2002-05-02 Punch List
"
PUNCH LIST
OWNER
CONTRACTOR
SEHNO.
OWNER NO.
PROJECT
City of Albertville
Kuechle Underground, Inc.
DATE OF CURRENT ISSUE
DATE OF ORIGINAL ISSUE
SUBSTANTIAL COMPLETION
FINAL COMPLETION
05/02/02
12/7/01
A-ALBEV 0109.00
N/A
2001 Albert Villas 3 Addition - Lift Station, Albertville, MN
Below is a list of items which must be completed or corrected prior to final acceptance of the subject projectA
completion of these items does not in any way relieve the Contractor of the responsibility to complete the
project in accordance with all Contract Documents.
Item Date Date
No. Item Reviewed Comments Accepted
1. Replace stainless steel control panel 05/02/02 Watch for worsening
enclosure - outer surface is rusting.
Install stainless steel guide rails - replace .
2. galvanized with stainless steel. Center guide 05/02/02 Done but remove galvanized 05/02/02
rail brackets half the distance from top to from area
bottom.
Install control panel skirt - control panel
3. skirt installed backwards and is missing 05/02/02 No
several screws.
4. Remove all mud and debris from pumps and 05/02/02 Done 05/02/02
wet well invert.
5. Install generator receptacle in control panel. 05/02/02 Done 05/02/02
6. Install separate circuit breaker in control 05/02/02 Circuit breaker is there but light
panel for yard light. doesn't work.
Furnish lift station spare parts kit to City:
7. wear rings, mechanical seals, bearings, 0- 05/02/02
rings and gaskets, fuses, all in waterproof
container. See City specifications.
8. Install vent pipe screen at wet well. 05/02/02 No screen
9. Weld two additional hooks on pump power 05/02/02 Not done
cable rack.
10. Level and secure control panel base. 05/02/02 Door opens hard and rubs.
11. Grade lift station site for proper drainage 05/02/02 Park erosion and Kaiser very
and establish vegetation. soft. Hard access.
12. Grade and compact driveway, ready for
paVIng.
Verify field wiring matches wiring
13. schematics (at the request of Larry
Christenson - Electric Pump Field Service
Technician).
PROVIDE 48 HOURS NOTICE PRIOR TO THE START OF THIS WORK. THIS WORK SHOULD BE
COMPLETED IN ACCORDANCE WITH THE PROVISIONS OF ARTICLE 3 (CONTRACT TIME) OF THE
AGREEMENT.
1
REMARKS:
Issued By: Mike Czech
Title: RPR
mdh
c: Pete Carlson SEH
Scott Hedlund, SEH
Linda Goeb, City of Albertville
Tim Guimont, City of Albertville
Rick Lewandowski, Edina Development
Craig Schlichting, Plowe Engineering, Inc.
Kuechle Underground, Inc.
w:lalbevl0109\specs\punchlist-lift st..doc
2