in writing about
such condition. CONTRACTOR shall not further disturb
such condition or perform any Work in connection therewith
(except as aforesaid) until receipt of written order to do so.
I
I
B. . ENGINEER's Review: After receipt of written notice
as required by paragraph 4.03.A, ENGINEER will promptly
review the pertinent condition, determine the necessity of
OWNER's obtaining additional exploration or tests with
respect thereto, and advise OWNER in writing (with a copy
to CONTRACTOR) of ENGINEER's fmdings and
conclusions.
I
I
C. Possible Price and Times Adjustments
I
1
1. The Contract Price or the Contract Times, or
both, will be equitably adjusted to the extent that the
existence of such differing subsurface or physical
condition causes an increase or decrease in
CONTRACTOR's cost of, or time required for, perfor-
mance of the Work; subject, however, to the following:
I
I
a. such condition must meet anyone or more of
the categories described in paragraph 4.03.A; and
b. with respect to Work that is paid for on a
Unit Price Basis, any adjustment in Contract Price
will be subject to the provisions of paragraphs 9.08
and 11.03.
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2. CONTRACTOR shall not be entitled to any
adjustment in the Contract Price or Contract Times if:
a. CONTRACTOR knew of the existence of
such conditions at the time CONTRACTOR made a
fmal commitment to OWNER in respect of Contract
Price and Contract Times by the submission of a Bid
or becoming bound under a negotiated contract; or
b. the existence of such condition could
reasonably have been discovered or revealed as a
result of any examination, investigation, exploration,
test, or study of the Site and contiguous areas
required by the Bidding Requirements or Contract
Documents to be conducted by or for CON-
TRACTOR prior to CONTRACTOR's making such
fmal commitment; or
c. CONTRACTOR failed to give the written
notice within the time and as required by paragraph
4.03.A.
3. If OWNER and CONTRACTOR are unable to
agree on entitlement to or on the amount or extent, if any,
of any adjustment in the Contract Price or Contract
Times, or both, a Claim may be made therefor as
provided in paragraph 10.05. However, OWNER,
ENGINEER, and ENGINEER's Consultants shall not be
liable to CONTRACTOR for any claims, costs, losses, or
damages (including but not limited to all fees and charges
of engineers, architects, attorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) sustained by CONTRACTOR on or in connection
with any other project or anticipated project.
4.04 Underground Facilities
A. Shown or Indicated: The information and data shown
or indicated in the Contract Documents with respect to
existing Underground Facilities at or contiguous to the Site
is based on information and data furnished to OWNER or
ENGINEER by the owners of such Underground Facilities,
inchiding OWNER, or by others. Unless it is otherwise
expressly provided in the Supplementary Conditions:
1. OWNER and ENGINEER shall not be
responsible for the accuracy or completeness of any such
information or data; and
2. the cost of all of the following will be included in
the Contract Price, and CONTRACTOR shall have full
responsibility for:
a. reviewing and Checking all such information
and data,
00700 - 13
b. locating all Underground Facilities shown or
indicated in the Contract Documents,
c. coordination of the Work with the owners of
such Underground Facilities, including OWNER,
during construction, and
d. the safety and protection o~ all such Under-
ground Facilities and repairing any damage thereto
resulting from the Work.
B. Not Shown or Indicated
1. If an Underground Facility is uncovered or
revealed at or contiguous to the Site which was not shown
or indicated, or not shown or indicated with reasonable
accuracy in the Contract Documents, CONTRACTOR
shall, promptly after becoming aware thereof and before
further disturbing conditions affected thereby or
performing any Work in connection therewith (except in
an emergency as required by paragraph 6.16.A), identify
the owner of such Underground Facility and give written
notice to that owner and to OWNER and ENGINEER.
ENGINEER will promptly review the Underground
Facility and determine the extent, if any, to which a
change is required in the Contract Documents to reflect
and document the consequences of the existence or
location of the Underground Facility. During such time,
CONTRACTOR shall be responsible for the safety and
protection of such Underground Facility.
2. If ENGINEER concludes that a Change in the
Contract Documents is required, a Work Change
DireCtive or a Change Order will be issued to reflect and
document such consequences. An equitable adjustment
shall be made in the Contract Price of Contract Times, or
both, to the extent that they are attributable to the
existence or location of any Underground Facility that
was not shown or indicated or not shown or indicated
with reasonable accuracy in the Contract Documents and
that CONTRACTOR did not know of and could not
reasonably have been expected to be aware of or to have
anticipated. If OWNER and CONTRACTOR are unable
to agree on entitlement to or on the amount or extent, if
any, of any such adjustment in Contract Price or Contract
Times, OWNER or CONTRACTOR may make a Claim
therefor as provided in paragraph 10.05.
4.05 Reference Points
A. OWNER shall provide engineering surveys to
establish reference points for construction which in
ENGINEER's judgment are necessary to enable CON~
TRACTOR to proceed with the Work. CONTRACTOR
shall be responsible for laying out the Work, shall protect and
preserve the established reference points and property
monuments, and shall make no changes or relocations
without the prior written approval of OWNER.
CONTRACTOR shall report to ENGINEER whenever any
reference point or property monument is lost or destroyed or
requires relocation because of necessary changes in grades or
locations, and shall be responsible for the accurate
replacement or relocation of such reference points or
property monuments by professionally qualified personnel.
4.06 Hazardous Environmental Condition at Site
A. Repons and Drawings: Reference is made to the
Supplementary Conditions for the identification of those
reports and drawings relating to a Hazardous Environmental
Condition identified at the Site, if any, that have been utilized
by the ENGINEER in the preparation of the Contract
Documents.
B. Limited Reliance by CONTRACI'OR on Technical
Data Authorized: CONTRACTOR may rely upon the
general accuracy of the "technical data" contained in such
reports and drawings, but such reports and drawings are not
Contract Documents. Such "technical data" is identified in
the Supplementary Conditions. Except for such reliance on
such "technical data," CONTRACTOR may not rely upon or
make any Claim against OWNER, ENGINEER or any of
ENGINEER's Consultants with respect to:
1. the completeness of such reports and drawings
for CONTRACTOR's purposes, including, but not
limited to, any aspects of the means, methods,
techniques, sequences and procedures of construction to
be employed by CONTRACTOR and safety precautions
and programs incident thereto; or
2. other data, interpretations, opinions and
information contained in such reports or shown or
indicated in such drawings; or
3. any CONTRACTOR interpretation of or
conclusion drawn from any "technical data" or any such
other data, interpretations, opinions or information.
C. CONTRACTOR shall not be responsible for any
Hazardous Environmental Condition uncovered or revealed
at the Site which was not shown or indicated in Drawings or
Specifications or identified in the Contract Documents to be
within the scope of the Work. CONTRACTOR shall be
responsible for a Hazardous Environmental Condition created
with any materials brought to the Site by CONTRACTOR,
Subcontractors, Suppliers, or anyone else for whom CON-
TRACTOR is responsible.
D. If CONTRACTOR encounters a Hazardous
Environmental Condition or.ifCONTRACTOR or anyone for
whom CONTRACTOR is responsible creates a Hazardous
I
Environmental Condition, CONTRACTOR shall immedi-
ately: (i) secure or otherwise isolate such condition; (ii) stop
all Work in connection with such condition and in any area
affected thereby (except in an emergency as required by
paragraph 6.16); and (iii) notify OWNERand ENGINEER
(and promptly thereafter confrrm such notice in writing).
OWNER shall promptly consult with ENGINEER concerning
the necessity for OWNER to retain a qualified expert to
evaluate such condition or take corrective action, if any.
1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
.1
I
I
E. CONTRACTOR shall not be required to resume
Work in connection with such condition or in any affected
area until after OWNER has obtained any required permits
related thereto and delivered to CONTRACTOR written
notice: (i) specifying that such condition and any affected
area is or has been rendered safe for the resumption of Work;
or (ii) specifying any special conditions under which such
Work may be resumed safely. If OWNER and
CONTRACTOR cannot agree as to entitlement to or on the
amount or extent, if any, of any adjustment in Contract Price
or Contract Times, or both, as a result of such Work stop-
page or such special conditions under which Work is agreed
to be resumed by CONTRACTOR, either party may make a
Claim therefor as provided in paragraph 10.05.
F. If after receipt of such written notice
CONTRACTOR does not agree to resume such Work based
on a reasonable belief it is unsafe, or does not agree to
resume such Work under such special conditions, then
OWNER may order the portion of the Work that is in the
area affected by such condition to be deleted from the Work.
If OWNER and CONTRACTOR cannot agree as to
entitlement to or on the amount or extent, if any, of an
adjustment in Contract Price or Contract Times as a result of
deleting such portion of the Work, then either party may
make a Claim therefor as provided in paragraph 10.05.
OWNER may have such deleted portion of the Work
performed by OWNER's own forces or others in accordance
with Article 7.
G. To the fullest extent permitted by l..aws and
Regulations, OWNER shall indemnify and hold harmless
CONTRACTOR, Subcontractors, ENGINEER,
ENGINEER's Consultants and the officers, directors,
partners, employees, agents, other consultants, and
subcontractors of each and any of them from and against all
claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other
dispute resolution costs) arising out of or relating to a
Hazardous Environmental Condition, provided that' such
Hazardous Environmental Condition: (i) was not shown or
indicated in the Drawings or Specifications or identified in
the Contract Documents to be included within the scope of
the Work, and (ii) was not created by CONTRACTOR or by .
anyone for whom CONTRACTOR is responsible. Nothing
00700 - 14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
in this paragraph 4.06.E shall obligate OWNER to indemnify
any individual or entity from and against the consequences of
that individual'S or entity's own negligence.
H. To the fullest extent. permitted by Laws and
Regulations, CONTRACTOR shall indemnify and hold
harmless OWNER, ENGINEER, ENGINEER's Consultants,
and the officers, directors, partners, employees, agents, other
consultants, and subcontractors of each and any of them from
and against all claims, costs, losses, and damages (including
but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of or
relating to a Hazardous Environmental Condition created by
CONTRACTOR or by anyone for whom CONTRACTOR is
responsible. Nothing in this paragraph 4.06.F shall obligate
CONTRACTOR to indemnify any individual or entity from
and against the consequences of that individual's or entity's
own negligence.
I. The provisions of paragraphs 4.02, 4.03, and 4.04
are not intended to apply to a Hazardous Environmental
Condition uncovered or revealed at the Site.
ARTICLE 5 - BONDS AND INSURANCE
5.01 Performance, Payment, and Other Bonds
A. CONTRACTOR shall furnish performance and
payment Bonds, each in an amount at least equal to the
Contract Price as security for the faithful performance and
payment of all CONTRACTOR's obligations under the
Contract Documents. These Bonds shall remain in effect at
least until one year after the date when fInal payment
becomes due, except. as provided otherwise by Laws or
Regulations or by the Contract Documents. CONTRACTOR
shall also furnish such other Bonds as are required by the
Contract Documents.
B. All Bonds shall be in the form prescribed by the
Contract Documents except as provided otherwise by Laws
or Regulations, and shall be executed by such sureties as are
named in the current list of "Companies Holding CertifIcates
of Authority as Acceptable Sureties on Federal Bonds and as
Acceptable Reinsuring Companies" as published in Circular
570 (amended) by the Financial Management Service, Surety
Bond Branch, U.S. Depanment of the Treasury. All Bonds
signed by an agent must be accompanied by a certifIed copy
of such agent's authority to act.
C. If the surety on any Bond furnished by CON-
TRACTOR is declared bankrupt or becomes insolvent or its
right to do business is terminated in any state where any pan
of the Project is located or it ceases to meet the requirements
00700 - 15
of paragraph 5.01.B, CONTRACTOR shall within 20 days
thereafter substitute another Bond and surety, both of which
shall comply with the requirements of paragraphs 5.01. B and
5.02.
5.02 Licensed Sureties and Insurers
A. All Bonds and insurance required by the Contract
Documents to be purchased and maintained by OWNER or
CONTRACTOR shall be obtained from surety or insurance
companies that are duly licensed or authorized in the
jurisdiction in which the Project is located to issue Bonds or
insurance policies for the limits and coverages so required.
Such surety and insurance companies shall also meet such
additional requirements and qualifIcations as may be provided
in the Supplementary Conditions.
5.03 Certificates of Insurance
A. CONTRACTOR shall deliver to OWNER, with
copies to each additional insured identified in the Supple-
mentary Conditions, certifIcates of insurance (and other
evidence of insurance requested by OWNER or any other
additional insured) which CONTRACTOR is required to
purchase and maintain. OWNER shall deliver to
CONTRACTOR, with copies to each additional insured
identifIed in the Supplementary Conditions, certifIcates of
insurance (and other evidence of insurance requested by
CONTRACTOR or any other additional insured) which
OWNER is required to purchase and maintain.
5.04 CONTRACTOR's Liability Insurance
A. CONTRACTOR shall purchase and maintain such
liability and other insurance as is appropriate for the Work
being performed and as will provide protection from claims
set forth below which may arise out of or result from
CONTRACTOR's performance of the Work and
CONTRACTOR's other obligations under the Contract
Documents, whether it is to be performed by
CONTRACTOR, any Subcontractor or Supplier, or by
anyone directly or indirectly employed by any of them to
perform any of the Work, or by anyone for whose acts any
of them may be liable:
1. claims under workers' compensation, disability
benefIts, and other similar employee benefIt acts;
2. claims for damages because of bodily injury,
occupational sickness or disease, or death of
CONTRACTOR's employees;
3. claims for damages because of bodily injury,
sickness or disease, or death of any person other than
CONTRACTOR's employees;
4. claims for damages insured by reasonably
available personal injury liability coverage which are sus-
tained: (i) by any person as a result of an offense directly
or indirectly related to the employment of such person by
CONTRACTOR, or (ii) by any other person for any
other reason;
5. claims for damages, other than to the Work
itself, because of injury to or destruction of tangible
property wherever located, including loss of use resulting
therefrom; and
6. claims for damages because of bodily injury or
death of any person or property damage arising out of the
ownership, maintenance or use of any motor vehicle.
