2005-04-06 Planning Report NORTHWEST ASSOCIATED CONSULTANTS, INC. 4800 Olson Memorial Highway, Suite 202, Golden Valley, MN 55422 Telephone: 763.231.2555 Facsimile: 763.231.2561 planners@nacplanning.com PLANNING REPORT TO: Larry Kruse, City Administrator FROM: Michael Darrow I Alan Brixius DATE: April 6, 2005 RE: Albertville - Parkside Commercial CUP/PUD and Site Plan Approval NAC FILE: 163.06 - 05.07 BACKGROUND Premier Development Group, LLC has submitted an application for a CUP-PUD and site plan approval to allow for three office buildings with in the site. A similar plan was introduced to the Planning Commission in June 2004. During that time, Kent Roessler withdrew the application. Subsequently, Premier Development Group entered into an agreement with Mr. Roessler for the acquisition of the subject site. The site area is 232,181 square feet or 5.33 acres and is located west of Highway 19 and north of 5ih Street Northeast. The area is surrounded by residential uses to the south and west and commercial uses north and east. The site is zoned B-2A, Special Business District. Original preliminary plat approval was granted in March of 2000. The plat was part of a two lot, 7.21 acre subdivision. Casey's General Store was granted a conditional use permit and site plan approval in 2001. The proposed plan calls for development on Lot 2, Block 1. Because the proposed development shares access with Casey's, a shared access easement agreement will be a condition of approval. The following is a technical review based upon plans received on March 15, 2005: Attached for reference: Exhibit A: Exhibit B: Exhibit C: Exhibit D: Exhibit E: City Engineer's Comments Site Plan, Code Review, and Details Building and Elevations 1 Building and Elevations 2 & 3 Landscape Plan 5 Exhibit F: Exhibit G: Exhibit H: Exhibit I: Exhibit J: Schematic Emergency Vehicle Access Plan Existing Conditions and Proposed Layout Grading and Construction Plan Standard Details Lighting Plan ISSUES ANALYSIS Zoning. The property is zoned B-2A, Special Business District. The purpose of the B- 2A District is to provide for quality, limited retail and service commercial development that serves both local and regional needs. A Commercial PUD is a conditional use within the B-2A District and is subject to the requirements of Section 2700 of the Zoning Ordinance. The Comprehensive Plan states that this area should continue to be developed as commercial uses. The proposed use is an office condominium. The developer is proposing that the building be managed through an office condominium arrangement. The developer has prepared the necessary declarations, by-laws, and related association documents for the creation of a Common Interest Community (CIC) development. The City will need to make the determination as to if this type of arrangement is appropriate. Lot Area and Setbacks. The minimum lot area requirements are shown below: Lot Area Lot Width Front yard Setback Side yard Setback Rear Yard Setback Lot Coverage Required 1 acre 150 feet 35 feet 1 0 feet 20 feet 80% Proposed 5.33 acres 298 feet 35 feet 35 feet 50 Building Coverage =16% Green Space Coverage =53% The proposed site is in conformance with the minimum required lot area. The lot includes three office buildings ranging in size from 7,520 square feet (building 1) and 14,830 square feet (building 2 & 3). An existing wetland is located within the northern portion of the site area. The applicant has identified a buffer area between that area and the parking stalls and buildings. Parking and Circulation. The Zoning Ordinance requires 1 stall per 200 square feet of office space. There is a total of 37,180 square feet of office space proposed. Based upon the parking required by Ordinance a total of 167 stalls are required. The applicant has identified a total of 167 stalls and therefore is in compliance with the Ordinance. 6 The internal drive isles are measured at 24 feet with a parking stall size of 9 feet by 20 feet. The proposed parking plan meets the requirements of the Zoning Ordinance in regard to the total stalls needed, curbing, and accessible spaces. The developer's plan provides parking stalls northwest of the curb cut into Casey's. This design will avoid a traffic conflict point within that area. The curb cut is also measured at 60 feet. The increased size of the curb cut will allow for truck traffic to and from Casey's as well as the office complex. Access to the site will come off of an existing access drive from sih Street NE. No additional curb cuts are proposed for the site. A shared access easement agreement will be a condition of approval. During concept plan review the city had inquired about a through street connecting the site from sih Street from the area north of the site. Due to topographic conditions and the wetlands within the site, a through-street would not be practical. Traffic Maneuverability. The