1993-08-30 Utility Permit
Wright COUNTY
DEPARTMENT OF HIGHWAYS
Page 1
. , .
Utility Permit
Reference: Project
C.S.A.H. 35
C.R.
In accordance with the application herein, a Utility Permit is granted to City of
Albertville to place, construct and thereafter maintain watermain and
s;:mj t:<3ry sewer on or across, or under the right of way of County Highway No. 35
in the location shown on the sketch which is a part of said application, or in such location as may be specified
by the Department of Highways in the Special Provisions hereof.
SPECIAL PROVISIONS:
(]) see 4'iT~C~'O :SM::~
@ ~v6~;1 Ir~~ tU-~l-r~ ~ }r ~ /-?V/~
;end ~jJr~ ref/'4 I',/n h waf.
o ~~"'1C" i"f::'-< " ~ ~ ?tt'o ~ IOc;.-- 11 4 S; "dO. "0 OCiV /"0 FkIC/L 7-0
S~'r7.-vc:.
c::-- ~ <" .
-;-,..t", s
;:>~_ ,;r "',s ~", <0
........7?<:.
~ocr-j'
T3 0 ""'- -0 .. S Ti::o>o v" .c:>c-)::)
Approv~d
?-Jo - 7'-3
(date)
PermitNo._ 'l.=3-/3S
Certified Check No.
Surety Bond No.
Date of S. Bond or C. Check
Bank or Bonding Co.
Deposit Made by
Board of County Commissioners
Rllff<310 , Minnesota
& /?Lid/I
County Highway Engineer
By
PC'1t~ / r rCl:~~':<'.:r<E
COPIES:
'C"'--~:7-----:--.~"':r--'--~----'-:-_"-"-,,___,,,-_,_
IX. 'Ifat'anytime Wright County,
. acting through its Board of County Commissioners, shall deem
. it necessary to make any improvements or changes on all or
any part of the right of way oft he county highway which affect
a utility located on county highway right of way, then and in
, such event, the owner of the utility shall within 15 days after
written notice from the Board of County Commissioners, or its
authorized agent, proceed to alter, change, vacate or remove
said utility from the county highway right of way so as to
conform to said county highway changes and as directed by
the Board of County Commissioners. S~ch work shall be done
without any cost whatsoever to Wrloht County
and shall be completed within the date specified in said written
notice. Th.e Ntlity shall assume all liability and
saw' Wrlq County harmless from any and
all claims of damage of any nature whatsoever occasioned by
reason of not having removed said utility within the time
specified in said notice.
Page 3
II. When pipes with bells or flanges are installed, the
crossings of the roadbeds of the county highway shall bemade
by boring inside a conduit as provided in paragraph I of this
section or jacking a conduit of sufficient diameter to permit
threading the carrier pipe through it.
III. All voids caused by jacking or boring shall be filled by
pressure grouting. The grout material shall consist of a sand-
cement slurry of at least two sacks of cement per cubic yard and
a minumum of water to assure satisfactory placement.
IV. The underground utilites shall be so installed as virtually
to preclude any necessity for distrubing the roadbeds to
perform maintenance operations.
V. Underground installations shall be accomplished without
damaging or destroying the principal root structure of
specimen trees.
LOCATION SKETCH
Shqw location of proposed facility in relation to the center line of the county highway and other pertinent
features such as right of way line, shoulder line, curb line and edge of surfacing. The facility should also be
referenced to adjacent land lines.