B. The policies of insurance so required by this
paragraph 5.04 to be purchased and maintained shall:
1. I with respect to insurance required by paragraphs
5.04.A:3 through 5.04.A.6 inclusive, include as
additional insureds (subject to any customary exclusion in
respect of professional liability) OWNER, ENGINEER,
ENGINEER's Consultants, and any other individuals or
entities identified in the Supplementary Conditions, all of
whom shall be listed as additional insureds, and include
coverage for the respective officers, directors, partners,
employees, agents, and other consultants and
subcontractors of each and any of all such additional
insureds, and the insurance afforded to these additional
insureds shall provide primary coverage for all claims
covered thereby;
2. include at least the specific coverages and be
written for not less than the limits of liability provided in
the Supplementary Conditions or required by Laws or
Regulations, whichever is greater;
3. include completed operations insurance;
4. include contractual liability insurance covering
CONTRACTOR's indemnity obligations under para-
graphs 6.07,6.11, and 6.20;
5. contain a provision or endorsement that the
coverage afforded will Dot be canceled, materially
changed or renewal refused until at least thirty days prior
written notice has been given to OWNER and
CONTRACTOR and to each other additional insured
identified in the Supplementary Conditions to whom a
certificate of insurance has been issued (and the
certificates of insurance furnished by the CONTRACTOR
pursuant to paragraph 5.03 will so provide);
6. remain in effect at least until final payment and
at all times thereafter when CONTRACTOR may be
00700 - 16
I
correcting, removing, or replacing defective Work in
accordance with paragraph 13.07; and
I
7. with respect to completed operations insurance,
and any insurance coverage written on a claims-made
basis, remain in effect for at least two years after final
payment (and CONTRACTOR shall furnish OWNER and
each other additional insured identified in the Supple-
mentary Conditions, to whom a certificate of insurance
has been issued, evidence satisfactory to OWNER and
any such additional insured of continuation of such
insurance at final payment and one year thereafter).
I
I
I
5.05 OWNER's Liability Insurance
I
I
A. In addition to the insurance required to be provided
by CONTRACTOR under paragraph 5.04, OWNER, at
OWNER's option, may purchase and maintain at OWNER's
expense OWNER's own liability insurance as will protect
OWNER against claims which may arise from operations
under the Contract Documents.
I
5.06 Property Insurance
A. Unless otherwise provided in the Supplementary
Conditions, OWNER shall purchase and maintain property
insurance upon the Work at the Site in the amount of the full
replacement cost thereof (subject to such deductible amounts
as may be provided in the Supplementary Conditions or
required by Laws and Regulations). This insurance shall:
I
I
1. include the interests of OWNER, CONTRAC-
TOR, Subcontractors, ENGINEER, ENGINEER's
Consultants, and any other individuals or entities identi-
fied in the Supplementary Conditions, and the officers,
directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them,
each of whom is deemed to have an insurable interest and
shall be listed as an additional insured;
I
I
I
I
2. be written on a Builder's Risk "all-risk" or open
peril or special causes of loss policy form that shall at
least include insurance for physical loss or damage to the
Work, temporary buildings, false work, and materials and
equipment in transit, and shall insure against at least the
following perils or causes of loss: . fire, lightning,
extended coverage, theft, vandalism and malicious
mischief, earthquake, collapse, debris removal,
demolition occasioned by enforcement of Laws and
Regulations, water damage, and such other perils or
causes of loss as may be specifically required by the
Supplementary Conditions;
I
I
I
3. include expenses incurred in the repair or
replacement of any insured property (including but not
limited to fees and charges of engineers and architects);
I
I
I
I
I
1
I
I
I
I
4. cover materials and equipment stored at the Site
or at another location that was agreed to in writing by
OWNER prior to being incorporated in the Work,
provided that such materials and equipment have been
included in aJ:!. Application for Payment recommended by
ENGINEER;
5. allow for partial utilization of the Work by
OWNER;
6. include testing and startup; and
7. be maintained in effect until final payment is
made unless otherwise agreed to in writing by OWNER,
CONTRACTOR, and ENGINEER with 30 days written
notice to each other additional insured to whom a certifi-
cate of insurance has been issued.
B. OWNER shall purchase and maintain such boiler and
machinery insurance or additional property insurance as may
be required by the Supplementary Conditions or Laws and
Regulations which will include the interests of OWNER,
CONTRACTOR, Subcontractors, ENGINEER,
ENGINEER's Consultants, and any other individuals or
,entities identified in the Supplementary Conditions, each of
whom is deemed to have an insurable interest and shall be
listed as an insured or additional insured.
I
I
I
I
I
I
I
I
I
I
I
C. All the policies of insurance (and the certificates or
other evidence thereof) required to be purchased and
maintained in accordance with paragraph 5.06 will contain a
provision or endorsement that the coverage afforded will not
be canceled or materially changed or renewal refused until at
least 30 days prior written notice has been given to OWNER
and CONTRACTOR and to each other additional insured to
whom a certificate of insurance has been issued and will
contain waiver provisions in accordance with paragraph 5.07.
D.' OWNER shall not be responsible for purchasing and
maintaining any property insurance specified in this
paragraph 5.06 to protect the interests of CONTRACTOR,
Subcontractors, or others in the Work to the extent of any
deductible amounts that are identified in the Supplementary
Conditions. The risk of loss within such identified deductible
amount will be borne by CONTRACTOR, Subcontractors,
or others suffering any such loss, and if any of them wishes
property insurance coverage within the limits of such
amounts, each may purchase and maintain it at the
purchaser's own expense.
E. If CONTRACTOR requests in writing that other
special insurance be included in the property insurance
policies provided under paragraph 5.06, OWNER shall, if
possible, include such insurance, and the cost thereof will be
charged to CONTRACTOR by appropriate Change Order or
Written Amendment. Prior to commencement of the Work
00700 - 17
at the Site, OWNER shall in writing advise CONTRACTOR
whether or not such other insurance has been procured by
OWNER.
5.07 Waiver of Rights
A. OWNER and CONTRACTOR intend that all policies
purchased in accordance with paragraph 5.06 will protect
OWNER, CONTRACTOR, Subcontractors. ENGINEER,
ENGINEER's Consultants, and all other individuals or
entities identified in the Supplementary Conditions to be
listed as insureds or additional insureds (and the officers,
directors, partners, employees, agents, and other consultants
and subcontractors of each and any of them) . in such policies
and will provide primary coverage for all losses and damages
caused by the perils or causes of loss covered thereby. All
such policies shall contain provisions to the effect that in the
event of payment of any loss or damage the insurers will
have no rights of recovery against any of the insureds or
additional insureds thereunder. OWNER and CONTRAC-
TOR waive all rights against each other and their respective
officers, directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them for
all losses and damages caused by, arising out of or resulting
from any of the perils or causes of loss covered by such
policies and any other property insurance applicable to the
Work; and, in addition, waive all such rights against
Subcontractors, ENGINEER, ENGINEER's COnsultants, and
all other individuals or entities identified in the Supplemen-
tary Conditions to be listed as insureds or additional insureds
(and the officers, directors, partners, employees, agents, and
other consultants and subcontractors of each and any of them)
under such policies for losses and damages so caused. None
of the above waivers shall extend to the rights that any party
making such waiver may have to the proceeds of insurance
held by OWNER as trustee or otherwise payable under any
policy so issued.
B. OWNER waives all rights against CONTRACTOR,
Subcontractors, ENGINEER, ENGINEER's Consultants, and
the officers, directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them for:
1. loss due to business interruption, loss of use, or
other consequential loss extending beyond direct physical
loss or damage to OWNER's property or the Work
caused by, arising out of, or resulting from fire or other
peril whether or not insured by OWNER; and
2. loss Or damage to the completed Project or part
thereof caused by, arising out of, or reSulting from fire or
other insured peril or cause of loss covered by any
property insurance maintained on the completed Project
or part thereof by OWNER during partial utilization
pursuant to paragraph 14.05, after Substantial Completion
pursuant to paragraph' 14.04, or after final payment
pursuant to paragraph 14.07.
C. Any insurance policy maintained by OWNER cover-
ing any loss, damage or consequential loss referred to in
paragraph 5.07.B shall contain provisions to the effect that in
the event of payment of any such loss, damage, or
consequential loss, the insurers will have no rights of
recovery against CONTRACTOR, Subcontractors,
ENGINEER, or ENGINEER's Consultants and the officers,
directors, partners, employees, agents, and other consultants
and subcontractors of each and any of them.
5.08 Receipt and Application of Insurance Proceeds
A. Any insured loss under the policies of insurance
required by paragraph 5.06 will be adjusted with OWNER
and made payable to OWNER as fiduciary for the insureds,
as their interests may appear, subject to the requirements of
any applic~ble mortgage clause and of paragraph 5.08.B.
OWNER shall deposit in a separate account any money so
received and shall distribute it in accordance with such agree-
ment as the parties in interest may reach. If no other special
agreement is reached, the damaged Work shall be repaired or
replaced, the moneys so received applied on account thereof,
and the Work and the cost thereof covered by an appropriate
Change Order or Written Amendment.
B. OWNER as fiduciary shall have power to adjust and
settle any loss with the insurers unless one of the parties in
interest. shall object in writing within 15 days after the
occurrence of loss to OWNER's exercise of this power. If
such objection be made, OWNER as fiduciary shall make
settlement with the insurers in accordance with such
agreement as the parties in interest may reach. If no such
agreement among the parties in interest is reached, OWNER
as fiduciary shall adjust and settle the loss with the insurers
and, if required in writing by any party in interest, OWNER
as fiduciary. shall give bond for the proper performance of
such duties.
5.09 Acceptance of Bonds and Insurance; Option to
Replace
A. If either OWNER or CONTRACTOR has any
objection to the coverage afforded by or other provisions of
the Bonds or insurance required to be purchased and
maintained by the other party in accordance with Article 5 on
the basis of non-conformance with the Contract Documents,
the objecting party shall so notify the other party in writing
within 10 days after receipt of the certificates (or other
evidence requested) required by paragraph 2.05.C. OWNER
and CONTRACTOR shall each provide to the other such
additional information in respect of insurance provided as the
other may reasonably request. If either party does not
purchase or maintain all of the Bonds and insurance required
of such party by the Contract Documents, such party shall
notify the other party in writing of such failure to purchase
prior to the start of the Work, or of such failure to maintain
prior to any change in the required coverage. Without
prejudice to any other right or remedy, the other party may
elect to obtain equivalent Bonds or insurance to protect such
other party's interests at the expense of the party who was
required to provide such coverage, and a Change Order shall
be issued to adjust the Contract. Price accordingly.
I
I
I
I
I
1
I
I
5.10 Partial Utilization, Acknowledgment of Property
Insurer
A. If OWNER fmds it necessary to occupy or use a
portion or portions of the Work prior to Substantial
Completion of all the Work as provided in paragraph 14.05,
no such use or occupancy shall commence before the insurers
providing the property insurance pursuant to paragraph 5.06
have acknowledged notice thereof and in writing effected any
changes in coverage necessitated thereby . The insurers
providing the property insurance shall consent by endorse~
ment on the policy or policies, but the property insurance
shall not be canceled or permitted to lapse on account of any
such partial use or occupancy.
I
I
I
I
I
I
I
I
I
I
I
ARTICLE 6 - CONTRACTOR'S RESPONSmILlTIES
6.01 Supervision and Superintendence
A. CONTRACTOR shall supervise, inspect, and direct
the Work competently and efficiently, devoting such attention
thereto and applying such skills and expertise as may be
necessary to perform the Work in accordance with the
Contract Documents. CONTRACTOR shall be solely
responsible for the means, methods, techniques, sequences,
and procedures of construction, but CONTRACTOR shall
not be responsible for the negligence ()f OWNER or
ENGINEER in the design or specification of a specific
means, method, technique, sequence, or procedure of
construction which is shown or indicated in and expressly
required by the Contract Documents. CONTRACTOR shall
be responsible to see that the completed Work complies
accurately with the Contract Documents.
B. At all times during the progress of the Work,
CONTRACTOR shall assign a competent resident superin-
tendent thereto who shall not be replaced without written
notice to OWNER and ENGINEER except under
extraordinary circumstances. The superintendent will be
CONTRACTOR's representative at the Site and shall have
authority to act on behalf of CONTRACTOR. All
communications given to or received from the superintendent
shall be binding on CONTRACTOR.
00700 - 18
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
1
I
6.02 Labor,' Working Hours
A. CONTRACTOR shall provide competent, suitably
qualified personnel to survey, layout, and construct the
Work as required by the Contract Documents. CON-
TRACTOR shall at all times maintain good discipline and
order at the Site.
B. Except as otherwise required for the safety or
protection of persons or the Work or property at the Site or
adjacent thereto, and except as . otherwise stated in the
Contract Documents, all Work at the Site shall be performed
during regular working hours, and CONTRACTOR will not
permit overtime work or the performance of Work on
Saturday, Sunday, or any legal holiday without OWNER's
written consent (Which will not. be unreasonably withheld)
given after prior written notice to ENGINEER.
6.03 Services, Materials, and Equipment
A. Unless otherwise specified in the General Re-
quirements, CONTRACTOR shall provide and assume full
responsibility for all services, materials, equipment, labor,
transportation, construction equipment and machinery, tools,
appliances, fuel, power, light, heat, telephone, water,
sanitary facilities, temporary facilities, and all other facilities
and incidentals necessary for the performance, testing,
start-up, and completion of the Work.
B. All materials and equipment incorporated into the
Work shall be as specified or, if not specified, shall be of
good quality and new, except as otherwise provided in the
Contract Documents. All warranties and guarantees
specifically called. for by the Specifications shall expressly
run to the benefit of OWNER. If required by ENGINEER,
CONTRACTOR shall furnish satisfactory evidence
(including reports of required tests) as to the source, kind,
and quality of materials and equipment. All materials and
equipment shall be stored, applied, installed, connected,
erected, proteCted, used, cleaned, and conditioned in
accordance with instructions of the applicable Supplier,
except as otherwise may be provided in the Contract Docu-
ments.
6.04 Progress Schedule
A. CONTRACTOR shall adhere to the progress schedule
established in accordance with paragraph 2.07 as it may be
adjusted from time to time as provided below.
1. CONTRACTOR shall submit to ENGINEER for
acceptance (to the extent indicated in paragraph 2.07)
proposed adjustments in the progress schedule that will
not result in changing the Contract Times (or Milestones).
Such adjustments will conform generally to the progress
schedule then in effect and additionally will comply with
any provisions of the General Requirements applicable
thereto.
2. Proposed adjustments in the progress schedule
that will change the Contract Times (or Milestones) shall
be submitted in accordance with the requirements of
Article 12. Such adjustments may only be made by a
Change Order or Written Amendment in accordance with
Article 12.
