2005-11-02 CC Joint MeetingCity of Albertville and City of Otsego Joint Meeting
Wednesday, November 2, 2005
Otsego City Hall
7:00 Joint Meeting called to Order by Larry Fournier
1. NEW MACIVER (Cost share discussion)
2. OLD MACIVER
3. CSAH 37 TRAFFIC SIGNAL
4. 70`h STREET IMPROVEMENT PROJECT
5. CSAH 19 & 70th STREET IMPROVEMENTS
6. I-94 STATE AND FEDERAL ACCESS REQUEST
a. Status update
b. Phasing Plan
7. MASTER TRANSPORTATION AGREEMENT (Items 1-6)
8. STMA SCHOOL SITE & UTILITIES
9. OTSEGO CREEK (Update/set meeting)
10 FIRE CONTRACT (Questions, comments, etc.)
11 70TH STREET CORRIDOR STUDY (Access Points)
is
8
•
•
L�
-A
SEH
TO:
FROM:
DATE:
RE:
MEMORANDUM
Larry Kruse
City Administrator
Robert Moberg, PE
Project Manager
February 1, 2005
Albertville, Minnesota
70th Street Corridor - Construction Cost Options
SEH No. A-ALBEV0506.00 14.00
At the request of City staff, I have developed construction cost estimates for installation
of a paved roadway in 701h Street between CSAH 19 and Maciver Avenue. Construction
cost estimates were prepared for four options.
Option 1— Construction of a Two -Lane Rural Roadway on the Existing Gravel Road
Width of the bituminous surface would be 36 feet, allowing for two 12-foot travel lanes
with 6-foot paved shoulders. A 2-foot gravel shoulder would also be installed on both
sides. Typical section would be 4 inches of bituminous on 4 inches of Class 5. Without
knowing the thickness of the existing gravel surface, it is estimated an additional 4 inches
of Class 5 would be adequate to provide the desired strength for a 7-ton roadway. It is
assumed the existing roadbed is wide enough to support a 36-foot wide surface.
Option 2 — Construction of a 10-ton Two -Lane Rural Roadway
Width of bituminous would be 44 feet, allowing for two 12-foot travel lanes with 10-foot
paved shoulders. Typical section would be 6 inches of bituminous on 12 inches of Class 5
on 18 inches of Class 3. To build this section, the existing road core would be removed.
Option 3 — Construction of a Two -Lane Urban Roadway with Curb and Gutter to City
Standards for a City Street
Street width would be 36 feet from curb face to curb face: Typical section would be 5.5
inches of bituminous on 8 inches of Class 5 on 18 inches of Class 3. Storm sewer would
be installed throughout the corridor.
Option 4 — Construction of a Two -Lane Urban Roadway to County Standards
Street width would be 44 feet from curb face to curb face. Typical section would be 6
inches of bituminous on 12 inches of Class 5 on 18 inches of Class 3. Storm sewer would
be installed throughout the corridor.
2
Estimated construction cost for the four options is summarized below.
Option Estimated Costal)
1 $422,000
2 $1,114,000
3 $1,336,000
4 $1,471,000
(1) Includes 10% construction contingency.
Please call me if you have any questions.
tlo
c: Pete Carlson, SEH — St. Cloud
x:sae\albev\050600\cortespondence*mse020105.doc
•
•
3
0 DRAFT- November 2, 2005
AGREEMENT BETWEEN THE CITY OF OTSEGO AND THE CITY OF
ALBERTVILLE REGARDING
IMPROVEMENTS TO 70TH STREET
AGREEMENT entered into this day of , 2005 between the
City of Otsego ("Otsego'), a municipal corporation organized under the laws of the
State of Minnesota, and the City of Albertville ("Albertville"), also a municipal
corporation organized under the laws of the State of Minnesota. For purposes of this
Agreement, Otsego and Albertville may also be collectively described as "the
Cities."
Scope of Project. This Agreement shall identify the roles and responsibilities of
Otsego and Albertville as they relate to improvements to 70th Street, a rural, two-
lane, border street between the two Cities. The proposed project is located on that
segment of 70th Street between CSAH 19 and MacIver Avenue. The project
involves subgrading and installing asphalt surfacing to be centered on the existing
right of way. It is contemplated that this improvement project is an interim
improvement and that 70th Street will be entirely reconstructed within five to ten
years from the date of execution of this Agreement, at which time the Cities agree
to seek funding from County, State or Federal funds for the expansion of 701h
Street to a four -lane minor arterial street. (The City of Otsego shall be the lead
Government Unit for the ultimate expansion to four (4) lanes.)
