SEH MEMORANDUM
TO: Larry Kruse
Albertville City Administrator
FROM: Robert L. Moberg, PE
Project Manager
DATE: December 13, 2004
RE: Mud Lake Water Main Crossing -Albertville, Minnesota
SEH No. P-ALBEV0508.00
This memorandum serves as a letter proposal for professional services related to designing a water main
crossing of Mud Lake. The crossing is necessary to serve the proposed Hunter's Pass Estates development
which is anticipated to proceed with construction in 2005. The crossing of Mud Lake would be made to
interconnect the proposed development with the Towne Lakes development.
Our proposed scope of services will include:
1. Topographic survey on the west side of Mud Lake.
2. Geotechnical investigation of the proposed crossing route. Soil borings will be taken in late
January 2005 when ice thickness is at maximum depth. Soil borings will be performed by Braun
Intertec.
3. Preparation of a geotechnical report based on results of the soil borings.
4. Selection of alignment, profile, and construction method for the crossing.
5. Preparation of final plans and specifications for construction.
We anticipate the Hunter's Pass Estates developer will incorporate the plans and specifications for the
water main crossing into their bidding documents and that construction will be done as a single project.
We propose to provide the services identified herein for a maximum not-to-exceed amount of $19,200.
This amount includes $7,015 for geotechnical work by Braun Intertec. Our services will be provided on
an hourly basis at our standard billing rates, including reimbursable expenses.
If you are in agreement with the contents of this memorandum, please sign both copies of the document
and return one to SEH.
Robert L. Moberg, PE
PrincipaUProject Manager