6.05 Substitutes and "Or-Equals n
A. Whenever an item of material or equipment is
specified or described in the Contract Documents by using
the name of a proprietary item or the name of a particular
Supplier, the specification or description is intended to
establish the type, function, appearance, and quality required.
Unless the specification or description contains or is followed
by words reading that no like, equivalent, or "or-equal" item
or no substitution is permitted, other items of material or
equipment or material or equipment of other Suppliers may
be submitted to ENGINEER for review under the circum-
stances described below.
1. "Or-Equal" Items: If in ENGINEER's sole
discretion an item of material or equipment proposed by
CONTRACTOR is functionally equal to that named and
sufficiently similar so that no change in related Work will
be required, it may be considered by ENGINEER as an
"or-equal" item, in which case review and approval of
the proposed item may,in ENGINEER's sole discretion,
be accomplished without compliance with some or all of
the requirements for approval of proposed substitute
items. For the purposes of this paragraph 6.05.A.l, a
proposed item of material or equipment will be
considered functionally equal to an item so named if:
a. in the exercise of reasonable judgment
ENGINEER determines that: (i) it is at least equal in
quality, durability, appearance, strength, and design
characteristics; (ii) it will reliably perform at least
equally well the function imposed by the design
concept of the completed Project as a functioning
whole, and;
b. CONTRACTOR certifies that: (i) there is no
increase in cost to the OWNER; and (ii) it will
conform substantially, even with deviations, to the
detailed requirements of the item named in the
Contract Documents.
2. Substitute Items
a. !fin ENGINEER's sole discretion an item of
material or equipment proposed by CONTRACTOR
does not qualify as an "or-equal" item under
00700 - 19
paragraph 6.05.A.l, it will be considered a proposed
substitute item.
b. CONTRACTOR shall submit sufficient
information as provided below to allow ENGINEER
to determine that the item of material or equipment
proposed is essentially equivalent to that named and
an acceptable substitute therefor ., Requests for
review of proposed substitute items of material or
equipment will not be accepted by ENGINEER from
anyone other than CONTRACTOR.
c. The procedure for review by ENGINEER
will be as set forth in paragraph 6.05.A.2.d, as
supplemented in the General Requirements and as
ENGINEER may decide is appropriate under the
circumstances.
d. CONTRACTOR shall fIrst make written
app~cation to ENGINEER for review of a proposed
substitute item of material or equipment that
CONTRACTOR seeks to furnish or use. The
application shall certify that the proposed substitute
item will perform adequately the functions and
achieve the results called for by the general design,
be similar in substance to that specified, and be suited
to the Same use as that specified. The application
will state the extent, if any, to which the use of the
proposed substitute item will prejudice
CONTRACTOR's achievement of Substantial
Completion on time, whether or not use of the
proposed substitute item in the Work will require a
change in any of the Contract Documents (or in the
provisions of any other direct contract with OWNER
for work on the Project) to adapt the design to the
proposed substitute item and whether or not
incorporation or use of the proposed substitute item
in connection with the Work is subject to payment of
any license fee or royalty. All variations of the pro-
posed substitute item from that specified will be
identified in the application, and available
engineering, sales, maintenance, repair, and
replacement services will be indicated. The
application will also contain an itemized estimate of
all costs or credits that will result directly or indi-
rectly from. use of such substitute item, including
costs of redesign and claims of other contractors
affected by any resulting change, all of which will be
considered by ENGINEER in evaluating the proposed
substitute item. ENGINEER may require CON-
TRACTOR to furnish additional data about the pro-
posed substitute item.
B. Substitute Construction Methods or Procedures: If a
specifIc means, method, technique, sequence, or procedure
of construction is shown or indicated in and expressly
00700 - 20
required by the Contract Documents, CONTRACTOR may
furnish or utilize a substitute means, method, technique,
sequence, or procedure of construction approved by ENGI-
NEER. CONTRACTOR shall submit sufficient information
to allow ENGINEER, in ENGINEER's sole discretion, to
determine that the substitute proposed is equivalent to that
expressly called for by the Contract Documents. The proce-
dure for review by ENGINEER will be similar to that
provided in subparagraph 6.05.A.2.
C. Engineer's Evaluation: ENGINEER will be allowed
a reasonable time within which to evaluate each proposal or
submittal made pursuant to paragraphs 6.05.A and 6.05.B.
ENGINEER will be the sole judge of acceptability. No
"or-equal" or substitute will be ordered, installed or utilized
until ENGINEER's review is complete, which will be
evidenced by either a Change Order for a substitute or an
approved Shop Drawing for an "or equal." ENGINEER will
advise CONTRACTOR in writing of any negative
determination.
D. Special Guarantee: OWNER may require CON-
TRACTOR to furnish at CONTRACTOR's expense a special
performance guarantee or other surety with respect to any
substitute.
E. ENGINEER's Cost Reimbursement: ENGINEER will
record time required by ENGINEER and ENGINEER's
Consultants in evaluating substitute proposed or submitted by
CONTRACTOR pursuant to paragraphs 6.05.A.2 and 6.05.B
and in making changes in the Contract Documents (or in the
provisions of any other direct contract with OWNER for
work on the Project) occasioned thereby. Whether or not
ENGINEER approves a substitute item so proposed or
submitted by CONTRACTOR, CONTRACTOR shall
reimburse OWNER for the charges of ENGINEER and
ENGINEER's Consultants for evaluating each such proposed
substitute.
F. CONrRAcrOR's Expense: CONTRACTOR shall
provide all data in support of any proposed substitute or
"or-equal" at CONTRACTOR's expense.
6.06 Concerning Subcontractors, Suppliers, and Others
A. CONTRACTOR shall not employ any Subcontractor,
Supplier, or other individual or entity (including those
acceptable to OWNER as indicated in paragraph 6.06.B),
whether initially or as a replacement, against whom OWNER
may have reasonable objection. CONTRACTOR shall not be
required to employ any Subcontractor, Supplier, or other
individual or entity to furnish or perform any of the Work
against whom CONTRACTOR has reasonable objection.
B. If the Supplementary Conditions require the identity
of certain Subcontractors, Suppliers, or other individuals or
I
1
I
I
I
I
I
I
I
I
I
I
I
I
I
1
I
I
I
1
1
I
I
I
1
I
I
I
I.
entitiesm be submitted to OWNER in advance for acceptance
by OWNER by a specified date prior to the Effective Date of
the Agreement, and if CONTRACTOR has submitted a list
thereof in accordance with the Supplementary Conditions,
OWNER's acceptance (either in writing or by failing to make
written objection thereto by the date indicated for acceptance
or objection in the Bidding Documents or the Contract
Documents) of any such Subcontractor, Supplier, or other
individual or entity so identified may be revoked on the basis
of reasonable objection after due investigation. CON~
TRACTOR shall submit an acceptable replacement for the
rejected Subcontractor, Supplier, or other individual or
entity, and the Contract Price will be adjusted by the differ-
ence in the cost occasioned by such replacement, and an
appropriate Change Order will be issued or Written
Amendment signed. No acceptance by OWNER of any such
Subcontractor, Supplier, or other individual or entity,
whether initially or as a replacement, shall constitute a
waiver of any right of OWNER or ENGINEER to reject
defective Work.
C. CONTRACTOR shall be fully responsible to
OWNER and ENGINEER for all acts and omissions of the
Subcontractors, Suppliers, and other individuals or entities
performing or furnishing any of the Work just as
CONTRACTOR is responsible for CONTRACTOR's own
acts and omissions. Nothing in the Contract Documents shall
create for the benefit of any such Subcontractor, Supplier, or
other individual or entity any contractual relationship between
OWNER or ENGINEER and any. such Subcontractor,
Supplier or other individual or entity, nor shall it create any
obligation on the part of OWNER or ENGINEER to payor
to see to the payment of any moneys due any such Subcon-
tractor, Supplier, or other individual or entity except as may
otherwise be required by Laws and Regulations.
1
1
I
I
I
I
I
I
I
. D. CONTRACTOR shall be solely responsible for
scheduling and coordinating the Work of Subcontractors,
Suppliers, and other individuals or entities performing or
furnishing any of the Work under a direct or indirect contract
with CONTRACTOR.
E. CONTRACTOR shall require all Subcontractors,
Suppliers, and such other individualS or entities performing
or furnishing any of the Work to communicate with ENGI-
NEER through CONTRACTOR.
F. The divisions and sections of the Specifications and
the identifications of any Drawings shall not control
CONTRACTOR in dividing the Work among Subcontractors
or Suppliers or delineating the Work to be performed by any
specific trade.
G. All Work performed for CONTRACTOR by a
Subcontractor or Supplier will be pursuant to an appropriate
agreement between CONTRACTOR.and the Subcontractor
or Supplier which specifically binds the Subcontractor or
Supplier to the applicable terms and conditions of the
Contract Documents for the benefit of OWNER and
ENGINEER. Whenever any such agreement is with a
Subcontractor or Supplier who is listed as an additional
insured on the property insurance provided in paragraph
5.06, the agreement between the CONTRACTOR and the
Subcontractor or Supplier will contain provisions whereby
the Subcontractor or Supplier waives all · rights against
OWNER, CONTRACTOR, ENGINEER, ENGINEER's
Consultants, and all other individuals or entities identified in
the Supplementary Conditions to be listed as insureds or
additional insureds (and the officers, directors, partners,
employees, agents, and other consultants and subcontractors
of each and any of them) for all losses and damages caused
by, arising out of, relating to, or resulting from any of the
perils or causes of loss covered by such policies and any
other property insurance applicable to the Work. If the
insurers on any such policies require separate waiver forms
to be signed by any Subcontractor or Supplier, CONTRAC-
TOR will obtain the same.
6.07 Patent Fees and Royalties
A. CONTRACTOR shall pay all license fees and
royalties and assume all costs incident to the use in the
performance of the Work or the incorporation in the Work of
any invention, design, process, product, or device Which is
the subject of patent rights or copyrights held by others. If
a particular invention, design, process, product, or device is
specified in the Contract Documents for use in the
performance of the Work and if to the actual knowledge of
OWNER or ENGINEER its use is subject to patent rights or
copyrights calling for the payment of any license fee or
royalty to others, the existence of such rights shall be
disclosed by OWNER in the Contract Documents. To the
fullest extent permitted by Laws and Regulations,
CONTRACTOR shall indemnify and hold harmless
OWNER, ENGINEER, ENGINEER's Consultants, and the
officers, directors, partners, employees or agents, and other
consultants of each and any of them from and against all
claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects. attorneys, and
other professionals and all court or arbitration or other
dispute resolution costs) arising out of or relating to any
infringement of patent rights . or copyrights incident to the use
in the performance of the Work or resulting from the
incorporation in the Work of any invention, design, process,
product, or device not specified in the Contract Documents.
6.08 Permits
A. Unless otherwise provided in the Supplementary
Conditions, CONTRACTOR shall obtain and pay for all
construction permits and licenses. OWNER shall assist
CONTRACTOR, when necessary, in obtaining .such permits
00700 - 21
and licenses. CONTRACTOR shall pay all governmental
charges and inspection fees necessary for the prosecution of
the Work which are applicable at the time of opening of Bids,
or, if there are no Bids, on the Effective Date of the
Agreement. CONTRACTOR shall pay all charges of utility
owners for connections to the Work, and OWNER shall pay
all charges of such utility owners for capital costs related
thereto, such as plant investment fees.
6.09 Laws and Regulations
A. CONTRACTOR shall give all notices and comply
with all Laws and Regulations applicable to the performance
of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, neither OWNER nor
ENGINEER shall be responsible for monitoring
CONTRACTOR's compliance with any Laws or Regulations.
B. If CONTRACTOR performs any Work knowing or
having r~on to know that it is contrary to Laws or
Regulations, CONTRACTOR shall bear all claims, costs,
losses, and damages (including but not limited to all fees and
charges of engineers, architects, anorneys, and other
professionals and all court or arbitration or other dispute
resolution costs) arising out of or relating to such Work;
however, it shall not be CONTRACTOR's primary
responsibility to make certain that the Specifications and
Drawings are in accordance with Laws and Regulations, but
this shall not relieve CONTRACTOR of CONTRACTOR's
obligations under paragraph 3.03.
C. Changes in Laws or Regulations not known at the
time of opening of Bids (or, on the Effective Date of the
Agreement if there were no Bids) having an effect on the cost
or time of performance of the Work may be the subject of an
adjustment in Contract Price or Contract Times. If OWNER
and CONTRACTOR are unable to agree on entitlement to or
on the amount or extent, if any, of any such adjustment, a
Claim may be made therefor as provided in paragraph 10.05.
6.10 Taxes
A. CONTRACTOR shall pay all sales, consumer, use,
and other similar taxes required to be paid by CONTRAC-
TOR in accordance with the Laws and Regulations of the
place of the Project which are applicable during the
performance of the Work.
6.11 Use of Site and Other Areas
A. Limitation on Use of Site and Other Areas
1. CONTRACTOR shall confme construction
equipment, the storage of materials and equipment, and
the operations of workers to the Site and other areas
permined by Laws and Regulations, and shall not
00700 - 22
unreasonably encumber the Site and other areas with
construction equipment or other materials or equipment.
CONTRACTOR shall assume full responsibility for any
damage to any such land or area, or to the owner or
occupant thereof, or of any adjacent land or areas
resulting from the performance of the Work.
I
1
I
1
I
1
I
I
2. Should any claim be made by anY such owner or
occupant because of the performance of the Work,
CONTRACTOR shall promptly settle with such other
party by negotiation or otherwise resolve the claim by
arbitration or other dispute resolution proceeding or at
law.
3. To the fullest extent permitted by Laws and
Regulations, CONTRACTOR shall indemnify and hold
harmless OWNER, ENGINEER, ENGINEER's
Consultant, and the officers, directors, partners,
employees, agents, and other consultants of each and any
of them from and against all claims, costs, losses, and
damages (including but not limited to all fees and charges
of engineers, architects, anorneys, and other professionals
and all court or arbitration or other dispute resolution
costs) arising out of or relating to any claim or action,
legal or equitable, brought by any such owner or occupant
against OWNER, ENGINEER, or any other party
indemnified hereunder to the extent caused by or based
upon CONTRACTOR's performance of the Work.
I
I
B. Removal of Debris During Performance of the Work:
During the progress of the Work CONTRACTOR shall keep
the Site and other areas free from accumulations of waste
materials, rubbish, and other debris. Removal and disposal
of such waste materials, rubbish, and other debris shall con-
form to applicable Laws and Regulations.
