1992-10-15 Escrow Item Costs
MEYER-ROHLIN, INC.
ENGINEERS -LAND SURVEYORS 1111 Hwy. 25 N., Buffalo, Minn. 55313 Phone 612 - 682-1781
October 15, 1992
Mike Couri
Radzwill Law Office
PO Box 369
St. Michael, MN 55376
Re: Psyks 5th Addition
Dear Mike,
The following is a breakdown of the escrow item costs attributed
to the above-referenced project.
1. Petition Items (Public
a) Sanitary Sewer
b) Water Mains
c) Storm Sewer
d) Streets
Improvements)
$30,234.50
$45,041.10
$68,174.95
$74,071.80
Subtotal
$218,071.80
e) Contingencies (5%)
f) Engineering (18%)
10,903.20
39,253.00
Total Improvement Costs
$268,228.00
use $268,200.00
2. On- and Off-Site Improvements
Based upon the 19-1ot psyk Fifth Addition:
a) Boulevard Improvements
Topsoil and sodding
Front lawn trees
Hard surface driveway &
b) Grading control
$200.00/1ot
30.00/1ot
base 130.00/1ot
50.00/1ot
$410.00 x
19 lots
= $7,790.00
c) Street signs )
d) street cleanup)
lump sum for the development
3,000.00
$10,790.00
use $11,000.00