1991-07-02 CC Minutes Special
.
.
.
ALBERTVILLE CITY COUNCIL
July 2, 1991
Albertville City Hall
7:30 PM
PRESENT: Mayor Jim Walsh, Councilmen Donatus Vetsch, Mark
Barthel, and Duane Berning, Engineer Thore Meyer, Clerk Linda
Houghton
Mayor Walsh called the special meeting to order. The purpose
of the meeting is to review the bids received and award the bid for
the 1991-1 Improvement Project for Westwind Second Addition.
Thore.presented the bid tabulation. All bids were properly
submi t ted by responsibl e contractors. The following bids were
received:
Redstone Construction Co. Inc.
Latour Construction
Buffalo Bituminous Inc.
Northdale Construction
Bonine Excavating
Annandale Contracting Inc.
S. J. Louis Construction Inc.
B & D Underground Inc.
$221,600.34
$232,838.40
$258,721.75
$269,086.45
$270,699.37
$270,812.25
$291,738.70
$295,356.00
Thore recommended the Council award a contract to Redstone
Construction Co. Inc. in the amount of $221,600.34. Although Thore
has never worked with Redstone Construction, he has checked the
references of Redstone and Redstone has good recommendations.
Barthel made a motion to award the contract for the 1991-1
Improvement Project (Westwind Second Addition) to Redstone
Construction Co. Inc. of Mora, MN, in the amount of $221,600.34.
Vetsch seconded the motion. All voted aye.
Berning made a motion to adjourn.
motion. All voted aye.