Loading...
1993-12-14 Partial payment Request #1 . . MEYER-ROHLIN, INC. ENGINEERS-LAND SURVEYORS 1111 Hwy. 25N., Buffalo, Minn.55313 Phone 612-682-1781 December 14, 1993 City of Albertville c/o Linda Houghton, Clerk Box 131 Albertville, MN 55301 RE: 1993~1 utilities & street Improvement Project Hardwood Pond 2nd Addition Partial Payment Request No. 1 'l/0. Honorable Mayor and City Council: The contractor for the above-referenced project has requested partial payment for work completed to date. Below you shall find the quantities for the work performed. BID "A" SANITARY SEWER Item Bid Inst. No. Item Qty. Qty. Unit Unit Price Total Price 1. 8" PVC, SDR 35 ( 0-8 ' ) 1015 773 l.f. $ 15.75 $12,174.75 2. 8" PVC, SDR 35 (8-10') 130 358 l.f. $ 16.75 $ 5,996.50 3. 8" PVC, SDR 35 ( 10-12 ' ) 125 82 l.f. $ 17.75 $ 1,455.50 4. 8" PVC, SDR 35 ( 12-14 ' ) 115 143 l.f. $ 18.75 $ 2,681.25 5. Manhole 48" dia. (0-8') 6 6 each $1100.00 $ 6,600.00 6. Manhole extra depth 8.5 7.10 l.f. $ 70.00 $ 497.00 7. Sewer service connection 27 27 each $ 40.00 $ 1,080.00 8. 4" PVC, SDR 26 service pipe 1320 1290 l.f. $ 6.10 $ 7,869.00 Thore P. Meyer, Professional Engineer Robert Rohlin, Licensed Land Surveyor . . page 2 9. Raise manhole casting 6 1 each $ 200.00 $ 200.00 10. Density tests 80 27 each $ 30.00 $ 810.00 11. Crushed rock 30 17.57 c.y. $ 11.00 $ 193.27 TOTAL BID "A" $~~4:ggZ~~Z ALTERNATE BID "B" - WATERMAIN 1. 6" PVC, C-900 1440 1440 l.f. $ 10.13 $14,587.20 2. 6" 11,z.O DIP bend 2 2 each $ 85.00 $ 170.00 3. 6" 0 1 1 each $ 90.00 $ 90 DIP bend 90.00 4. 8" x 8" x 6" DIP Tee 1 1 each $ 165.00 $ 165.00 5. 6" x 6" x 6" DIP tee 4 4 each $ 125.00 $ 500.00 6. 811 sleeve 1 0 each $ 85.00 $ 0.00 7. Hydrants 4 4 each $1175.00 $ 4,700.00 8. 611 resilient seat gate valve, valve box and riser 6 6 each $ 351.00 $ 2,106.00 9. Water service connection 27 27 each $ 100.00 $ 2,700.00 10. 111 copper service pipe 1315 1270 l.f. $ 6.22 $ 7,899.40 11. Bacteriological test 3 0 each $ 65.00 $ 0.00 12. Density tests 80 29 each $ 30.00 $ 870.00 13. Crushed rock 10 0 c.y. $ 11.00 $ 0.00 14. Raise gate valve 2 1 each $ 150.00 $ 150.00 TOTAL ALTERNATE BID "BII $~~4:~~Z~g~ BID IICII STORM SEWER 1 . 1211 RCP, CL. III 170 170 l.f. $ 17.00 $ 2,890.00 . . . .page 3 2. 1511 RCP, CL. III 345 344 l.f. $ 18.00 $ 6,192.00 3. 1811 RCP, CL. III 413 416 l.f. $ 20.00 $ 8,320.00 4. Catchbasin, 3011 dia. (CBl) 1 1 each $ 700.00 $ 700.00 5. Catchbasin, 4811 dia. (CB7, CB8) 2 2 each $ 950.00 $ 1,900.00 6. Catchbasin 2711 dia. (CB4, CB6, CB9) 3 3 each $ 775.00 $ 2,325.00 7. Catchbasin, Special (CB2, CB3, CB5) 3 3 each $ 825.00 $ 2,475.00 8. 18" RCP flared end section w/galvanized trash guard 2 2 each $ 585.00 $ 1,170.00 9. Remove existing CB salvage casting, remove 18" RCP 100% 100% l.s. $ 210.00 $ 210.00 10. Random rip-rap Class III 3.6 0 c.y. $ 55.00 $ 0.00 11. Filter blanket 1.8 0 c.y. $ 8.00 $ 0.00 12. Clearing & grubbing 100% 100% l.s. $2000.00 $ 2,000.00 13. Pond grading 100% 100% l.s. $1200.00 $ 1,200.00 14. Density tests 20 0 each $ 30.00 $ 0.00 15. Crushed rock 10 0 c.y. $ 11.00 $ 0.00 TOTAL BID "C" $~~4:~~~~~~ BID "D" STREET 1. Subgrade preparation 7150 0 s.y. $ .50 $ 0.00 2. Aggregate base placed, Class 5 2375 34 c.y. $ 10.35 $ 351.90 3. Remove concrete curb and gutter 66 66 l.f. $ 2.00 $ 132.00 4. Type 31 base Course mixture 9350 200 sy-in $ 1.48 $ 296.00 5. Type 41 wear course mixture 9350 200 sy-in $ 1.48 $ 296.00 . . page- 4 . . 6. Surmountable concrete curb & gutter 2630 o l.f. $ 5.35 7. Density test o each $ 40.00 15 TOTAL BID "D" TOTAL COMPLETED WORK LESS 5% RETAINAGE PARTIAL PAYMENT NO. 1 $ $ 0.00 0.00 $=~4:~Zg~~~ $103,952.77 $ 5,197.64 $ 98,755.13 We therefore recommend Partial Payment No. 1 be made to Annandale Contracting, Inc., 6646 Co. Rd. 5 NW, Annandale, MN 55302, in the amount of $98,755.13 If you have any questions, please feel free to contact me. Sincerely, MEYER-ROHLIN, INC. ~~ Norman Gartner Professional Engineer cc: E-930l-B Annandale Contracting, Inc.