2. 70th Street Plans and Specifications. Albertville shall be the lead Government
Unit for the project, and it shall, through its City Engineer or another Engineer
acceptable to both Cities, complete the Plans and Specifications to be used for
purposes of bidding the improvement project. The Albertville City Engineer shall
provide copies of the completed Plans and Specifications at least fourteen (14)
days prior to presentation to both City Councils for approval for purposes of
• review and comment. Both Cities shall approve the Plans and Specifications and
4
authorize the bidding for the project prior to the time such advertisement is
published.
3. Awarding of Bid. Upon receipt of bids, the Albertville City Engineer shall
provide the bids and related calculations to the Otsego City Engineer for review
prior to award of bid. In the event that issues are raised by either City relative to
responsiveness of a bid or responsibility of a bidder they shall be resolved by
mutual agreement prior to awarding of a bid. Albertville and Otsego shall both
pass Resolutions Awarding Bid and Authorizing Project to Proceed. Albertville
shall be the party who enters into the contract with the lowest responsible bidder.
The contract shall provide that Otsego shall be indemnified and held harmless
from any claim or cause of action related to the project. Both cities shall provide
contractors with access to necessary portions of their respective right of way.
4. Project Management and Oversight. Albertville and its City Engineer shall be
responsible for management and oversight of the project and shall coordinate with
Otsego staff and the Otsego City Engineer to complete the project. Albertville
shall approve and make progress payments to the contractor after consultation
with Otsego and its City Engineer. Upon such progress payments to the
contractor, Albertville shall invoice Otsego for reimbursement of Otsego's portion
of the payments. Otsego shall remit its reimbursement to Albertville within 30
days of Albertville's invoice. The two Cities shall consult and agree on all issues
revolving retainage or partial payment of requested progress payments. All
reports and correspondence related to contractor payments or disputes shall be
copied to Otsego and its City Engineer.
5. Change Orders. Albertville shall coordinate with Otsego regarding major
change orders and shall inform and copy Otsego and its City Engineer regarding
all change orders. Otsego shall be able to submit comments to Albertville
regarding any change order. Albertville shall have unilateral discretion to
approve up to two (2) change orders which have an aggregate sum of not more
than 5% of the total construction contract. In the event of a change order that
exceeds 5% of the total construction cost or more than two such change orders,
both Cities must approve the change order(s). In the event of any disagreement
between the Cities relative to a proposed change order or change orders, the Cities
shall meet as soon as practicable and make all good faith efforts to resolve the
dispute in a timely manner so as to not delay or adversely affect the project.
6. Construction Schedule. Construction of the 701h Street project is scheduled to
commence during 2005. This Agreement shall remain in effect until December
31, 2006.
7. Project Funding. Otsego and Albertville shall each be responsible for 50% of
the total cost of the project. The cost of the project includes all project related
engineering costs, including construction observation and plans and
• specifications, any project related legal costs, costs of right of way and
5
construction costs. In the event that the project is discontinued for any reason,
each City shall be responsible for 50% of project costs incurred up to the date of
discontinuance. Each City shall also be responsible for 50% of any costs that are
incurred as a result of the discontinuance.
8. Disagreements and Contested Issues. In the event of a disagreement or
contested issue arising from this Agreement or progress of the project, the Cities
agree that every effort will be made to resolve such issues between themselves
prior to initiating the involvement of any third -parties. If the matter cannot be
resolved between the parties both Cities agree to proceed to mediation in order to
resolve the dispute with all mediation related costs split evenly between the
parties. In the event that the dispute cannot be resolved through mediation, the
two parties will agree upon a third party who will hear all issues involved in the
dispute and shall render a decision. Both parties will be bound by this decision
and shall equally divide the costs related to the rendering of the decision. If the
matter in dispute is more than $50,000.00 the decision may be appealed to District
Court.
9. Miscellaneous.
a. Any action or inaction of either Otsego or Albertville shall not
constitute a waiver or amendment to the provisions of this Agreement.