I
I
I
I
I
C. Cleaning: Prior to Substantial Completion of the
Work CONTRACTOR shall clean the Site and make it ready
for utilization by OWNER. At the completion of the Work
CONTRACTOR shall remove from the Site all tools,
appliances, construction equipment and machinery, and
surplus materials and shall restore to original condition all
property not designated for alteration by the Contract
Documents.
D. Loading Structures: CONTRACTOR shall not load
nor permit any part of any structure to be loaded in any
manner that will endanger the structure, nor shall
CONTRACTOR subject any part of the Work or adjacent
property to stresses or pressures that will endanger it.
I
I
I
I
6.12 Record Documents
A. CONTRACTOR shall maintain ina safe place at the
Site one record copy of all Drawings, Specifications,
Addenda, Wrinen Amendments, Change Orders, Work
I
1
1
1
1
I
I
I
I
1
Change Directives, Field Orders, and written interpretations
and clarifications in good order and annotated to show
changes made during construction. These record documents
together with all approved Samples and a counterpart of all
approved Shop Drawings will be available to ENGINEER for
reference. Upon completion of the Work, these record
documents, Samples, and Shop Drawings will be delivered to
ENGINEER for OWNER.
6.13 Safety and Protection
A. CONTRACTOR shall be solely responsible for
initiating, maiJ1taining and supervising all safety precautions
and programs in connection with the Work. CONTRACTOR
shall take all necessary precautions for the safety of, and
shall provide the necessary protection to prevent damage,
injuzy or loss to:
1. all persons on the Site or who may be affected
by the Work;
2. all the Work and materials and equipment to be
incorporated therein, whether in storage on or off the
Site; and
3. other property at the Site or adjacent thereto,
including trees, shrubs, lawns, walks, pavements,
roadways, structures, utilities, and Underground Facilities
not designated for removal, relocation, or replacement in
the course of construction.
I
1
I
I
I
I
I
I
1
B. CONTRACTOR shall comply with all applicable
Laws and Regulations relating to the safety of persons or
property, or to the protection of persons or property from
damage, injuzy, or loss; and shall erect and maintain all
necessary safeguards for such safety and protection.
CONTRACTOR shall notify owners of adjacent property and
of Underground Facilities and other utility owners when
prosecution of the Work may affect them, and shall cooperate
with them in the protection, removal, relocation, and
replacement of their property. All damage, injury, or loss to
any property referred to in paragraph 6.13.A.2 or 6.13.A.3
caused, directly or indirectly, in whole or in part, by CON-
TRACTOR, any Subcontractor, Supplier, or any other
individual or entity directly or indirectly employed by any of
them to perform any of the Work, or anyone for whose acts
any of them may be liable, shall be remedied by
CONTRACTOR (except damage or loss attributable to the
fault of Drawings or Specifications or to the acts or
omissions of OWNER or ENGINEER or ENGINEER's Con-
sultant, or anyone employed by any of them, or anyone for
whose acts any of them may be liable, and not attributable,
directly or indirectly, in whole or in part, to the fault or
negligence .of CONTRACTOR or any Subcontractor,
Supplier, or other individual or entity directly or indirectly
employed by any of them). CONTRACTOR's duties and
00700 - 23
responsibilities for safety and for protection of the Work shall
continue until such time as all the Work is completed and
ENGINEER has issued a notice to OWNER' and
CONTRACTOR in accordance with paragraph 14.07.B that
the Work is acceptable (except as otherwise expressly
provided in connection with Substantial Completion).
6.14 Safety Representative
A. CONTRACTOR shall designate a qualified and
experienced safety representative at the Site whose duties and
responsibilities shall be the prevention of accidents and the
maintaining and supervising of safety precautions and
programs.
6.15 Hazard Communication Programs
A. CONTRACTOR shall be responsible for coordinating
any exchange of material safety data sheets or other hazard
communication information required to be made available to
or exchanged between or among employers at the Site in
accordance with Laws or Regulations.
6.16 Emergencies
A. In emergencies affecting the safety or protection of
persons or the Work or property at the Site or adjacent
thereto, CONTRACTOR is obligated to act to prevent
threatened damage, injuzy, or loss. CONTRACTOR shall
give ENGINEER prompt written notice if CONTRACTOR
believes that any significant changes in the Work or
variations from the Contract Documents have been caused
thereby or are required as a result thereof. If ENGINEER
determines that a change in the Contract Documents is
required because of the action taken by CONTRACTOR in
response to such an emergency, a Work Change Directive or
Change Order will be issued.
6.17 Shop Drawings and Samples
A. CONTRACTOR shall submit Shop Drawings to
ENGINEER for review and approval in accordance with the
acceptable schedule of Shop Drawings and Sample
submittals. All submittals will be identified as ENGINEER
may require and in the number of copies specified in the
General Requirements. The data shown on the Shop
Drawings will be complete with respect to quantities, dimen-
sions, specified performance and design criteria, materials,
and similar data to show ENGINEER the services, materials,
and equipment CONTRACTOR proposes to provide and to
enable ENGINEER to review the information for the limited
purposes required by paragraph 6.17.E.
B. CONTRACTOR shall also submit Samples to
ENGINEER for review and approval in accordance with the
acceptable schedule of Shop Drawings and Sample
submittals. Each Sample will be identified clearly as to
material, Supplier, pertinent data such as catalog numbers,
and the use for which intended and otherwise as ENGINEER
may require to enable ENGINEER to review the submittal
for the limited purposes required by paragraph 6.l7.E. The
numbers of each Sample to be submitted will be as specified
in the Specifications.
C. Where a Shop Drawing or Sample is required by the
Contract Documents or the schedule of Shop Drawings and
Sample submittals acceptable to ENGINEER as required by
paragraph 2.07, any related Work performed prior to
ENGINEER's review and approval of the pertinent submittal
will be at the sole expense and responsibility of
CONTRACTOR.
D. Submittal Procedures
1. Before submitting each Shop Drawing or Sample,
CONTRACTOR shall have determined and verified:
a. all field measurements, quantities, dimen-
sions, specified performance criteria, installation
requirements, materials, catalog numbers, and
similar information with respect thereto;
b. all materials with respect to intended use,
fabrication, shipping, handling, storage, assembly,
and installation pertaining to the performance of the
Work;
c. all information relative to means, methods,
techniques, sequences, and procedures of construc-
tion and safety precautions and programs incident
thereto; and
d. CONTRACTOR shall also have reviewed
and coordinated each Shop Drawing or Sample with
other Shop Drawings and Samples and with the
requirements of the Work and the Contract Docu-
ments.
2. Each submittal shall bear a stamp or specific
written indication that CONTRACTOR has satisfied
CONTRACTOR's obligations under the Contract
Documents with respect to CONTRACTOR's review and
approval of that submittal.
3. At the time of each submittal, CONTRACTOR
shall give ENGINEER specific written notice of such
variations, if any, that the Shop Drawing or Sample
submitted may have from the requirements of the
Contract Documents, such notice to be in a written com-
munication separate from the submittal; and, in addition,
shall cause a specific notation to be made on each Shop
00700 - 24
I
Drawing and Sample submitted to ENGINEERfor review
and approval of each such variation.
I
I
1
I
I
I
I
I
I
1
I
I
I
I
E. ENGINEER's Review
1. ENGINEER will timely review and approve
Shop Drawings and Samples in accordance with the
schedule of Shop Drawings and Sample submittals
acceptable to ENGINEER. ENGINEER's review and
approval will be only to determine if the items covered by
the submittals will, after installation or incorporation in
the Work, conform to the information given in. the
Contract Documents and be compatible with the design
concept of the completed Project as a functioning whole
as indicated by the Contract Documents.
2. ENGINEER's review and approval will not
extend to means, methods, techniques, sequences, or
procedures of construction (except where a particular
means, method, technique, sequence, or procedure of
construction is specifically and expressly called for by the
Contract Documents) or to safety precautions or programs
incident thereto. The review and approval of a separate
item as such will not indicate approval of the assembly in
which the item functions.
3. ENGINEER's review and approval of Shop
Drawings or Samples shall not relieve CONTRACTOR
from responsibility for any variation from the require-
ments of the Contract Documents unless CONTRACTOR
has in writing called ENGINEER's attention to each such
variation at the time of each submittal as required by
paragraph 6.17.D.3 and ENGINEER has given written
approval of each such variation by specific written
notation thereof incorporated in or accompanying the
Shop Drawing or Sample approval; nor will any approval
by ENGINEER relieve CONTRACTOR from
responsibility for complying with the requirements of
paragraph 6.17.D.1.
F. Resubmittal Procedures
1. CONTRACTOR shall make corrections required
by ENGINEER and shall return the required number of
corrected copies of Shop Drawings and submit as
required new Samples for review and approval. CON-
TRACTOR shall direct specific attention in writing to
revisions other than the corrections called for by ENGI-
NEER on previous submittals.
I
I
I
I
6.18 Continuing the Work
A. CONTRACTOR shall carry on the Work and adhere
to the progress schedule during all disputes or disagreements
with OWNER. No Work shall be delayed or postponed
pending resolution of any disputes .or disagreeD?-ents, except
I
I
I
I
I
I
I
I
as permitted by paragraph 15.04 or as OWNER and
CONTRACTOR may otherwise agree in writing.
6.19 CONTRACTOR's General Warranty and Guarantee
A. CONTRACTOR warrants and guarantees to
OWNER, ENGINEER, and ENGINEER's Consultants that
all Work will be in accordance with the Contract Documents
and will not be defective. CONTRACTOR's warranty and
guarantee hereunder excludes defects or damage caused by:
1. abuse, modification, or improper maintenance or
operation by persons other than CONTRACTOR, Sub-
contractors, Suppliers, or any other individual or entity
for whom CONTRACTOR is responsible; or
2. normal wear and tear under normal usage.
B. CONTRACTOR's obligation to perform and
complete the Work in accordance with the Contract
Documents shall be absolute. None of the following will
constitute an acceptance of Work that is not in accordance
with the Contract Documents or a release of
CONTRACTOR's obligation to perform the Work in
accordance with the Contract Documents:
I
I
I
I
I
I
I
1. observations by ENGINEER;
2. recommendation by ENGINEER or payment by
OWNER of any progress or [mal payment;
3. the issuance of a certificate of Substantial
Completion by ENGINEER or any payment related
thereto by OWNER;
4. use or occupancy of the Work or any part thereof
by OWNER;
5. any acceptance by OWNER or any failure to do
so;
6. any review and approval of a Shop Drawing or
Sample submittal or the issuance of a notice of acceptabil-
ity by ENGINEER;
7. any inspection, test, or approval by others; or
I
I
I
I
8. any correction of defective Work by OWNER.
6.20 Indemnification
A. To the fullest extent permitted by Laws and Regula-
tions, CONTRACTOR shall indemnify and hold harmless
OWNER, ENGINEER, ENGINEER's Consultants, and the
officers, directors, partners, employee~, agents, and other
consultants and subcontractors of each and any of them from
00700 - 25
and againstall claims, costs, losses, and damages (including
but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) arising out of or
relating to the performance of the Work,provided that any
such claim, cost, loss, or damage:
1. is attributable to bodily injury, sickness, disease,
or death, or to injury to or destruction of tangible
property (other than the Work itself), including the loss of
use resulting therefrom; and
2. is caused in whole or in part by any negligent act
or omission of CONTRACTOR, any Subcontractor, any
Supplier, or any individual or entity directly or indirectly
employed by any of them to perform any of the Work or
anyone for whose acts any of them may be liable,
regardless of whether or not caused in part by any
negligence or omission of an individual or entity indem-
nified hereunder or whether liability is imposed upon such
indemnified party by Laws and Regulations regardless of
the negligence of any such individual or entity.
B. In any and all claims against OWNER or ENGINEER
or any of their respective consultants, agents, officers,
directors, partners, or employees by any employee (or the
survivor or personal representative of such eIttployee) of
CONTRACTOR, any Subcontractor, any Supplier, or any
individual or entity directly or indirectly employed by any of
them to perform any of the Work, or anyone for whose acts
any of them may be liable, the indemnification obligation
under paragraph 6.20.A shall not be limite4 in any way by
any limitation on the amount or type of damages,
compensation, or benefits payable by or for CONTRACTOR
or any such Subcontractor, Supplier, or other individual or
entity under workers' compensation acts, disability benefit
acts, or other employee benefit acts.
C. The indemnification obligations of CONTRACTOR
under paragraph 6.20.A shall not extend to the liability of
ENGINEER and ENGINEER's Consultants or to the
officers, directors, partners, employees, agents, and other
consultants and subcontractors of each and any of them
arising out of:
1. the preparation or approval of, or the failure to
prepare or approve, maps, Drawings, opinions, reports,
surveys, Change Orders, designs, or Specifications; or
2. giving directions or instructions, or failing to
give them, if that is the primary cause of the injury or
damage.
ARTICLE 7 - OTHER WORK
7.01 Related Work at Site
A. OWNER may perform other work related to the
Project at the Site by OWNER's employees, or let other
direct contracts therefor, or have other work performed by
utility owners. If such other work is not noted in the Con-
tract Documents, then:
1. written notice thereof will be given to CON-
TRACTOR prior to starting any such other work; and
2. if OWNER and CONTRACTOR are unable to
agree on entitlement to or on the amount or extent, if any,
of any adjustment in the Contract Price or Contract Times
that should be allowed as a result of such other work, a
Claim may be made therefor as provided in paragraph
10.05..<
B. CONTRACTOR shall afford each other contractor
who is a party to such a direct contract and each utility owner
(and OWNER, if OWNER is performing the other work with
OWNER's employees) proper and safe access to the Site and
a reasonable opportunity for the introduction and storage of
materials and equipment and the execution of such other
work and shall properly coordinate the Work with theirs.
Unless otherwise provided in the Contract Documents, CON-
TRACTOR shall do all cutting, fitting, and patching of the
Work that may be required to properly connect or otherwise
make its several parts come together and properly integrate
with such other work. CONTRACTOR shall not endanger
any work of others by cutting, excavating, or otherwise
altering their work and will only cut or alter their work with
the written consent of ENGINEER and the others whose
work will be affected. The duties and responsibilities of
CONTRACTOR under this paragraph are for the benefit of
such utility owners and other contractors to the extent that
there are comparable provisions for the benefit of
CONTRACTOR in said direct contracts between OWNER
and such utility owners and other contractors.
