October 18,2002
RE: Albertville, Minnesota
Kollville Estates Second Addition
SEH No. A-ALBEV0211.00 14
Matt Froelich
Heart of the Lakes Construction, Inc.
P.O. Box 1166
Monticello, MN 55362
Dear Matt:
I received your letter, dated October 18, 2002, regarding the Kollville Estates Second Addition
development. I understand the difficulty you are experiencing in maintaining erosion control;
however, the City of Albertville is responsible for enforcing the NPDES storm water discharge
permit requirements.
We have tried to be flexible when working with all builders to enforce the erosion control
requirements. The proposal you outlined in your letter is a good first step, and I am willing to work
with you to implement it with the exception of item 3. I would like to remove the subjectivity from
item 3 and have the streets swept on a daily basis. Given the amount of work that is going on at the
site and the other conditions you have outlined in your letter, it seems like the streets would need to
be swept on a daily basis anyway.
If this is agreeable to you, I will approve the submitted lot surveys.
eter J. Carlson, . .
Albertville City Engineer
sl
c: Linda Goeb, City Administrator
Jon Sutherland, City Building Official
Mike Couri, City Attorney
Scott Dahlke, Quality Site Design
w:lalbevI0211 Icorr\l- froelich 10 1802.doc
Short Elliott Hendrickson Inc.
Your Trusted Resource
Equal Opportunity Employer