To be binding, amendments or waivers shall be in writing, signed by
the parties and approved by written resolution of both Otsego and
Albertville's City Council. Either City's failure to promptly take legal
action to enforce this Agreement shall not be a waiver or release.
b. If any portion, section, subsection, sentence, clause, paragraph or
phrase of this Agreement is for any reason held invalid, such decision
shall not affect the validity of the remaining portion of this Agreement.
c. Third parties shall have no recourse against either City under this
Agreement.
d. Albertville shall hold Otsego its agents, officers and employees
harmless from any and all claims or causes of action related to the
project, except of claims or causes of action based solely upon the
negligence of Otsego, including all costs incurred as a consequence of
such claim or cause of action, including professional fees, costs,
disbursements and attorney's fees.
e. Albertville shall require that any and all contractors or subcontractors
working on the project shall have adequate public liability insurance in
an amount acceptable to both Cities and with both Cities being named
• as an additional insured.
C1
f This Agreement shall not be considered as any representation to
others, or agreement between the parties that would allow for the
stacking of any applicable insurance coverages in relation to any claim
or cause of action.
g. This written Agreement is the final agreement between the parties and
any previous agreements either oral or in writing are merged into this
Agreement.
h. This Agreement may only be amended or modified by written
addendum to this Agreement signed by both parties.
10. Applicable Law. This Agreement shall be construed under the laws of the State
of Minnesota.
11. Term of Agreement. This Agreement shall be in effect from the date of
execution until December 31, 2006.
ADOPTED this day of May, 2006 by the Otsego City Council.
IN FAVOR:
OPPOSED:
CITY OF OTSEGO
Larry Fournier, Mayor
Judy Hudson, City Clerk
Adopted this _day of May, 2005 by the Albertville City Council.
IN FAVOR:
h
OPPOSED:
CITY OF ALBERTVILLE
Don Peterson, Mayor
Bridget Miller, City Clerk
•
•
0
CSAH 19 & 70TH STREET PROJECT
October 28, 2005
PROJECT SCOPE:
To improve CSAH 19 from the Premium Outlet Mall north beyond 70th Street
Approximately 1200 feet to a four lane urban designed street, with underground
infrastructure to support a future traffic signal.
CSAH 19 & 70th Street
Preliminary Cost Estimate, September 7, 2005
CSAH 19
CSAH 19
70th
Total
South of
North of
Street
70th Street
70th Street
East &
(Mall north)
(1,100 feet)
'West of
CSAH 19
(800 feet)
Jurisdiction
Albertville
$560,000
$365,700
$925,700
31.5%
Otsego
$237,600
$365,700
$603,300
20.5%
Wright County
$988,000
$422,400
$1,410,400
48.0%
$1,548,000
$660,000
$731,400
$2,939,400
100.0%
Wright County
Payment to
Albertville 15 Year
Amortization
$93,584
Wright County
Payment to Otsego
15 Year Amortization
1 $40,010
CSAH 19 designed to a four lane roadway with left and right turn lanes. 70th Street is designed as a two lane with
left and right turn lanes. Traffic signal would be planned for sometime in the future, with underground installed now.
[I
BO L.TON 8L M B N K, I NC_
Consulting Engineers & Surveyors
2638 Shadow Lane, Suite 200 • Chaska, MN 55318
Phone (952) 448-8838 • FAX (952) 448-8805
May 20, 2005
Larry R. Kruse, City Administrator
City of Albertville
P.O. Box 9
5975 Main Avenue NE
Albertville, Minnesota 55301
Re: Avenue — Preliminary Cost -Estimate
Street & Utility Improvements
City of Albertville
BMI Project No. T15.21660
isDear Mr. Kruse:
is
Based on your request, we have prepared a preliminary cost -estimate for street and utility
improvements on Avenue from the former entrance to the wastewater treatment facility (WWTF)
to the existing north/south Avenue (previously improved by the City of Otsego).
We estimate the total cost of the improvements to be approximately $585,000 (see attached). Our
estimate includes 10% for contingencies, 20% for engineering, and 10% for legal, fiscal and
administrative.
For the basis of our estimate, we assumed that the street improvements would be consistent with
the City's typical section for Commercial/Industrial roadways as identified on Standard Detail
Plate STR-8. This detail assumes a 9-ton design. We also assumed that we would continue a
street width of 36' (measured back of curb to back of curb). This street width presently exists on
Avenue from 62"d Street to the entrance to the former WWTF. The total length of improvements
is approximately 1,510'. We have also assumed a 6' wide bituminous trail along the north side of
the roadway.