developer has met with the Albertville Fire Chief and Futrell Fire Consultant and Design Inc. The plan shows a 33 foot inside turning radius and a minimum of 43 feet outside turning radius which meets the fire departments apparatus road requirements. The overall plan is sufficient for truck traffic needed for garage pick-ups and deliveries. As a condition of approval, all curb islands will be required to be raised with landscaped plantings. Building Design and Building Operation. The developer has provided building elevations for the three office buildings. The majority of the building's exterior will be face brick, stucco, and prefinished metal fascia. Additionally, the applicant is proposing recessed lighting near the entryways to the building. The same materials will be required for all ground signage and trash enclosures. The developer is proposing that the building be managed through an office condominium arrangement. The developer has prepared the necessary declarations, by-laws, and related association documents for the creation of a Common Interest Community (CIC) development. The City will need to make the determination as to if this type of arrangement is appropriate. The by-laws and related documents are subject to the review of the City Attorney. As a condition of approval, the City may wish to restrict the type of uses within the CUP/PUD to professional office uses, clinics, or personal or on-site services. This will ensure that no other high volume retail type of use that may impact the overall site such as those businesses that require a high degree of truck traffic or storage from occupying space within the buildings. Screening and Landscaping. During the review of a similar application presented to the Planning Commission in June of 2004, the City discussed the option of constructing a berm west of the proposed office buildings. A large dirt pile currently exists due to the grading completed as part of the Casey's building to the east. 7 The developer is proposing to keep the existing spruce trees on the western portion of the site and plant an additional row of trees. A total of 24 new spruce trees of between 6' and 8 feet tall are proposed. This row would be planted in staggered rows and would offer additional screening within that area. Additionally, 13 new ornamental deciduous trees are proposed near the rear windows of the office complex. The Planning Commission and City Council will need to make the determination as to if the buildings will provide sufficient screening in relation to the overall plan. As a condition of approval, the applicant should submit a cross section of the buildings and proposed landscaping to ensure that adequate screening is provided for the site. Staff would recommend that additional plantings be provided in the northeastern and southwestern portion of the site plan. This will create a more aesthetically appealing landscaping plan. The developer will be required to provide additional raised landscaped islands within the striped parking stalls at the perimeter of the parking areas. These islands will assist the overall traffic circulation within the site. The developer will be required to verify whether landscaped medians will require irrigation. Irrigation service lines shall be shown on the plans. Grading, Drainage, and Utilities. The developer overall access and easement area within the site. As a condition of approval, all buildings shall be equipped with an automatic fire suppression system and the buildings may not be 58 feet deep. An additional fire hydrant has been proposed at the west end of the parking lot between buildings 2 and 3. Drainage calculations must be submitted to the City Engineer for review and comment. The drainage calculations are needed to verify whether the number of drainage facilities is adequate and whether the proposed pond modifications provide the same level of flood protection as current conditions. An existing pond is located on the northeastern portion of the plan. The existing skimmer system located on the northern portion of the pond will be removed. Silt fencing and other erosion control measures have been identified within the grading and construction plans. The grading, drainage, and utility plan will be subject to the review and approval of the City Engineer. The City Engineer's memorandum dated March 31, 2005 is attached to this report. Lighting. The applicant has submitted a photometric plan and lighting fixture plan. All light posts will be required to be no higher than 20 feet to ensure that the light posts cannot be seen from the residential uses to the west. Additionally, all light fixtures shall be required to be down-lit at a gO-degree cutoff. The Zoning Ordinance states that any exterior lighting on site must be arranged as to deflect light away from public streets. The source of all lights shall be hooded. Any light or