1994-06-23 Change Order #1
. .
MEYER-ROHLIN, INC.
ENGINEERS-LAND SURVEYORS 1111 Hwy. 25 N., Buffalo, Minn.55313 Phone 612 - 682-1781
CHANGE ORDER
Change Order No. 1
Date 6/23/94
Job No. E-930l-B
TO: Annandale Contracting, Inc.
NAME OF JOB: 1993-1 Improvement Project, (utilities and street
Improvement, Hardwood Pond 2n~Add~tion)
OWNER: City of Albertville, MN
The cost of the following changes in your contract on the above
named project is requested. Please complete this form and return
to the Engineer's office on or before June 28. 1994
BREAKDOWN OF CHANGE COSTS
PRESENT TOTAL CONTRACT PRICE . $ 179,980.40
ADD DEDUCT
COST FOR ITEM NO. 1 $ 12.287.50 $
ITEM NO. 2 $ $
ITEM NO. 3 $ $
ITEM NO. 4 $ $
ITEM NO. 5 $ $
ITEM NO. 6 $ $
TOTAL ADD $ 12,287.50 DEDUCT $
NEW TOTAL CONTRACT PRICE .
. $ 192,267.90
Date 7- b - 'Y contract:: Ziti ;~4ZInc.
APPROVED: MEYER-ROHLIN, INC.
~/fl~
BY
Date
APPROVED:
OWNER~ Ci ty of 1lrtville
BYc4 .Lv \ ~~
Date 7/1?)~
7-//-J?~
.
.
DESCRIPTION OF CHANGES
During recent weeks this project has been plagued by heavy
rains. The soils within the development have become wet and,
with the trees shading the roads and blocking the drying winds,
it is doubtful that the roads will be able to dry sufficiently.
All utilities were installed in the fall of 1993 and thus the
trenches should be stable. Therefore, in order to continue with
the project it is recommended that a geotextile fabric be
installed on the subgrade and an additional 3 inches of
aggregate base, Class 5, be installed in order to bridge the
softer subgrade soils.
All work described above has been discussed with Mr. Bob Braun
and received his verbal concurrence to proceed.
The estimated cost of this work is as follows:
1 . Geotextile fabric, type V 7150 sy @ $0.85/sy = $6077.50
2. Aggregate base placed,
Class 5 600 cy @ $10.35/cy = $6210.00
TOTAL CHANGE ORDER No. 1 = $~~:!:~~Z~~~
The quanti ties listed above are estimates on the conservative
side. It is anticipated that the actual quanti ties installed
will be less than those indicated.
End of Addendum No. 1
.
.
DESCRIPTION OF CHANGES
During recent weeks this proj ect has been plagued by heavy
rains. The soils within the development have become wet and,
with the trees shading the roads and blocking the drying winds,
it is doubtful that the roads will be able to dry sufficiently.
All utili ties were installed in the fall of 1993 and thus the
trenches should be stable. Therefore, in order to continue with
the project it is recommended that a geotextile fabric be
installed on the subgrade and an additional 3 inches of
aggregate base, Class 5, be installed in order to bridge the
softer subgrade soils.
All work described above has been discussed with Mr. Bob Braun
and received his verbal concurrence to proceed.
The estimated cost of this work is as follows:
1. Geotextile fabric, type V 7150 sy @ $0.85/sy = $6077.50
2. Aggregate base placed,
Class 5 600 cy @ $10.35/cy = $6210.00
TOTAL CHANGE ORDER No. 1 = $~~:!:~~Z~~~
The quanti ties listed above are estimates on the conservative
side. It is anticipated that the actual quanti ties installed
will be less than those indicated.
End of Addendum No. 1