10
•
•
Prope *
Existing
Otsego
Wright
City of
Improvement
Total Cost
Businesses
Property
County
Albertville
600'
(900')
(420')
(1,080'
Street &
Restoration
$77,178
$115,767
$54,025
$138,930
$385,900
Sanitary Sewer
$18,660
$0.00
$13,062
$33,578
$65,300
Watermain
$17,742
$0.00
$12,419
$31,939
$62,100
Storm Sewer
$14,340
$21,510
$10,038
$25,812
$71,700
Total
$127,920
$137,277
$89,544
$230,259
$585,000
*Note: Approximate front footages.
Street & Restoration Cost/LF - $128.63 (3,000 LF Assessable)
Sanitary Sewer Cost/LF - $31.10 (2,100 LF Assessable)
Watermain Cost/LF - $29.57 (2,100 LF Assessable)
Storm Sewer Cost/LF - $23.90 (3,000 LF Assessable)
Based upon the above assumptions, the following would be the totals for street and utility
assessments:
Existing Business
$127,920
Otsego Property
$137,277
Wright County
$89,544
City of Albertville
$230,259
Total
$585,000
Please call me at 612-817-2446 once you have had time to review this information
Sincerely,
BOLTON & MENK, INC.
Mark D. Kasma, P.E.
Albertville City Engineer
11
A I T, i
Council Workshop
9-20-05
SEH
ISlide 2
•
•
13
Slide 3
9
•
14
Slide 5
•
•
15
Possible Phasing Scenario Given
Financial Impacts
} Build CR full CR 19 interchange and Close
CR 37 West Ramps
2} Build Westbound CC} Road System
3} Build Westbound CD road System
(option 3 complete)
-D ruz�+ 5 7�>, Cq6,
2006 FIRE PROTECTION AGREEMENT
WITH THE CITY OF OTSEGO
This agreement made and entered into by and between the City of Albertville, a
municipal corporation of the County of Wright in the State of Minnesota, and the City of
Otsego, in the County of Wright in the State of Minnesota.
WHEREAS, Otsego desires the services of the fire department of Albertville in case of
fires occurring in Otsego, as well as the emergency medical services of Albertville in case of a
medical emergency, and
WHEREAS, Albertville maintains a volunteer fire department with emergency medical
response capability, which department is available to provide fire protection and emergency
medical response services to properties located in Otsego, and
THEREFORE, it is agreed by and between said parties as follows:
1. Albertville, through its fire department, shall provide fire protection and emergency
medical response services to those properties in Otsego. Such fire protection and
emergency medical response services shall be provided from January 1 through December
31, 2006.
2. Otsego shall agree to pay Albertville $35,227.10 in exchange for the provision of fire
protection and emergency medical response services as described above. Payment due for
the year 2006 shall be made in two installments of $17,613.55 on or before July 1, 2006,
and $17,613.55 on or before December 31, 2006.
3. Albertville's obligation to provide fire protection service and emergency medical response
shall be subject to the following:
a. If road and weather conditions at the time of the call are such that the fire/medical run
cannot be made with reasonable safety to men and equipment, and the decision of the
Fire Chief or his Deputy in charge shall be final in such matter, no obligation arises
under this agreement on the part of the City of Albertville to answer such call.
b. In the event that a sufficient amount of the fire fighting/medical equipment and the
number of volunteer firemen, or both, are committed at the time of the fire call, in sole
judgment of the Fire Chief or his Deputy, to fighting pre-existing fires or attending pre-
existing medical emergencies, so as to render the available equipment and manpower
inadequate to answer a fire or medical call from Otsego, no obligation shall arise under
this agreement to answer such call, and no person or party shall have recourse against
isthe City of Albertville for refusal to answer such call. A pre-existing fire/medical
MAPublic DataTire DepartmentTire Service Contract06 - Otsego.doc I
emergency to which the fire department of Albertville is called previous to receiving the
call from Otsego and which fire is still being fought or medical emergency is still being
attended to by the Albertville Fire Department at the time the call from Otsego is
received.
c. In the event a fire call by Otsego is answered by Albertville, but before the fire in
question is extinguished, the fire fighting equipment or volunteer firemen, or both, are
needed to fight a fire in Albertville or protect property in Albertville from a fire, the
Chief or his Deputy without liability therefore to any person or to Otsego under this
agreement, may in their judgement recall the fire equipment and firemen to Albertville
for the purpose of fighting the fire in Albertville. The judgement of the Fire Chief or his
Deputy shall be final and no person or party shall have recourse against the City of
Albertville for any damages or losses resulting from such action or decision.