C. If the proper execution or results of any part of
CONTRACTOR's Work depends upon work performed by
others under this Article 7, CONTRACTOR shall inspect
such other work and promptly repon to ENGINEER in
writing any delays, defects, or deficiencies in such other
work that render it unavailable or unsuitable for the proper
execution and results of CONTRACTOR's Work.
CONTRACTOR's failure to so repon will constitute an
acceptance of such other work as fit and proper for
integration with CONTRACTOR's Work except for latent
defects and deficiencies in such other work.
00700 - 26
I
7.02 Coordination
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
A. If OWNER intends to contract with others for the
performance of other work on the Project at the Site, the
following will be set fonh in Supplementary Conditions:
I. the individual or entity who will have authority
and responsibility for coordination of the activities among
the various contractors will be identified;
2. the specific matters to be covered by such
authority and responsibility will be itemized; and
3. the extent of such authority and responsibilities
will be provided.
B. Unless otherwise provided in the Supplementary
Conditions, OWNER shall have sole authority and respon-
sibility for such coordination.
ARTICLE 8 - OWNER'SRESPONSmILITIES
8.01 Communications to Contractor
A. Except as otherwise provided in these General Condi-
tions, OWNER shall issue all communications to
CONTRACTOR through ENGINEER.
8.02 Replacement of ENGINEER
A. In case of termination of the employment of ENGI-
NEER,. OWNER shall appoint an engineer to whom
CONTRACTOR makes no reasonable objection, whose status
under the Contract Documents shall be that of the former
ENGINEER.
8.03 Furnish Data
A. OWNER shall promptly furnish the data required of
OWNER under the Contract Documents.
8.04 Pay Promptly When Due
A. OWNER shall make payments to CONTRACTOR
promptly when they are due as provided in paragraphs
14.02.C and 14.07.C.
8.05 Lands and Easements; Repons and Tests
A. OWNER's duties in respect of providing lands and
easements and providing engineering surveys to establish
reference points are set fonh in paragraphs 4.01 and 4.05.
Paragraph 4.02 refers to OWNER's identifying and making
available to CONTRACTOR copies of reports of explorations
I
I
I
I
I
I
I
I
I
I
and tests of subsurface conditions and drawings of physical
conditions in or relating to existing surface or subsurface
structures at or contiguous to the Site that have been utilized
by ENGINEER in preparing the Contract Documents.
8.06 Insurance
A. OWNER's responsibilities, if any, in respect to pur-
chasing and maintaining liability and property insurance are
set fonh in Article 5.
8.07 Change Orders
A. OWNER is obligated to execute Change Orders as
indicated in paragraph 10.03.
8.08 Inspections, Tests, and Approvals
A. OWNER's responsibility in respect to certain inspec-
tions, tests, and approvals is set forth in paragraph 13.03.B.
8.09 Limitations on OWNER's Responsibilities
A. The OWNER shall not supervise, direct, or have
control or authority over, nor be responsible for,
CONTRACTOR's means, methods, techniques, sequences,
or procedures of construction, or the safety precautions and
programs incident thereto, or for any failure of CON-
TRACTOR to COIttply with Laws and Regulations applicable
to the performance of the Work. OWNER will not be
responsible for CONTRACTOR's failure to perform the
Work in accordance with the Contract Documents.
I
I
I
I
I
I
I
I
I
8.10 Undisclosed Hazardous Environmental Condition
A. OWNER's responsibility in respect to an undisclosed
Hazardous Environmental Condition is set fonh in paragraph
4.06.
8.11 Evidence of Financial Arrangements
A. If and to the extent OWNER has agreed to furnish
CONTRACTOR reasonable evidence that fmancial
arrangements have been made to satisfy OWNER's
obligations under the Contract Documents, OWNER's
responsibility in respect thereof will be as set fonh in the
Supplementary Conditions.
ARTICLE 9. ENGINEER'S' STATUS DURING
CONSTRUCTION
9.01 OWNER'S Representative
A. ENGINEER will be OWNER's representative during
the construction period. The duties and responsibilities and
the limitations of authority of ENGINEER as OWNER's
representative during construction are set fonh in the
Contract Documents and will not be changed without written
consent of OWNER and ENGINEER.
9.02 Visits to Site
A. ENGINEER will make visits to the Site at intervals
appropriate to the various stages of construction as
ENGINEER deems necessary in order to observe as an
experienced and qualified design professional the progress
that has been made and the quality of the various aspects of
CONTRACTOR's executed Work. Based on infOrInation
obtained during such visits and observations, ENGINEER,
for the benefit of OWNER, will determine, in general, if the
Work is proceeding in accordance with the Contract
Documents. ENGINEER will not be required to make
exhaustive or continuous inspections on the Site to check the
quality or quantity of the Work. ENGINEER's efforts will
be directed toward providing for OWNER a greater degree
of confidence that the completed Work will conform
generally to the Contract Documents. On the basis of such
visits and observations, ENGINEER will keep OWNER
informed of the progress of the Work and will endeavor to
guard OWNER against defective Work.
B. ENGINEER's visits and observations are subject to
all the limitations on ENGINEER's authority and
responsibility set fonh in paragraph 9.10, andpanicularly,
but without limitation, during or as a result of ENGlNEER' s
visits or observations of CONTRACTOR's Work
ENGINEER will not supervise, direct, control, or have
authority over or be responsible for CONTRACTOR's
means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs incident
thereto, or for any failure of CONTRACTOR to comply with
Laws and Regulations applicable to the performance of the
Work.
9.03 Project Representative
A. If OWNER and ENGINEER agree, ENGINEER will
furnish a Resident Project Representative to assist
ENGINEER in providing more extensive observation of the
Work. The responsibilities and authority and limitations
thereon of any such Resident Project Representative and
assistants will be as provided in paragraph 9.10 and in the
Supplementary Conditions. If OWNER designates another
00700 - 27
representative or agent to represent OWNER at the Site who
is not ENGINEER's Consultant, agent or employee, the
responsibilities and authority and limitations thereon of such
other individual or entity will be as provided in the Supple-
mentary Conditions.
9.04 Clarifications and Interpretations
A. ENGINEER will issue with reasonable promptness
such written clarifications or interpretations of the require-
ments of the Contract Documents as ENGINEER may deter-
mine necessary, which shall be consistent with the intent of
and reasonably inferable from the Contract Documents. Such
written clarifications and interpretations will be binding on
OWNER and CONTRACTOR. If OWNER and CON-
TRACTOR are unable to agree on entitlement to or on the
amount or extent, if any, of any adjustment in the Contract
Price or Contract Times, or both, that should be allowed as
a result of a written clarification or interpretation, a Claim
may be made therefor as provided in paragraph 10.05.
.!
9.05 Authorized Variations in Work
A. ENGINEER may authorize minor variations in the
Work from the requirements of the Contract Documents
which do not involve an adjustment in the Contract Price or
the Contract Times and are compatible with the design
concept of the completed Project as a functioning whole as
indicated by the Contract Documents. These may be
accomplished by a Field Order and will be binding on
OWNER and also on CONTRACTOR, who shall perform
the Work involved promptly. If OWNER and CONTRAC-
TOR are unable to agree on entitlement to or on the amount
or extent, if any, of any adjustment in the Contract Price or
Contract Times, or both, as a result of a Field Order, a
Claim may be made therefor as provided in paragraph 10.05.
9.06 Rejecting Defective Work
A. ENGINEER will have authority to disapprove or
reject Work which ENGINEER believes to be defective, or
that ENGINEER believes will not produce a completed
Project that conforms to the Contract Documents or that will
prejudice the integrity of the design concept of the completed
Project as a functioning whole as indieated by the Contract
Documents. ENGINEER will also have authority to require
special inspection or testing of the Work as provided in
paragraph 13.04, whether or not the Work is fabricated,
installed, or completed.
9.07 Shop Drawings, Change Orders and Payments
A. In connection with ENGINEER's authority as to Shop
Drawings and Samples, see paragraph 6.17.
00700 - 28
I
B. In connection with ENGINEER's authority as to
Change Orders, see Anieles 10, 11, and 12.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
C. In connection with ENGINEER's authority as to
Applications for Payment, see Aniele 14.
9.08 Determinationsfor Unit Price Work
A. ENGINEER will determine the actual quantities and
classifications of Unit Price Work performed by
CONTRACTOR. ENGINEER will review with CON-
TRACTOR the ENGINEER's preliminary determinations on
such matters before rendering a written decision thereon (by
recommendation of an Application for Payment or
otherwise). ENGINEER's written decision thereon will be
[mal and binding (except as modified by ENGINEER to
reflect changed factual conditions or more accurate data)
upon OWNER and CONTRACTOR, subject to the
provisions of paragraph 10.05.
9.09 Decisions on Requirements of Contract Documents
and Acceptability of Work
A. ENGINEER will be the initial interpreter of the
requirements of the Contract Documents and judge of the
acceptability of the Work thereunder. Claims, disputes and
other matters relating to the acceptability of the Work, the
quantities and classifications of Unit Price Work, the
interpretation of the requirements of the Contract Documents
penaining to the performance of the Work, and Claims
seeking changes in the Contract Price or Contract Times will
be referred initially to ENGINEER in writing, in accordance
with the provisions of paragraph 10.05, with a request for a
formal decision.
B. When functioning as interpreter and judge under this
paragraph 9.09, ENGINEER will not show partiality to
OWNER or CONTRACTOR and will not be liable in
connection with any interpretation or decision rendered in
good faith in such capacity. The rendering of a decision by
ENGINEER pursuant to this paragraph 9.09 with respect to
any such Claim, dispute, or other matter (except any which
have been waived by the making or acceptance of final
payment as provided in paragraph 14.07) will be a condition
precedent to any exercise by OWNER or CONTRACTOR of
such rights or remedies as either may otherwise have under
the Contract Documents or by Laws or Regulations in respect
of any such Claim, dispute, or other matter.
9.10 Limitations on ENGINEER's Authority and Respon-
sibilities
I
I
I
A. Neither ENGINEER's authority or responsibility
under this Aniele 9 or under any other provision of the
Contract Documents nor any decision made by ENGINEER
in good faith either to exercise or not exercise such authority
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
or responsibility or the undertaking, exercise, or performance
of any authority or responsibility by ENGINEER shall create,
impose, or give rise to any duty in contract, ton, or
otherwise owed by ENGINEER to CONTRACTOR, any
Subcontractor, any Supplier, any other individual. or entity,
or tb any surety for or employee or agent of any of them.
B. ENGINEER will not supervise, direct, control, or
have authority over or be responsible for CONTRACTOR's
means, methods, techniques, sequences, or procedures of
construction, or the safety precautions and programs incident
thereto, or for any failure of CONTRACTOR to comply with
Laws and Regulations applicable to the performance of the
Work. ENGINEER will not be responsible for
CONTRACTOR's failure to perform the Work in accordance
with the Contract Documents.
C. ENGINEER will not be responsible for the acts or
omissions of CONTRACTOR or of any Subcontractor, any
Supplier, or of any other individual or entity performing any
of the Work.
D. ENGINEER's review of the [mal Application for
Payment and accompanying documentation and all mainte-
nance and operating instructions, schedules, guarantees,
Bonds, certificates of inspection, tests and approvals, and
other documentation required to be delivered by paragraph
14.07.A will only be to determine generally that their content
complies with the requirements of, and in the case of
certificates of inspections, tests, and approvals that the results
certified indicate compliance with, the Contract Documents.
E. The limitations upon authority and responsibility set
fonh in this paragraph 9 .10 shall also apply to ENGINEER's
Consultants, Resident Project Representative, and assistants.
ARTICLE 10 . CHANGES IN THE WORK; CLAIMS
10.01 Authorized Changes in the Work
A. Without invalidating the Agreement and without
notice to any surety, OWNER may, at any time or from time
to time, order additions, deletions, or revisions in the Work
by a Written Amendment, a Change Order, or a Work
Change Directive. Upon receipt of any such document,
CONTRACTOR shall promptly proceed with the Work
involved which will be performed under the applicable
conditions of the Contract Documents (except as otherwise
specifically provided).
B. If OWNER and CONTRACTOR are unable to agree
on entitlement to, or on the amount or extent, if any, of an
adjustment in the Contract Price or Contract Times, or both,
that should be allowed as a result of a Work Change
Direā¬tive, a Claim Ittay. be made therefor as provided in
paragraph 10.05.
10.02 Unauthorized Changes in the Work
A. CONTRACTOR shall not be entitled to an increase
in the Contract Price or an extension of the Contract Times
with respect to any work performed that is not required by
the Contract Documents as amended, modified, or
supplemented as provided in paragraph 3.04, except in the
case of an emergency as provided in paragraph 6.16 or in the
case of uncovering Work as provided in paragraph 13.04.B.
10.03 Execution of Change Orders
A. OWNER and CONTRACTOR shall execute
appropriate Change Orders recommended by ENGINEER (or
Written Amendments) covering:
1. changes in the Work which are: (i) ordered by
OWNER pursuant to paragraph 1O.01.A, (ii) required
because of acceptance of defective Work under para-
graph 13.08.A or OWNER's correction of defective
Work under paragraph 13.09, or (iii) agreed to by the
parties;
2. changes in the Contract Price or Contract Times
which are agreed to by the panies, including any
undisputed sum or amount of tiItte for Work actually
performed in accordance with a Work Change Directive;
and
3. changes in the Contract Price or Contract Times
which embody the substance of any written decision
rendered by ENGINEER pursuant to paragraph 10.05;
provided that, in lieu of executing any such Change
Order, an appeal may be taken from any such decision
in accordance with the provisions of the Contract
Documents and applicable Laws and Regulations, but
during any such appeal, CONTRACTOR shall carry on
the Work and adhere to the progress schedule as
provided in paragraph 6.18.A.
10.04 Notification to Surety
A. If notice of any change affecting the general scope
of the Work or the provisions of the Contract Documents
(including, but not limited to, Contract Price or Contract
Times) is required by the provisions of any Bond to be given
to a surety, the giving of any such notice will be
CONTRACTOR's responsibility. The amount of each
applicable Bond will be adjusted to reflect the effect of any
such change.
