2000-11-29 Punch List
PUNCH LIST
OWNER
DATE OF CURRENT ISSUE 11/29/00
DATE OF ORIGINAL ISSUE 10/30/00
SUBSTANTIAL COMPLETION
FINAL COMPLETION
Cedar Creek South Sixth Addition. Albertville, MN
Pilot Land Development
CONTRACTOR Kuechle Underground
SEHNO.
OWNER NO.
PROJECT
A-ALBEVOI05.00
Below is a list of items which must be completed or corrected prior to final acceptance of the subject project.
A completion of these items does not in any way relieve the Contractor of the responsibility to complete the
project in accordance with all Contract Documents.
Item Item Date Comments Date
No. Reviewed Accepted
1 Adjust hydrant at north end of project to 11/29/00 Done but needs hydrant flags
finish grade. on all hydrants
2 Install chimney seal on existing manhole 11/29/00 Nothing Attempted
and adjust casting to finish grade.
3 Adjust manhole at south end of project 11/29/00 Done 11/29/00
to finish grade.
4 Clean and grout all catch basins. 11/29/00 Nothing Attempted
5 Fine grade around all hydrants and adjust 11/29/00 Nothing Attempted
gate valves to finish grade.
6 Bituminous wear course to be placed in 11/29/00 Nothing Attempted
spring of 200 1.
PROVIDE 48 HOURS NOTICE PRIOR TO THE START OF THIS WORK. THIS WORK SHOULD BE
COMPLETED IN ACCORDANCE WITH THE PROVISIONS OF ARTICLE3 (CONTRACT TIME) OF
THE AGREEMENT.
REMARKS:
Issued By: Wayne c.B. Stark, P.E.
Title: Project Engineer
djg
c: Wayne Stark, SEH
Pete Carlson, SEH
Mike Czech, SEH
John Wilczek, Meyer-Rohlin
Linda Goeb, City of Albertville
W:\albevlO lO5\specs\punch.doc
Tim Guimont, City of Albertville
Don Jensen, Pilot Land Development
Don Kuechle, Kuechle Underground