4. The parties acknowledge the fact that Albertville may enter into similar contracts with other
municipalities, and acknowledge that Albertville has entered into mutual aid contracts with
other fire departments in other municipalities, and that a fire call under any such contract
preceding a call in Otsego could be a valid and reasonable basis for the decision of the Fire
Chief or his Deputy in refusing to answer a fire call in Otsego.
5. Because the City of Albertville has heretofore entered into mutual assistance fire fighting
agreements with other municipalities possessing fire fighting equipment and firemen,
which equipment and firemen could be called by the Chief or his Deputy to a fire in
Otsego, the City of Otsego agrees to pay such additional cost as may be incurred thereby if
in the sole judgement of the Chief or his Deputy, such additional fire fighting equipment
and firemen are needed to fight a fire in Otsego and are in fact called to such fire by the
Chief or his Deputy.
IN WITNESS WHEREOF, the parties have hereunto set their hands and seals this
By:
day of 92005.
CITY OF ALBERTVILLE
Don Peterson, Mayor
ATTEST:
Larry Kruse
City Administrator
CITY OF OTSEGO
By:
Larry Fournier, Mayor
Michael Robertson
City Administrator
MAPublic DataTire DepartmentTire Service Contract06 - Otsego.doc 19
9
With All Eauiament & Fire Hall Dearecation
2005 FD Budget
312,645.00
2004 Fire Aid
40,000.00
Depreciation
42,369.44
315,014.44
Otsego
693,732.00
0.100506129
31,660.88
St. Michael
531,873.00
0.077056409
24,273.88
Albertville
5,676,780.00
0.822437462
259,079.68
Total
902.00
1.00
315 014.44
Fire Tax Capacity05
19'
•
•
70th STREET CORRIDOR
sm
• City of Albertville and City of Otsego Joint Meeting
Wednesday, November 2, 2005
Otsego City Hall
6:00 City Council to meet at Albertville City Hall to discuss and get organized for 7:00
meeting in Otsego.
