1993-10-14 Extension of Contract Completion Dates
ANNANDALE CONTRACTING, INC.
6646 Co. Rd. 5 N.W. . Annandale, Minnesota 55302
October 14, 1993
Mr. Norm Gartner
Meyer-Rohlin, Inc.
1111 Highway 25 N.
Buffalo, MN 55313
Re: Hardwood Ponds 2nd. Addition
Albertville, MN
Dear Mr. Gartner:
This letter is in regard to the contract completion dates on the aforementioned project in
Albertville.
Please consider this letter as our request to have project completion dates extended an
additional 30 calendar days. With a project bid date of September 7th, 1993, an award to
Annandale Contracting on the evening of the same date, completion and return of
bonding/contracts to the City on September 14, 1993, a notice to proceed could have been
issued on approximately September 15, 1993. As of today's date, we are still awaiting
signed contracts and a notice to proceed from the City. We will attempt to meet original
goals for gravel and curb construction this fall, however, progress will be greatly
dependent upon weather conditions.
We are also asking that the City consider our request to be paid an additional $.43/LF for
any required concrete curb and gutter construction after 11-1-93. Heated concrete and/or
blanket protection will be required for proper cold weather protection after this date. Our
curb contractor has indicated there will be an additional charge for this work.
As always, please feel free to contact me if you have any questions or if you will need
additional information in support of this claim.
Sincerely,
iJ4
Wade Smith
ANNANDALE CONTRACTING, INC.
~(P30 I x $ t}, "f/.!3/lf -;:c ////30.9D