2005-04-20 Punch List
PUNCH LIST
CONTRACTOR
SEH NO.
OWNER NO.
PROJECT
Kuechle Underground, Inc.
DATE OF ORIGINAL ISSUE
SUBSTANTIAL COMPLETION
FINAL COMPLETION
04/20/05
05/19/04 (6th)
05/02/02(4 th)
06/19/01 (3rd)
10/27/00(1 st)
City of Albertville
DATE OF CURRENT ISSUE
OWNER
A-ALBEV 0212
N/A
Albert Villas 1-6 Additions, Albertville, MN
Below is a list of items, which must be completed or corrected prior to final acceptance of the subject project. A
completion of these items does not in any way relieve the Contractor of the responsibility to complete the project
in accordance with all Contract Documents.
Item Date Date
No. Item Reviewed Comments Accepted
I. Clean storm sewer as needed 6ID Addition
2. Touchup grout on Sanitary sewer and storm 6th Addition
sewer rings as needed prior to wear course.
Replace broken curb and sidewalk prior to
3. wear course placement. Call RPR to 6th addition
arrange walk-through
4. Top section on gate valve box broken at 6th addition
hydrant at lot 25, b1k 7
Pond inlets are washing out. Re-grade
5. storm water pond (some filling may be 6th addition
required) to stabilize slopes in vicinity of
storm sewer outlets.
Adjust manholes and gate valves prior to
wear course (1/2" below finished wear). If
6. wear course not installed prior to snowfall, 6th addition
ensure all manhole, gate valves, and cross
gutters are ramped or lowered for snow
plows.
7. Install wear course 6ID addition
8. Restore major washouts at entrance culverts 6th addition, temporarily fIxed
9. Clean out all pick holes after wear course is 6th addition
installed
Remove all silt fence once sufficient
10. vegetation is established. Contact engineer 6th addition
prior to removal to ensure sufficient
vegetation is established
II. Remove all fabric from CB's 4/20/05 3rd, 4ID, and 6ID addition
(3RD & 4TH done 4/20/05)
County Ditch No.9 needs cleaning (silt and
12. garbage) at both entrances and throughout 3rd, 4th ,6th addition
proj ect area.
1
Item Date Date
No. Item Reviewed Comments Accepted
13. Apron south of CB 9 needs band to tie 4/20/05 4th addition 4/20/05
flared end
14. Sediment needs to be cleaned from ponds 4ffi addition
15. Slopes at outlet need flattening, too steep 3rd addition, Ditch structure
south of Kali, parallel to Kagan
Sidewalks and curb replacement, as marked
16. in field. Also, saw and seal curb as marked 3rd 4th additions
,
in field
Furnish lift station spare parts kit to City:
17. Wear rings, mechanical seals, bearings, 0- 4/20/05 3rd addition, lift station 4/20/05
rings and gaskets, fuses, all in waterproof
container. See City Specifications
18. Install vent pipe screen at wet well 4/20/05 3rd addition, lift station 4/20/05
19. Establish wetland buffer areas per approved 3rd 4th and 6th additions
plans. ' ,
20. Construct bituminous trail as per approved 6th addition
plan. Contact RPR prior to construction.
21. Restore turf for areas disturbed by 6th addition
installation of drain tile lines.
22. Remove concrete bridge structure over 6th addition
County Ditch No.9 near Albertvillas Park
23. Remove construction debris and washout 4th addition
material in County Ditch No.9 at 49th street.
PROVIDE 48 HOURS NOTICE PRIOR TO THE START OF TillS WORK. TillS WORK SHOULD BE
COMPLETED IN ACCORDANCE WITH THE PROVISIONS OF ARTICLE 3 (CONTRACT TIME) OF THE
AGREEMENT.
REMARKS:
Issued By: Russ Bly
Title: RPR
djg
c: Bob Moberg, SEH
Russ Bly, SEH
Larry Kruse, City of Albertville
John Middendorf, City of Albertville
Rick Lewandowski, Edina Development
Craig Schlichting, Plowe Engineering, Inc.
Matt Davich, E.G. Rud & Sons, Inc.
Kuechle Underground, Inc.