2002-04-11 Notice to Proceed 2001 Savitski Lift Station Upgrade~~ ."
DOCUMENT 00630
NOTICE TO PROCEED
To: Barbarossa & Sons, Inc.
11000 93rd Avenue North
PO Box 367
Osseo, MN 55369-0367
Dated: April 11, 2002
Contract: A-ALBEV 0111
Project: 2001 Savitski Lift Station Upgrade, Albertville, MN
You are hereby notified that the Contract Times under the above contract will commence to run on April
11, 2002. By that date, you are to start performing your obligations under the Contract Documents. In accordance
with Article 3 of the Agreement, the date of Substantial Completion is July 1, 2002, and the date of readiness for
final payment is July 15, 2002.
Also, before you may start any Work at the Site, you must:
Submit the following to Engineer for approval:
1) Bypass Pumping Plan
2) Traffic Control Plan
Please return two acknowledged copies of this Notice to Proceed promptly.
SEH
~/ !~ ry
- _ Titla: Project Engineer
ACCEPTANCE OF NOTICE
Receipt of the above Notice to Proceed is hereby acknowledged by BARBAROSSA & SONS, INC. this
`7 ~ day of ~' ~, , ~ , 2002.
~` ~ r--_
By ~..
Title „~: ~ _ ' ~,,,--
W:\albev\Olll\specs\preceed.dec