2001-12-01 Punch List
PUNCH LIST
OWNER
CONTRACTOR
SEH NO.
OWNER NO.
PROJECT
City of Albertville
Kuechle Underground, Inc.
DATE OF CURRENT ISSUE
DATE OF ORIGINAL ISSUE
SUBSTANTIAL COMPLETION
FINAL COMPLETION
12/10/01
10/30/01
A-ALBEV 0109.00
N/A
2001 Albert Villas 3 Addition, Albertville, MN
Below is a list of items which must be completed or corrected prior to final acceptance of the subject project. A
completion of these items does not in any way relieve the Contractor of the responsibility to complete the project
in accordance with all Contract Documents.
Item Date Date
No. Item Reviewed Comments Accented
1. MH's # 3,5, and 12 have joints that are
leaking which must be sealed.
Silt fence is non-functioning or non-existant
2. on a large portion of county ditch, both
sides, and through various areas of Villas 4
grading - PCA meeting Oct 31.
Silt fence to be installed back of curb or
walk by 5' where vegetation has not
3. exceeded 4" high consistant dense growth.
Kaiser Ave, Kahler Ct., Kagan Ave., Kahl
Ave., and spots on Kal: west side and all of
east side.
4. Provide sanitary sewer televising tapes of
Villas 3.
5. Street cleaning and curb failures repaired if
any pnor wear course.
Drainage ditch south of control structure
between Kahler Court and Kahl Ave. must
6. be reseeded and portected with fiber
blanket. Mulch is not working. In addition,
control structure has damage from
equipment drive-over which needs repair.
Lift station driveway and south end of
7. Kaiser Ave. must be graded and compacted
for city access and drainage.
8. County ditch culverts to be placed at Kaiser
and at Kagan Ave.
9. SEE SEPARATE LIFT STATION PUNCH
LIST
10.
PROVIDE 48 HOURS NOTICE PRIOR TO THE START OF THIS WORK. THIS WORK SHOULD BE
COMPLETED IN ACCORDANCE WITH THE PROVISIONS OF ARTICLE 3 (CONTRACT TIME) OF THE
AGREEMENT.