00700 - 29
10.05 Claims and Disputes
A. Notice: Written notice stating the general nature of
each Claim, dispute, or other matter shall be delivered by the
claimant to ENGINEER and the other party to the Contract
promptly (but in no event later than 30 days) after the start of
the event giving rise thereto. Notice of the amount or extent
of the Claim, dispute, or other matter with supponing data
shall be delivered to the,ENGINEER and the other party to
the Contract within 60 days after the start of such event
(unless ENGINEER allows additional time for claimant to
submit additional or more accurate data in suppon of such
Claim, dispute, or other matter). A Claim for an adjustment
in Contract Price shall be prepared in accordance with the
provisions of paragraph 12.01.B. A Claim for an adjustment
in Contract Time shall be prepared in accordance with the
provisions of paragraph 12.02.B. Each Claim shall be
accompanied by claimant's written statement that the adjust-
ment claimed is the entire adjustment to which the claimant
believes it is entitled as a result of said event. The opposing
party shatl submit any response to ENGINEER and the
claimant within 30 days after receipt of the claimant's last
submittal (unless ENGINEER allows additional time).
B. ENGINEER's Decision: ENGINEER will render
a formal decision in writing within 30 days after receipt of
the last submittal of the claimant or the last submittal of the
opposing party, if any. ENGINEER's written decision on
such Claim, dispute, or other matter will be final and binding
upon OWNER and CONTRACTOR unless:
1. an appeal from ENGINEER's decision is taken
within the time limits and in accordance with the dispute
resolution procedures set fonh in Anicle 16; or
2. if no such dispute resolution procedures have
been set forth in Article 16, a wrinen notice of intention
to appeal from ENGINEER's written decision is
delivered by OWNER or CONTRACTOR to the other
and to ENGINEER within 30 days after the date of such
decision, and a formal proceeding is instituted by the
appealing party in a forum of competent jurisdiction
within 60 days after the date of such decision or within
60 days after Substantial Completion, whichever is later
(unless otherwise agreed in writing by OWNER and
CONTRACTOR), to exercise such rights or remedies as
the appealing party may have with respect to such
Claim, dispute, or other matter in accordance with
applicable Laws and Regulations.
C. If ENGINEER does not render a formal decision in
writing within the time stated in paragraph 1O.05.B, a
decision denying the Claim in its entirety shall be deemed to
have been issued 31 days after receipt of the last submittal of
the claimant or the last submittal of the opposing party, if
any.
00700 - 30
I
D. No Claim for an adjustment in Contract Price or
Contract Times (or Milestones) will be valid if not submitted
in accordance with this paragraph 10.05.
I
I
I
I
ARTICLE 11 - COST OF THE WORK; CASH
ALLOWANCES; UNIT PRICE WORK
11.01 Cost of the Work
A. Costs Included: The term Cost of the Work means
the sum of all costs necessarily incurred and paid by CON-
TRACTOR in the proper performance of the Work. When
the value of any Work covered by a Change Order or when
a Claim for an adjustment in Contract Price is determined on
the basis of Cost of the Work, the costs to be reimbursed to
CONTRACTOR will be only those additional or incremental
costs required because of the change in the Work or because
of the event giving rise to the Claim. Except as otherwise
may be agreed to in writing by OWNER, such costs shall be
in amounts no higher than those prevailing in the locality of
the Project, shall include only the following items, and shall
not include any of the costs itemized in paragraph 11.01.B.
I
I
I
I
I
1. Payroll costs for employees in the direct employ
of CONTRACTOR in the performance of the Work
under schedules of job classifications agreed upon by
OWNER and CONTRACTOR. Such employees shall
include without limitation superintendents, foremen, and
other personnel employed full time at the Site. Payroll
costs for employees not employed full time on the Work
shall be apportioned on the basis of their time spent on
the Work. Payroll costs shall include, but not be limited
to, salaries and wages plus the cost of fringe benefits,
which shall include social security contributions, unem-
ployment, excise, and payroll taXes, workers'
compensation, health and retirement benefits, bonuses,
sick leave, vacation and holiday pay applicable thereto.
The expenses of performing W ()rk outside of regular
working hours, on Saturday, Sunday, or legal holidays,
shall be included in the above to the eXtent authorized by
OWNER.
I
I
I
I
I
2. Cost of all materials and equipment furnished
and incorporated in the Work, including costs of
transportation and storage thereof, and Suppliers' field
services required in connection therewith. All cash
discounts shall accrue to CONTRACTOR unless
OWNER deposits funds with CONTRACTOR with
which to make payments, in which case the cash
discounts shall accrue to OWNER. All trade discounts,
rebates and refunds and returns from sale of surplus
materials and equipment shall accrue to OWNER, and
CONTRACTOR shall make provisions so that they may
be obtained.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. 'Payments made by CONTRACTOR to
Subcontractors for Work performed by Subcontractors.
If required by OWNER, CONTRACTOR shall obtain
competitive bids from subcontractors acceptable to
OWNER and CONTRACTOR and shall deliver such
bids. to OWNER, who will then determine, with the
advice of ENGINEER, which bids, if any, will be
acceptable. If any subcontract provides that the
Subcontractor is to be paid on the basis of Cost of the
Work plus a fee, the Subcontractor's Cost of the Work
and fee shall be determined in the same manner as
CONTRACTOR's Cost of the Work and fee as provided
in this paragraph 11.01.
4. Costs of special consultants (including but not
limited to engineers, architects, testing laboratories,
surveyors, attorneys, and accountants) employed for
services specifically related to the Work.
S. Supplemental costs including the following:
a. The proportion of necessary transportation,
travel, and subsistence expenses of
CONTRACTOR's employees incurred in discharge
of duties connected with the Work.
b. Cost, including transportation and mainte-
nance, of all materials, supplies, equipment,
machinery, appliances, office, and temporary facili-
ties at the Site, and hand tools not owned by the
workers, which are consumed in the performance of
the Work, and cost, less market value, of such items
used but not consumed which remain the property of
CONTRACTOR.
c. Rentals of all construction equipment and
machinery, and the parts thereof whether rented
from CONTRACTOR or others in accordance with
rental agreements approved by OWNER with the
advice of ENGINEER, and the costs of
transportation, loading, unloading, assembly,
dismantling, and removal thereof. All such costs
shall be in accordance with the terms of said rental
agreements. The rental of any such equipment, ma-
chinery, or parts shall cease when the use thereof is
no longer necessary for the Work.
d. Sales, consumer, use, and other similar
taxes related to the Work, and for which CON-
TRACTOR is liable, imposed by Laws and Regu-
lations.
e. Deposits lost for causes other than negli-
gence of CONTRACTOR, any Subcontractor, or
anyone directly or indirectly employed by any of
them or for whose acts any of"them may be liable,
00700 - 31
and royalty payments and fees for permits and
licenses.
f. Losses and damages (and related expenses)
caused by damage to the Work, not compensated by
insurance or otherwise, sustained by
CONTRACTOR in connection with the perfor~
mance of the Work (except losses and damages
within the deductible amounts of property insurance
established in accordance with paragraph S.06.D),
provided such losses and damages have resulted
from causes other than the negligence of
CONTRACTOR, any Subcontractor, or anyone
directly or indirectly employed by any of them or
for whose acts any of them may be liable. Such
losses shall include settlements made with the
written consent and approval of OWNER. No such
losses, damages, and expenses shall be included in
the Cost of the Work for the purpose of determining
CONTRACTOR's fee.
g. The cost of utilities, fuel, and sanitary
facilities at the Site.
h. Minor expenses such as telegrams, long
distance telephone calls, telephone service at the
Site, expressage, and similar petty cash items in
connection with the Work.
i. When the Cost of the Work is used to
determine the value of a Change Order or of a
Claim, the cost of premiums for additional Bonds
and insurance required because of the changes in the
Work or caused by the event giving rise to the
Claim.
j. When all the Work is performed on the
basis of cost-plus, the costs of premiums for all
Bonds and insurance CONTRACTOR is required by
the Contract Documents to purchase and maintain.
B. Costs Excluded: The term Cost of the Work shall
not include any of the following items:
1. Payroll costs and other compensation of
CONTRACTOR's officers, executives, principals (of
partnerships and sole proprietorships), general manag-
ers, engineers, architects, estimators, attorneys, audi-
tors, accountants, purchasing and contracting agents,
expediters, timekeepers, clerks, and other personnel
employed by CONTRACTOR, whether at the Site or in
CONTRACTOR's principal or branch office for general
administration of the Work and not specifically included
in the agreed upon schedule of job classifications
referred to in paragraph 11.01.A.l or specifically
covered by paragraph 11.01.A.4, all of which are to be
considered administrative costs covered by the
CONTRACTOR's fee.
2. Expenses of CONTRACTOR's principal and
branch offices other than CONTRACTOR's office at the
Site.
3. Any part of CONTRACTOR's capital expenses,
including interest on CONTRACTOR's capital employed
for the Work and charges against CONTRACTOR for
delinquent payments.
4. Costs due to the negligence of CONTRACTOR,
any Subcontractor, or anyone directly or indirectly
employed by any of them or for whose acts any of them
may be liable, including but not limited to, the
correction of defective Work, disposal of materials or
equipment wrongly supplied, and making good any
damage to property.
5. Other overhead or general expense costs of any
kind and the costs of any item not specifically and
expressly included in paragraphs 11.01.A and 11.01.B.
C. CONTRACTOR's Fee: When all the Work is
performed on the basis of cost-plus, CONTRACTOR's fee
shall be determined as set fonh in the Agreement. When the
value of any Work covered by a Change Order or when a
Claim for an adjustment in Contract Price is determined on
the basis of Cost of the Work, CONTRACTOR's fee shall be
determined as set fonh in paragraph 12.01.C.
D. Documentation: Whenever the Cost of the Work for
any purpose is to be determined pursuant to paragraphs
11.01.A and 11.01.B, CONTRACTOR will establish and
maintain records thereof in accordance with generally
accepted accounting practices and submit in a form
acceptable to ENGINEER an itemized cost breakdown
together with supponing data.
11.02 Cash Allowances
A. It is understood that CONTRACTOR has included
in the Contract Price all allOWances so named in the Contract
Documents and shall cause the Work so covered to be
performed for such sums as may be acceptable to OWNER
and ENGINEER. CONTRACTOR agrees that:
1. the allowances include the cost to CONTRAC-
TOR (less any applicable trade discounts) of materials
and equipment required by the allowances to be
delivered at the Site, and all applicable taxes; and
2. CONTRACTOR's costs for unloading and
handling on the Site, labor, installation costs, overhead,
profit, and other expenses contemplated for the allow-
00700 - 32
I
ances have been included in the Contract Price and not
in the allowances, and no demand for additional payment
on account of any of the foregoing will be valid.
I
I
I
I
I
I
I
B. Prior to final payment, an appropriate Change Order
will be issued as recommended by ENGINEER to reflect
actual amounts due CONTRACTOR on account of Work
covered by allowances, and the Contract Price shall be
correspondingly adjusted.
11.03 Unit Price Work
A. Where the Contract Documents provide that all or
pan of the Work is to be Unit Price Work, initially the
Contract Price will be deemed to include for all Unit Price
Work an amount equal to the sum of the unit price for each
separately identified item of Unit Price Work times the
estimated quantity of each item as indicated in the Agree-
ment. The estimated quantities of items of Unit Price Work
are not guaranteed and are solely for .the purpose of
comparison of Bids and determining an initial Contract Price.
Determinations of the actual quantities and classifications of
Unit Price Work performed by CONTRACTOR will be
made by ENGINEER subject to the provisions of paragraph
9.08.
I
I
B. Each unit price will be deemed to include an amount
considered by CONTRACTOR to be adequate to cover
CONTRACTOR's overhead and profit for each separately
identified item.
C. OWNER or CONTRACTOR may make a Claim for
an adjustment in the Contract Price in accordance with
paragraph 10.05 if:
I
I
I
I
I
I
I
I
I
1. the quantity of any item of Unit Price Work
performed by CONTRACTOR differs materially and
significantly from the estimated quantity of such item
indicated in the Agreement; and
2. there is no corresponding adjustment with
respect any other item of Work; and
3. if CONTRACTOR believes that
CONTRACTOR is entitled to an increase in Contract
Price as a result of having incurred additional expense or
OWNER believes that OWNER is entitled to a decrease
in Contract Price and the panies are unable to agree as
to the amount of any such increase or decrease.
I
'I
I
I
I
I
I
I
I
I
I
I
ARTICLE 12 - CHANGE OF CONTRACT PRICE;
CHANGE OF CONTRACT TIMES
12.01 Change of Contract Price
A. The Contract Price may only be changed by a
Change Order or by a Written Amendment. Any Claim for
an adjusttnent in the Contract Price shall be based on written
notice submitted by the party making the Claim to the
ENGINEER and the other party to the Contract in accor-
dance with the provisions of paragraph 10.05.
B. The value of any Work covered by a Change Order
or of any Claim for an adjusttnent in the Contract Price will
be determined as follows:
1. where the Work involved is covered by unit
prices contained in the Contract Documents, byapplica-
tion of such. unit prices to the quantities of the items
involved (subject to the provisions of paragraph 11.03 );
or
2. where the Work involved is not covered by unit
prices contained in the Contract Documents, by a
mutually agreed lump sum (which may include an
allowance for overhead and profit not necessarily in
accordance with paragraph 12.01.C.2); or
3. where the Work involved is not covered by unit
prices contained in the Contract Documents and agree-
ment to a lump sum is not reached under paragraph
12.01.B.2, on the basis of the Cost of the Work
(determined as provided in paragraph 11.01) plus a
CONTRACTOR's fee for overhead and profit (deter-
mined as provided in paragraph 12.01.C).
I
I
I
I
I
I
I
C. CONTRACTOR's Fee: The CONTRACTOR's fee
for overhead and profit shall be determined as follows:
1. a mutually acceptable fixed fee; or
2. if a fixed fee is not agreed upon, then a fee
based on the following. percentages of the various
portions of the Cost of the Work:
a. for costs incurred under paragraphs
11.01.A.l and 11.01.A.2, the CONTRACTOR's
fee shall be 15 percent;
b. for costs incurred under paragraph
11.01.A.3, the CONTRACTOR's fee shall be five
percent;
c. where one or more tiers. of subcontracts are
on the basis of Cost of the Work plus a fee and no
fixed fee is agreed upon, the intent of paragraph
12.01.C.2.a is that the Subcontractor who actually
performs the Work, at whatever tier, will be paid
a fee of 15 percent of the costs incurred by such
Subcontractor under paragraphs 11.01.A.l and
11.01.A.2 and that any higher tier Subcontractor
and CONTRACTOR will each be paid a fee of five
percent of the amount paid to the next lower tier
Subcontractor;
d. no fee shall be payable on the basis of costs
itemized under paragraphs 11.01.AA, 11.01.A.S,
and 11.01.B;
e. the amount of credit to be allowed by
CONTRACTOR to OWNER for any change which
results in a net decrease in cost will be the amount
of the actual net decrease in cost plus a deduction in
CONTRACTOR's fee by an amount equal to five
percent of such net decrease; and
f. when both additions and credits are in-
volved in anyone change, the adjustment in
CONTRACTOR's fee shall be computed on the
basis of the net change in accordance with para-
graphs 12.01.C.2.a through 12.01.C.2.e, inclu-
sive.
