1987-12-11 Prelim Cost Estimates
MEYER-ROHLIN, INC.
ENGINEERS-LAND SURVEYORS 11n Hwy. 25 N., Buffalo, Minn.55313 Phone 612- 682-1781
TO: Darkenwald Real Estate
FROM: Meyer-Rohlin, Inc.
RE: Preliminary Cost Estimates for Proposed Development
Southwest corner of County Roads 19 & 37
DATE: December 11, 1987
The following are preliminary cost estimates for the proposed Phase I
development based upon the sketch plan prepared by Meyer-Rohlin, Inc.
(S-87120) .
I. Development of Phase I (48 lots)
Estimates include construction and engineering
Sanitary Sewer
Water Main
Storm Sewer
Streets (finished)
Site grading
@
@
@
@
@
$1,700.00/1ot
$1,350.00/1ot
$1,600.00/1ot
$3,000.00/lot
$l,OOO.OO/lot
$S-:-650:-o5/1ot x 48 lots =$415,200.00
II. Extension of Water & Sanitary Sewer to the Phase I site:
a) Lift Station &
Force Main assess =
b) Trunk from lift station to
the 37 & 19 intersection =
$420.00/ac
$201.00/ac
$621:-00/ac x 90+
acres
= $ 55,890.00
c) Water & Sewer from 37 & 19 intersection to
48 lot Phase I - possible front foot assess
=
$_~~L~Q.Q.:..Q.Q.
$556,590.00
Tflore p. Meyer, Professional Engineer Robert Rohlin, Licensed Land Surveyor