combination of lights which cast light on a public street shall not exceed one (1) foot 8 candle as measured from the centerline of said street (s) and any light or combination of lights which cast light onto residential property shall not exceed four (4) foot candles as measured from the property boundary. Based upon the submitted schematic plan, it appears that the plan meets this criteria. Trash Enclosures. Two trash enclosures have been identified on the site. One of the enclosures is located between buildings 2 and 3 and the other is located on the western portion of building 1. The applicant is proposing brick veneer to match the building. Staff has concerns with the size of the enclosure between building 2 and 3. The developer will be required to demonstrate that the size of that enclosure is sufficient to accommodate the refuse between the two buildings. Signage. The applicant has identified two locations for monument signage. The first location is within the northeastern portion of the site and will front C.S.A.H 19. The other location is within the southern portion of the site and will front sih Street. According to the Sign Ordinance, not more that 1 ground sign shall be permitted on any lot. Flexibility from this standard is being sought in order to allow 2 ground signs on one lot. Because of the location on a corner lot as well as the nearby commercial use to the east, an additional ground sign maybe appropriate. The signs will be limited to 12 feet in height and 80 square feet of overall sign face. A comprehensive sign plan which must include sign details, including proposed design, size, height, setbacks, and lighting must be submitted and will be reviewed under a separate sign permit. Wall signage is also proposed on the northern elevation the buildings. According to the Sign Ordinance, not more than 1 sign shall be permitted on the front wall of any principal building. Because multiple tenants are proposed within each building, the building will be limited to 48 square feet of wall signage per tenant bay within the site.. As a condition of approval, the applicant will be required to apply for a sign permit. Park and Trail Dedication. Park dedication was approved during the final plat stage in 2000. No additional park dedication will be required as part of this PUD application. Development Contract. Upon approval of the PUD, the applicant must enter into a development contract. The development contract specifies that sanitary sewer capacity is reserved only for those developments final platted that have paid for such services consistent with the polices of the Comprehensive Plan. The development contract is subject to the review and approval of the City Attorney. CONCLUSION Staff finds that the proposed plan is generally consistent with the Zoning Ordinance. If the Planning Commission recommends approval of the CUP/PUD and Site and Building Plan Review, staff would recommend that the following conditions be required as part of that approval: 9 1. A shared access easement agreement shall be entered into with Casey's. 2. The landscaping plan shall be revised to include the following: a. Black Hills Spruce shall be planted fifteen (15) feet apart in staggered rows and shall be a 6-8 feet tall on the western portion of the site area. b. Additional species and quantities of plantings shall be provided in the northeastern and southwestern portion of the plan. c. A cross-section plan of the western portion of the site shall be submitted for City review and approval. d. All parking islands shall be raised. Additional landscaping planting islands shall be required within the striped areas at the perimeter of each parking area. 3. Uses within the buildings shall be limited to professional offices, clinics, and personal and on-site services. No outdoor storage shall be allowed within the site. 4. The grading, drainage, and utility plans shall be subject to comments found in the City Engineer's report dated March 31, 2005. 5. Monument signage shall be limited to no more than two signs that are no more than twelve (12) feet in height and are no more than eighty (80) square feet of sign face. A separate sign permit will be required for this application. Approval of this application shall not constitute approval sign permit approval. 6. All light poles shall not exceed twenty (20) feet in height. All lights shall be at 90-degree cutoff. 7. The Common Interest Community (CIC) declarations, by-laws, and related association documents shall be subject to the review and approval of the City Attorney. 8. The applicant shall enter into a Development Agreement with the City and shall be subject to the review and approval of the City Attorney. 9. Additional comments from City staff, Planning Commission, and City Council. pc: Jon Sutherland Robert Moberg Mike Couri Roger Fink 5605 West 36th Street, Suite 204 Sf. Louis Park, MN 55416 10