12.02
Change of Contract Times
A. The Contract Times (or Milestones) may only be
changed by a Change Order or by a Written Amendment.
Any Claim for an adjustment in the Contract Times (or
Milestones) shall be based on written notice submitted by the
party making the claim to the ENGINEER and the other
pany to the Contract in accordance with the provisions of
paragraph 10.05.
B. Any adjustment of the Contract Times (or
Milestones) covered by a Change Order or of any Claim for
an adjustment in the Contract Times (or Milestones) will be
determined in accordance with the provisions of this
Article 12.
12.03 Delays Beyond CONTRACTOR's Control
A. Where CONTRACTOR is prevented from
completing any part of the Work within the Contract Times
(or Milestones) due to delay beyond the control of
CONTRACTOR, the Contract Times (or Milestones) will be
extended in an amount equal to the time lost due to such
delay if a Claim is made therefor as provided in paragraph
12.02.A. Delays beyond the control of CONTRACTOR
shall include, but not be limited to, acts or neglect by
OWNER, acts or neglect of utility owners or other
contractors performing other work as contemplated- by
00700 - 33
Article 7, fires, floods, epidemics, abnormal weather
conditions, or acts of God.
12.04 Delays Within CONTRACTOR's Control
A. The Contract Times (or Milestones) will not be
extended due to delays within the control of
CONTRACTOR. Delays attributable to and within the
control of a Subcontractor or Supplier shall be deemed to be
delays within the control of CONTRACTOR.
12.05 Delays Beyond OWNER's and CONTRACTOR's
Control
A. Where CONTRACTOR is prevented from complet-
ing any part of the Work within the Contract Times (or
Milestones) due to delay beyond the control of both OWNER
and CONTRACTOR, an extension of the Contract Times (or
Milestones) in an amount equal to the time lost due to such
delay shall be CONTRACTOR's sole and exclusive remedy
for such delay.
12.06 Delay Damages
A. In no event shall OWNER or ENGINEER be liable
to CONTRACTOR, any Subcontractor, any Supplier, or any
other person or organization, or to any surety for or
employee or agent of any of them, for damages arising out of
or resulting from:
1. delays caused by or within the control of CON~
TRACTOR; or
2. delays beyond the control of both OWNER and
CONTRACTOR including but not limited to fires,
floods, epidemics, abnormal weather conditions, acts of
God, or acts or neglect by utility owners or other
contractors performing other work as contemplated by
Anicle 7.
B. Nothing in this paragraph 12.06 bars a change in
Contract Price pursuant to this Anicle 12 to compensate
CONTRACTOR due to delay, interference, or disruption
directly attributable to actions or inactions of OWNER or
anyone for whom OWNER is responsible.
ARTICLE 13 - TESTS AND INSPECTIONS;
CORRECTION, REMOVAL OR ACCEPTANCE OF
DEFECTIVE WORK
13.01 Notice of Defects
A. Prompt notice of all defective Work of which
OWNER or ENGINEER has actual knowledge will be given
to CONTRACTOR. All defective Work may be rejected,
corrected, or accepted as provided in this Anicle 13.
13.02 Access to Work
A. OWNER, ENGINEER, ENGINEER's Consultants,
other representatives and personnel of OWNER, independent
testing laboratories, and governmental agencies with
jurisdictional interests will have access to the Site and the
Work at reasonable times for their observation,. inspecting,
and testing. CONTRACTOR shall provide them proper and
safe conditions for such access and advise them of
CONTRACTOR's Site safety procedures and programs so
that they may comply therewith as applicable.
13.03 Tests and Inspections
A. CONTRACTOR shall give ENGINEER timely
notice of readiness of the Work for all required inspections,
tests, or approvals and shall cooperate with inspection and
testing personnel to facilitate required inspections or tests.
B. OWNER shall employ and pay for the services of an
independent testing laboratory to perform all inspections,
tests, or approvals required by the Contract Documents
except:
1. for inspections, tests, or approvals covered by
paragraphs 13.03.C and 13.03.D below;
2. that costs incurred in connection with tests or
inspections conducted pursuant to paragraph 13.04.B
shall be paid as provided in said paragraph 13.04.B; and
3. as otherwise specifically provided in the Con-
tract Documents.
C. If Laws or Regulations of any public body having
jurisdiction require any Work (or part thereof) specifically to
be inspected, tested, or approved by an employee or other
representative of such public body, CONTRACTOR shall
assume full responsibility for arranging and obtaining such
inspections, tests, or approvals, pay all costs in connection
therewith, and furnish ENGINEER the required cenificates
of inspection or approval.
D. CONTRACTOR shall be responsible for arranging
and obtaining and shall pay all costs in connection with any
inspections, tests, or approvals required for OWNER's and
ENGINEER's acceptance of materials or equipment to be
incorporated in the Work; or acceptance of materials, mix
designs, or equipment submitted for approval prior to
CONTRACTOR's purchase thereof for incorporation in the
Work. Such inspections, tests, or approvals shall be
performed by organizations acceptable to OWNER and
ENGINEER.
00700 - 34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
E. If any Work (or the work of others) that is to be
inspeCted, tested, or approved is covered by CONTRACTOR
without written concurrence of ENGINEER, it must, if
requested by ENGINEER, be uncovered for observation.
F. Uncovering Work as provided in paragraph 13.03.E
shall be at CONTRACTOR's expense unless CON-
TRACTOR has given ENGINEER timely notice of
CONTRACTOR's intention to cover the same and ENGI-
NEER has not acted with reasonable promptness in response
to such notice.
13.04 Uncovering Work
A. If any Work is covered contrary to the written
request of ENGINEER, it must, if requested by ENGINEER,
be uncovered for ENGINEER's observation and replaced at
CONTRACTOR's expense.
B. If ENGINEER considers it necessary or advisable
that covered Work be observed by ENGINEER or inspected
or tested by others, CONTRACTOR, at ENGINEER's
request, shall uncover, expose, or otherwise make available
for observation, inspection, or testing as ENGINEER may
require, that portion of the Work in question, furnishing all
necessary labor, material, and equipment. If it is found that
such Work is defective. CONTRACTOR shall pay all
Claims, costs, losses, and damages (including but not limited
to all fees and charges of engineers, architects, attorneys, and
other professionals and all court or arbitration or other
dispute resolution costs) arising out of or relating to such
uncovering, exposure, observation, inspection, and testing,
and of satisfactory replacement or reconstruction (including
but DOt liIttited to all costs of repair or replacement of work
of others); and OWNER shall be entitled to an appropriate
decrease in the Contract Price. If the parties are unable to
agree as to the amount thereof, OWNER may make a Claim
therefor as provided in paragraph 10.05. If, however, such
Work is DOt found to be defective, CONTRACTOR shall be
allowed an increase in the Contract Price or an extension of
the Contract Times (or Milestones), or both, directlyattribut-
able to such uncovering, exposure, observation, inspection,
testing, replacement, and reconstruction. If the parties are
unable to agree as to the amount or extent thereof,
CONTRACTOR may make a Claim therefor as provided in
paragraph 10.05.
I
I
I
I
I
I
I
I
I
I
I
13.05 OWNER May Stop the Work
A. If the Work is defective, or CONTRACTOR fails to
supply sufficient skilled workers or suitable materials or
equipment, or fails to perform the Work in such a way that
the completed Work will conform to the Contract
Documents, OWNER may order CONTRACTOR to stop the
Work, or any portion thereof, until the cause for such order
has been eliminated; however, this right'of OWNER to stop
the Work shall not give rise to any duty on the part of
OWNER to exercise this right for the benefit of
CONTRACTOR, any Subcontractor, any Supplier, any other
individual or entity, or any surety for, or employee or agent
of any of them.
13.06 Correction or Removal of Defective Work
A. CONTRACTOR shall correct all defective Work,
whether or not fabricated, installed, or completed, or, if the
Work has been rejected by ENGINEER, remove it from the
Project and replace it with Work that is not defective.
CONTRACTOR shall pay all Claims, costs, losses, and
damages (including but not liIttited to all fees and charges of
engineers, architects, attorneys, and other professionals and
all court or arbitration or other dispute resolution costs)
arising out of or relating to such correction or removal
(including but not limited to all costs of repair or replacement
of work of others).
13.07 Correction Period
A. If within one year after the date of Substantial
Completion or such longer period of time as may be
prescribed by Laws or Regulations or by the terms of any
applicable special guarantee required by the Contract
Documents or by any specific provision of the Contract
Documents, any Work is found to be defective, or if the
repair of any damages to the land or areas made available for
CONTRACTOR's use by OWNER or permitted by Laws and
Regulations as contemplated in paragraph 6.11.A is found to
be defective, CONTRACTOR shall promptly, without cost
to OWNER and in accordance with OWNER's written
instructions: (i) repair such defective land or areas, or (ii)
correct such defective Work or, if the defective Work has
been rejected by OWNER, remove it from the Project and
replace it with Work that is not defective, and (Hi) satisfac-
torily correct or repair or remove and replace any damage to
other Work, to the work of others or other land or areas
resulting therefrom. If CONTRACTOR does not promptly
comply with the terms of such instructions, or in an
emergency where delay would cause serious risk of loss or
damage, OWNER may have the defective Work corrected or
repaired or may have the rejected Work removed an~
replaced, and all Claims, costs, losses, and damages
(including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and
all court or arbitration or other dispute resolution costs)
arising out of or relating to such correction or repair or such
removal and replacement (including but not limited to all
costs of repair or replacement of work of others) will be paid
by CONTRACTOR.
B. In special circumstances where a particular item of
equipment is placed in continuous service before Substantial
Completion of all the Work, the correction period for that
00700 - 35
item may start to run from an earlier date if so provided in
the Specifications or by Written Amendment.
C. Where defective Work (and damage to other Work
resulting therefrom) has been corrected or removed and
replaced under this paragraph 13.07, the correction period
hereunder with respect to such Work will be extended for an
additional period of one year after such correction or removal
and replacement has been satisfactorily completed.
D. CONTRACTOR's obligations under this paragraph
13.07 are in addition to any other obligation or warranty.
The provisions of this paragraph 13.07 shall not be construed
as a substitute for or a waiver of the provisions of any
applicable statute of limitation or repose.
13.08 Acceptance of Defective Work
A. If, instead of requiring correction or removal and
replacement of defective Work, OWNER (and, prior to
ENGINEER's recommendation of final payment,
ENGINEER) prefers to accept it, OWNER may do so.
CONTRACTOR shall pay all Claims, costs, losses, and
daIttages (including but not limited to all fees and charges of
engineers, architects, attorneys, and other professionals and
all court or arbitration or other dispute resolution costs)
attributable to OWNER's evaluation of and determination to
accept such defective Work (such costs to be approved by
ENGINEER as to reasonableness) and the diminished value
of the Work to the extent not otherwise paid by
CONTRACTOR pursuant to this sentence. If any such
acceptance occurs prior to ENGINEER's recommendation of
[mal payment, a Change Order will be issued incorporating
the necessary revisions in the Contract Documents with
respect to the Work, and OWNER shall be entitled to an
appropriate decrease in the Contract Price, reflecting the
diminished value of Work so accepted. If the parties are
unable to agree as to the amount thereof, OWNER may make
a Claim therefor as provided in paragraph 10.05. If the
acceptance occurs after such recommendation, an appropriate
amount will be paid by CONTRACTOR to OWNER.
13.09 OWNER May Correct Defective Work
A. If CONTRACTOR fails within a reasonable time
after written notice from ENGINEER to correct defective
Work or to remove and replace rejected Work as required by
ENGINEER in accordance with paragraph 13.06.A, or if
CONTRACTOR fails to perform the Work in accordance
with the Contract Documents, or if CONTRACTOR fails to
comply with any other provision of the Contract Documents,
OWNER may, after seven days written notice to
CONTRACTOR, correct and remedy any such deficiency.
B. In exercising the'rights and remedies under this
paragraph, OWNER shall proceed expeditiously. In
I
.
connection with such corrective and remedial action,
OWNER may exclude CONTRACTOR from all or part of
the Site, take possession of all or part of the Work and
suspend CONTRACTOR's services related thereto.. take
possession of CONTRACTOR's tools, appliances, con-
struction equipment and machinery at the Site, and incorpo-
rate in the Work all materials and equipment stored at the
Site or for which OWNER has paid CONTRACTOR but
which are stored elsewhere. CONTRACTOR shall allow
OWNER, OWNER's representatives, agents and employees,
OWNER's other contractors, and ENGINEER and
ENGINEER's Consultants access to the Site to enable
OWNER to exercise the rights and remedies under this
paragraph.
I
I
I
I
I
I
C. All Claims, costs, losses, and damages (including
but not limited to all fees and charges of engineers,
architects, attorneys, and other professionals and all court or
arbitration or other dispute resolution costs) incurred or
sustained by OWNER in exercising the rights and remedies
under this paragraph 13.09 will be charged against CON-
TRACTOR, and a Change Order will be issued incorporating
the necessary revisions in the Contract DOCUIttents with
respect to the Work; and OWNER shall be entitled to an
appropriate decrease in the Contract Price. If the panies are
unable to agree as to the amount of the adjustment, OWNER
may make a Claim therefor as provided in paragraph 10.05.
Such claims, costs, losses and damages will include but not
be limited to all costs of repair, or replacement of work of
others destroyed or damaged by correction, removal, or
replacement of CONTRACTOR's defective Work.
I
I
I
I
D. CONTRACTOR shall not be allowed an extension
of the Contract Times (or Milestones) because of any delay
in the performance of the Work attributable to the exercise by
OWNER of OWNER's rights and remedies under this
paragraph 13.09.
I
I
I
ARTICLE 14 - PAYMENTS TO CONTRACTOR AND
COMPLETION
14.01 Schedule of Values
I
A. The schedule of values established as provided in
paragraph 2.07.A will serve as the basis for progress
payments and will be incorporated into a form of Application for Payment acceptable to ENGINEER. Progress payIttents
on account of Unit Price Work will be based on the number
of units completed.