7:00 Joint Meeting called to Order by Larry Fournier
1. NEW MACIVER (Cost share discussion)
2. OLD MACIVER
3. CSAH 37 TRAFFIC SIGNAL
4. 70'h STREET IMPROVEMENT PROJECT
5. CSAH 19 & 70'h STREET IMPROVEMENTS
6. I-94 STATE AND FEDERAL ACCESS REQUEST
a. Statusupdate
b. Phasing Plan
7. MASTER TRANSPORTATION AGREEMENT (Items'1-6)
8. STMA SCHOOL SITE & UTILITIES
9. OTSEGO CREEK (Update/set meeting)
10 FIRE CONTRACT (Questions, comments, etc.)
11 70TH STREET CORRIDOR STUDY (Access Points)
•
1
TO:
City Council
FROM:
Tina L. Lannes
DATE:
July 13, 2005
RE:
Project Update
Council requested an update on outstanding project status. Below are the contracted projects
with amounts paid to date as of June 30,2005:
Project
Total Contract
Paid to Date
Difference
2004 School Pedestrian Trail Bituminous
$353,876.90
$285,078.78
$68,798.12
2004 School Pedestrian Trail
$2,415.00
$1,950.00
$465.00
2004 Prairie Run
$1,595,233.53
$1,183,067.48
$412,166.05
2004 Seal Coat Improvement
$19,965.00
$18,692.60
$1,272.40
2004 Street Overlay
$98,070.00
$89,978.40
$8,091.60
Public Works Building
$1,714,020.00
$1,599,211.00
$114,809.00
2003 CSAH 19 Upgrade
$1,446,496.70
$1,340,629.92
$105,866.78
2003 Seal Coat Improvement
$10,421.00
$10,061.62
$359.38
Frontage Avenue Improvements
$313,719.00
$248,255.72
$65,463.28
Water Main Change Order
$32,394.00
$30,288.00
$2,106.00
CSAH 37 / 60th Street Storm Sewer
$49,983.00
$47,941.00
$2,042.00
Total
$5,636,594.13
$4,855,154.52
$781,439.61
36.14%
Other Projects with amounts paid to date as of June 30, 2005:
Project
Paid to Date
WWTF Expansion
$355,270.60
194 Project
$191,000.04
City Hall
$34,790.02
Total
$581,060.66
C = Construction
R = Retainage
C&R
R
C&R
R
R
C&R
C&R
R
C&R
R
R
CADocuments and Settings\tlannes.CITYOFALBERTVIL\Desktop\council\project.doc
•
•
0
lbertville
2005 Council Update
GENERALFUND
General Fund Revenue: 2005 2005 Actual % of
Budget 6/30/2005 Budget
31010
Current Ad Valorem Taxes
1,461,040
-
0.0%
32100
Business Licenses & Permits
25,000
27,302
109.2%
32110
Liquor Licenses
15,000
19,702
131.3%
32120
3.2 Liquor Licenses
250
394
157.6%
32150
Sign Permits
6,000
1,612
26.9%
32210
Building Permits
500,000
253,074
50.6%
32240
lAnimal Licenses
500
350
70.0%
33401
Local Government Aid
-
-
0.0%
33405
Police Aid
14,000
0.0%
33406
Fire Aid
40,000
0.0%
33422
Other State Aid Grants
-
-
0.0%
33620
County Grants & Aids
10,000
5,630
56.3%
34000
lCharges for Services
8,000
4,303
53.8%
34101
Lease Payments - City Property
1,500
3,285
219.0%
34001
Administration Fees
48,400
-
0.0%
34050
Developer Fees 3%
100,000
30
0.0%
34106
PID/Legal Description Requests
1,500
140
9.3%
34107
Title Searches
1,500
440
29.3%
34302
Fire Protection Contract Charges
58,000
15,830
27.3%
34780
Park Rental Fees
2,000
2,250
112.5%
35000
Fines & Forfeits
100
500
500.0%
36210
Interest Earnings
75,000
430
0.6%
Reserves
Total Revenues
$ 2,367,790
$ 335,272
14.2%
General Fund Expenditures 2005 2005 Actual % of
Budget 6/30/2005 Budget
41100
Council
49,875
12,823
25.7%
41300
Administrator
118,790
45,250
38.1%
41400
City Clerk
179,450
59,983
33.4%
41410
Elections
-
-
0.0%
41500
Financial Administration
93,850
34,509
36.8%
41550
City Assessor
25,000
29,944
119.8%
41600
City Attorney
30,419
3,925
12.9%
41700
City Engineer
40,000
31,147
77.9%
41800
Economic Development
20,700
1,781
8.6%
41910
Planning & Zoning
34,084
11,918
35.0%
41940
City Hall
137,425
18,571
13.5%
42000
Fire Department
312,645
43,772
14.0%
42110
Police
321,600
139,4 00
43.4%
42400
Building Inspection
217,452
70,946
32.6%
42700
Animal Control
3,420
544
15.9%
43100
Public Works - Streets
372,181
110,980
29.8%
43160
Street Lighting
46,800
17,412
37.2%
43200
Recycling
39,100
16,485
42.2%
45000
Culture & Recreation
27,250
230
0.8%
45100
Parks & Recreation
147,750
30,395
20.6%
49300
1 Capital Reserves
150,000
-
0.0%
Total Expenditures $ 2,367,791 $ 680,044
28.7%
data$/Public Data / Finance / Budget/Fin - 2nd budget update.xls
ALBERTVILLE REDEVELOPMENT DISCUSSION
August 10, 2005
A. Introduction to Redevelopment:
1. Easy to avoid.
2. Easy to delay.
3. Easy to put -off until tomorrow.
4. Easier to "take a nap" and allow the urge to pass.
B. Critical Components for Successful Redevelopment:
1. "N" - Need.
2. "A" - Authority.
3. "P" - Plan.
0 4. "T" - Trust.
5. "I" - Imagination.
6.66M99 - Money.
7. "E" - Energy.
C. Next Steps:
1. Reflection/Naptime — continue or not?
2. Develop list of needs, opportunities and conceptual plan alternatives.
3. Reflection/Naptime — continue or not?
10 Community Partners, Inc. — Dave Maroney — (507) 334-4120