2000-11-30 Punch List
'Jf
PUNCH LIST
OWNER
Pilot Land Development
DATE OF CURRENT ISSUE 11/30/00
DATE OF ORIGINAL ISSUE 10/30/00
SUBSTANTIAL COMPLETION
FINAL COMPLETION
2000 Cedar Creek South Fourth Addition, Albertville, MN
CONTRACTOR Latour Construction
SEHNO.
OWNER NO.
PROJECT
A-ALBEVOO 11.00
Below is a list of items which must be completed or corrected prior to final acceptance of the subject project.
A completion of these items does not in any way relieve the Contractor of the responsibility to complete the
project in accordance with all Contract Documents.
Item Item Date Comments Date
No. Reviewed Accepted
1 Cut back drain tile, grout, and clean all 11/30/00 No Attempt
catch basins.
2 Move silt fence behind hydrants (6 feet 11/30/00 No Attempt
minimum radius) for access.
3 Attach approved hydrant flags to all 11/30/00 No Attempt
hydrants.
4 Replace gate valve box at east end of 11/30100 No Attempt
project.
5 City to check all gate valves for proper 11/30/00 Have to wait until # 4 is
operation. complete
6 Fine grade around hydrants and adjust all 11/30/00 No Attempt
gate valves to finish grade.
7 Verify all required testing has been 11/30100
completed.
8 Bituminous wear course to be placed in 11/30/00 2001
spring of 2001.
9 Turf restoration in all disturbed right-of- 11/30/00 No Attempt
way areas.
10 Clean street of dirt and debris prior to 11/30100 Fairly Clean 11/30/00
snowfall.
PROVIDE 48 HOURS NOTICE PRIOR TO THE START OF TIllS WORK. THIS WORK SHOULD BE
COMPLETED IN ACCORDANCE WITH THE PROVISIONS OF ARTICLE 3 (CONTRACT TIME) OF
THE AGREEMENT.