I
I
I
00700 - 36
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
14.02 Progress Payments
A. Applications for Payments
1. At least 20 days before the date established for
each progress payment (but not more often than once a
month), CONTRACTOR shall submit to ENGINEER
for review an Application for Payment filled out and
signed by CONTRACTOR covering the Work
completed as of the date of the Application and
accompanied by such supponing documentation as is
required by the Contract Documents. If payment is
requested on the basis of materials and equipment not
incorporated in the Work but delivered and suitably
stored at the Site or at another location agreed to in
writing, the Application for . Payment shall also be
accompanied by a bill of sale, invoice, or other docu-
mentation warranting that OWNER has received the
materials and equipment free and clear of all Liens and
evidence that the materials and equipment are covered
by appropriate property insurance or other arrangements
to protect OWNER's interest therein, all of which must
be satisfactory to OWNER.
2. Beginning with the second Application for
Payment, each Application shall include an affidavit of
CONTRACTOR stating that all previous progress
payments received on account of the Work have been
applied on account to discharge CONTRACTOR's
legitimate obligations associated with prior Applications
for Payment.
3. The amount of retainage with respect to pro-
gress payments will be as stipulated in the Agreement.
B. Review of Applications
1. ENGINEER will, within 10 days after receipt of
each Application for Payment, either indicate in writing
a recommendation of payment and present the
Application to OWNER or return the Application to
CONTRACTOR indicating in writing ENGINEER's
reasons for refusing to recommend payment. In the
latter case, CONTRACTOR may make the necessary
corrections and resubmit the Application.
I
I
I
I
2. ENGINEER's recommendation of any payment
requested in an Application for Payment will constitute
a representation by ENGINEER to OWNER, based on
ENGINEER's observations on the Site of the executed
Work as an experienced and qualified design profession-
al and on ENGINEER's review of the Application for
Payment and the accompanying data and schedules, that
to the best of ENGINEER's knowledge, information and
belief:
00700 - 37
a. the Work has progressed to the point,
indicated;
b. the quality of the Work is generally in
accordance with the Contract Documents (subject to
an evaluation of the Work as a functioning whole
prior to or upon Substantial Completion, to the
results of any subsequent tests called for in the
Contract Documents, to a fInal determination of
quantities and classifications for Unit Price Work
under paragraph 9.08, and to any other
qualifications stated in the recommendation); and
c. the conditions precedent to
CONTRACTOR's being entitled to such payment
appear to have been fulfIlled in so far as it is
ENGINEER's responsibility to observe the Work.
3. By recommending any such payment ENGI-
NEER will not thereby be deemed to have represented
that: (i) inspections made to check the quality or the
quantity of the Work as it has been performed have been
exhaustive, extended to every aspect of the Work in
progress, or involved detailed inspections of the Work
beyond the responsibilities specifically assigned to
ENGINEER in the Contract Documents; or (ii) that
there may not be other matters or issues between the
parties that tnight entitle CONTRACTOR to be paid
additionally by OWNER or entitle OWNER to withhold
payment to CONTRACTOR.
4. Neither ENGINEER's review of
CONTRACTOR's Work for the purposes of recom-
mending payments nor ENGINEER's recommendation
of any payment, including final payment, will impose
responsibilitY on ENGINEER to supervise, direct, or
control the Work or for the means, methods, techniques,
sequences, or procedures of construction, or the safety
precautions and programs incident thereto, or for CON-
TRACTOR's failure to comply with Laws and Regu-
lations applicable to CONTRACTOR's performance of
the Work. Additionally, said review or recommendation
will not impose responsibility on ENGINEER to make
any examination to ascenain how or for what purposes
CONTRACTOR has used the moneys paid on account of
the Contract Price, or to determine that title to any of
the Work, materials, or equipment has passed to
OWNER free and clear of any Liens.
5. ENGINEER may refuse to recommend the
whole or any part of any payment if, in ENGINEER's
opinion, it would be incorrect to make the representa-
tions to OWNER referred to in paragraph 14.02.B.2.
ENGINEER may also refuse to recommend any such
payment or, because of subsequently discovered
evidence or the results of subsequent inspections or tests,
revise or revoke any such payment recommendation
previously made, to such extent as may be necessary in
ENGINEER's opinion to protect OWNER from loss
because:
a. the Work is defective, or completed Work
has been damaged, requiring correction or replace-
ment; '.
b. the Contract Price has been reduced by
Written Amendment or Change Orders;
c. OWNER has been required to correct
defective Work or complete Work in accordance
with paragraph 13.09; or
d. ENGINEER has actual knowledge of the
occurrence of any of the events enumerated in para-
graph 15.02.A.
4'
C. Payment Becomes Due
1. Ten days after presentation of the Application
for Payment to OWNER with ENGINEER's recom-
mendation, the amount recommended will (subject to the
provisions of paragraph 14.02.D) become due, and when
due will be paid by OWNER to CONTRACTOR.
D. Reduction in Payment
1. OWNER may refuse to make payment of the
full amount recommended by ENGINEER because:
a. claims have been made against OWNER on
account of CONTRACTOR's performance or fur-
nishing of the Work;
b. Liens have been filed in connection with the
Work, except where CONTRACTOR has delivered
a specific Bond satisfactory to OWNER to secure
the satisfaction and discharge of such Liens;
c. there are other items entitling OWNER to
a set-off against the amount recommended; or
d. OWNER has actual knowledge of the occur-
rence of any of the events enumerated in paragraphs
14.02.B.5.a through 14.02.B.5.c or paragraph
15.02.A.
2. If OWNER refuses to make payment of the full
amount recommended by ENGINEER, OWNER must
give CONTRACTOR immediate written notice (with a
copy to ENGINEER) stating the reasons for such action
and promptly pay . CONTRACTOR . any amount
remaining after deduction of the amount so withheld.
OWNER shall promptly pay CONTRACTOR the
amount so withheld, or any adjustment thereto agreed to
by OWNER and CONTRACTOR, when CONTRAC-
TOR corrects to OWNER's satisfaction the reasons for
such action.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. If it is subsequently determined that OWNER's
refusal of payment was not justified, the amount
wrongfully withheld shall be treated as an amount due as
determined by paragraph 14.02.C.1.
14.03 CONTRACl'OR's Warranty of Title
A. CONTRACTOR warrants and guarantees that title
to all Work, materials, and equipment covered by any
Application for Payment, whether incorporated in the Project
or not, will pass to OWNER no later than the time of
payment free and clear of all Liens.
14.04 Substantial Completion
A. When CONTRACTOR considers the entire Work
ready for its intended use CONTRACTOR shall notify
OWNER and ENGINEER in writing that the entire Work is
substantially complete (except for items specifically listed by
CONTRACTOR as incomplete) and request that ENGINEER
issue a cenificate of Substantial Completion. Promptly
thereafter, OWNER., CONTRACTOR, and ENGIN.EER
shall make an inspection of the Work to determine the status
of completion. If ENGINEER does not consider the Work
substantially complete, ENGINEER will notify
CONTRACTOR in writing giving the reasons therefor. If
ENGINEER considers the Work substantially complete,
ENGINEER will prepare and deliver to OWNER a tentative
certificate of Substantial Completion which shall fix the date
of Substantial Completion. There shall be attached to the
certificate a tentative list of items to. be completed or
corrected before fmal payment. OWNER shall have seven
days after receipt of the tentative certificate during which to
make written objection to ENGINEER as to any provisions
of the certificate or attached list. If, after considering such
objections, ENGINEER concludes that the Work is not
substantially complete, ENGINEER will within 14 days after
submission of the tentative cenificate to OWNER notify
CONTRACTOR in writing, stating the reasons therefor. If,
after consideration of OWNER's objections, ENGINEER
considers the Work substantially complete, ENGINEER will
within said 14 days execute and deliver to OWNER and
CONTRACTOR a defmitive certificate of Substantial
Completion (with a revised tentative list of items to be
completed or corrected) reflecting such changes from the
tentative certificate as ENGINEER believes justified after
consideration of any objections from OWNER. At the time
of delivery of the tentative certificate of Substantial Comple-
tion ENGINEER will deliver to OWNER and CONTRAC~
TOR a written recommendation as to division of responsibili-
00700 - 38
.
.
ties pending fmal payment between OWNER and
CONTRACTOR with respect to security, operation, safety,
and protection of the Work, maintenance, heat, utilities,
insurance, and warranties and guarantees. Unless OWNER
and CONTRACTOR agree otherwise in writing and so
inform ENGINEER in writing prior to ENGINEER's issuing
the definitive certificate of Substantial Completion,
ENGINEER's aforesaid recommendation will be binding on
OWNER and CONTRACTOR until fmal payment.
.
.
.
B. OWNER shall have the right to exclude
CONTRACTOR from the Site after the date of Substantial
Completion, but OWNER shall allow CONTRACTOR
reasonable access to complete or correct items on the
tentative list.
.
.
14.05 Partial Utilization
.
A. Use by OWNER at OWNER's option of any
substantially completed part of the Work which has
specifically been identified in the Contract Documents, or
which OWNER, ENGINEER, and CONTRACTOR agree
constitutes a separately functioning and usable part of the
Work that can be used by OWNER for its intended purpose
without significant interference with CONTRACTOR's
performance of the remainder of the Work, may be
accomplished prior to Substantial CoIttpletion of all the Work
subject to the following conditions.
.
.
.
1. OWNER at any time may request CON-
TRACTOR in writing to permit OWNER to use any
such part of the Work which OWNER believes to be
ready for its intended use and substantially complete. If
CONTRACTOR agrees that such pan of the Work is
substantially complete, CONTRACTOR will cenify to
OWNER and ENGINEER that such part of the Work is
substantially complete and request ENGINEER to issue
a certificate of Substantial Completion for that pan of
the Work. CONTRACTOR at any time may notify
OWNER and ENGINEER in writing that
CONTRACTOR considers any such pan of the Work
ready for its intended use and substantially complete and
request ENGINEER to issue a certificate of Substantial
Completion for that pan of the Work. Within a
reasonable time after either such request, OWNER,
CONTRACTOR, and ENGINEER shall make an
inspection of that pan of the Work to determine its status
of completion. If ENGINEER does not consider that
pan of the Work to be substantially complete,
ENGINEER will notify OWNER and CONTRACTOR
in writing giving the reasons therefor. If ENGINEER
considers that part of the Work to be substantially
complete, the provisions of paragraph 14.04 will apply
with respect to certification of Substantial Completion of
that pan of the Work and the division of responsibility
in respect thereof and access theretb.
.
.
.
.
.
.
.
.
;w
2. No occupancy or separate operation of pan of
the Work may occur prior to compliance with the
requirements of paragraph 5.10 regarding property
insurance.
14.06 Final Inspection
A. Upon written notice from CONTRACtOR that the
entire Work or an agreed portion thereof is complete,
ENGINEER will promptly make a final inspection with
OWNER and CONTRACTOR and will notify CON-
TRACTOR in writing of all paniculars in which this
inspection reveals that the Work is incomplete or defective.
CONTRACTOR shall immediately take such measures as are
necessary to complete such Work or remedy such
deficiencies.
14.07 Final Payment
A. Application for Payment
1. After CONTRACTOR has, in the opinion of
ENGINEER, satisfactorily completed all corrections
identified during the fmal inspection and has delivered,
in accordance with the Contract Docwnents, all main-
tenance and operating instructions, schedules, guaran-
tees, Bonds, certificates or other evidence of insurance
certificates of inspection, marked-up record documents
(as provided in paragraph 6.12), and other documents,
CONTRACTOR may make application for final
payment following the procedure for progress payments.
2. The fmal Application for Payment shall be
accompanied (except as previously delivered) by: (i) all
documentation called for in the Contract Documents,
including but not limited to the evidence of insurance
required by subparagraph 5.04.B.7; (ii) consent of the
surety, if any, to fmal payment; and (iii) complete and
legally effective releases or waivers (satisfactory to
OWNER) of all Lien rights arising out of Or Liens filed
in connection with the Work.
3. In lieu of the releases or waivers of Liens
specified in paragraph 14.07.A.2 and as approved by
OWNER, CONTRACTOR may furnish receipts Or
releases in full and an affidavit of CONTRACTOR that:
(i) the releases and receipts include all labOr, services,
material, and equipment for which a Lien could be filed;
and (ii) all payrolls, material and equipment bills, and
other indebtedness connected with the Work for which
OWNER or OWNER's property might in any way be
responsible have been paid or otherwise satisfied. If any
Subcontractor or Supplier fails to furnish such a release
or receipt in full, CONTRACTOR may furnish a Bond
or other collateral satisfactory to OWNER to indemnify
OWNER against any Lien.
00700 - 39
I
.
I
2.03
MULCH
The mulch material shall be Type 1, per MnDOT 3882.
WOOD FIBER BLANKET
The wood fiber blanket shall be the High Velocity Type per MnDOT 3.885.
I
2.04
.
.
PART 3 - CONSTRUCTION REQUIREMENTS
3.01
GENERAL
All construction activities under this section shall be performed in accordance to MnDOT
2575 except as modified below.
SEEDING
Within 48 hours of completion of site grading operations in a given watershed area, all
disturbed areas shall be seeded and mulched. Seed shall be applied at the rate of 50
pounds per acre or 50 kg. per hectare. All areas seeded shall be mulched and disk
anchored, unless wood fiber blanket is placed.
.
3.02
.
.
3.03
FERTILIZER
All areas seeded shall be fertilized. The fertilizers shall be dry and shall contain available
nitrogen, phosphoric acid and. potash in proportions which will supply the minimum quantities
of these plant foods.
.
.
3.04
BLACK DIRT
All placement of black dirt behind curbing shall be done prior to paving.
The Contractor shall be aware that the quantities of sod and seed used next to the curb shall
be at the Owner's discretion and that they may be changed or deleted with no change in the
unit price.
.
.
PART 4 - MEASUREMENT AND PAYMENT
The work of this section shall be measured and paid for pursuant to MnDOT 2575. It shall include the
following bid items:
1. Seeding (acre - ac)
2. Mulch Material, Type 1 (ton)
3. Disk Anchoring (acre - ac)
4. Wood Fiber Blankets, Type High Velocity: Square Yard (s.y.)
5. Sod (square yard - s.y.)
.
.
.
.
The Contractor shall have the topsoil tested to determine the type and application rate of fertilizers to use. For
bidding purposes, the Contractor shall use an application rate of 300 pounds per acre of a 20-10-10 fertilizer.
.
I
.
2
.