Loading...
2005-08-30 Construction Punch List "~ SEH ~ August 30, 2005 RE: Albertville, Minnesota 2004 Prairie Run SEH No. A-ALBEV0409.00 Mr. Gary Fehn Dennis Fehn Gravel & Excavating PO Box 256 Albertville, MN 55301 Dear Mr. Fehn: Please find enclosed a construction punch list for the subject project. If Fehn Excavating is able to complete the punch list items and all other unfinished work by September 13, 2005, the City of Albertville may be in a position to authorize installation of the bituminous wear course this year. Your prompt attention is appreciated. Please call me at 651.490.2147 if you have questions. Sincerely, i1:!1re~ Project Manager Enclosure urn x:laelalbev\0409(J()\wordlfelm083005.doc c: Larry Kruse, City Administrator Russell Bly, SEH Short Elliott Hendrickson Inc., 3535 Vadnais Center Drive, St. Paul, MN 55110-5196 SEH is an equal opportunity employer I www.sehinc.com I 651.490.2000 I 800.325.2055 I 651.490.2150 fax ~ Jt.. SEH PUNCH LIST Owner: City of Albertville, Minnesota Date of Current Issue: August 29, 2005 Project: 2004 Prairie Run Date of Original Issue: August 29, 2005 City Project No: Contract Completion Date: Substantial Final Contractor: Dennis Fehn Gravel & Excavating, Inc. SEH File: A-ALBEV0409 Date(s) of Inspection(s): August 29, 2005 Below is a List of Items which must be completed or corrected prior to final acceptance of the subject project. Item Date No. Item Description Current Status Accepted 1 Backfill curb and sidewalk with topsoil. 2 Finish pouring sidewalk 3 Grading, tree removal, and tree planting in Robert Heuring property 4 Remove excess dirt from ditch behind Meadow Court, Lot 26. 5 Remove old striping from CR 18 turn lane and put on new striping according to plan. 6 Flush and clean sanitary manhole and sewer lines. 7 Replace curb and sidewalk as needed prior to wear course. 8 Adjust iron to grade (1/2" below finished wear) prior to wear course. 9 Ensure all gate valve in working order (coordinate with City utility dept). 10 Correction of trail along CR 19 - see Engineer for details. 11 Touch up grout on manholes and catch basins as needed prior to wear course. 12 Remove all construction debris from site. 13 Seed and blanket boulevards as directed by Engineer. 14 Some seeding did not take from original application, reseed bare spots. 15 Spray cure on sidewalk and drives without it. 16 Extend 24-inch storm stub an additional 8 feet so sidewalk can be poured at temporary ditch off of Kyler. 17 Clean storm sewer as needed prior to wear course. Punch List Page 2 Item Date No. Item DescriDtion Current Status Accepted 18 Locate all gate valves at hydrants and raise as needed. 19 Replace slab at lift station over wet well- settled and broken. 20 All gate valves need nut risers on them. 21 mstall street signs. 22 mstall silt fence behind curbs and sidewalks. 23 Remove perimeter silt fence. 24 Repair lift station as directed by City utility dept. Please provide 48-hour notice prior to the start of this work. This work should be completed in accordance with the provisions of Article 3 (Contract Time) of the Agreement. Remarks: Issued By: Title: c: Dennis Fehn Gravel & Excavating, me. Robert L. Moberg, SEH Russell Bly, SEH Larry Kruse, City Administrator John Middendorf, City of Albertville Tim Guimont, City of Albertville nm x:laelalbevlO40900lwordlpunchlisI082905.doc