2004-06-16 Construction Meeting Minutes Towne lakes in Albertville Construction Meeting Minutes, Submitted by Stephen Swanson In Attendance: Steve Swanson, Rottlund Scott Ruegemer, Rottlund Dave Dickinson, Rottlund Russel Bly, SEH Ken Schick, Westwood cc: Steve Swanson, Rottlund Scott Ruegemer, Rottlund Tim Himmer, Rottlund Dave Dickinson, Rottlund Ken, Westwood John Carlson, Westwood Dave Hemple, CPDC Paul Haugo, Braun Intertec Russel Bly, SEH John Middendorf, City of Albertville Preinstall installation to start May 17th. Braun to review compaction of trench inspections to be 04/28 'done by John Middendoif at City and Russell at SEH. House side of curb stop take care in Hennen installation (inspect). Nine services left as of 6/16 (3 days left). 04/28 Hennen to test water line with City pressure. Sanitary sewer test 5 Ibs/15 minutes. 150 note John Carlson Ibs/2hours Copy test results to Jon Sutherland at the City of Albertville, Jim Schultz at SEH and Russell at 04/28 SEH (compaction and sewer and water). Sewer and water testing to be complete. Need to note Braun have model occupancy end of May. Report for ea plan. No written test reports. 04/28 Street start June 15th. Completion end of June. Dave, CPDC I 04/28 ISmail utility start date of July 5,2004. Need to contact Wayne B. and W/H. 04/28 'Phase II development not yet approved. Sometime July 2004. Submit 6/15 final plat 7/19/04 City Council Meeting. 04/28 Draintile leads not on development plan as of 4/28/04. Plans done. Sump discharge (single family) must discharge to storm sewer. Current single family (developed lots) daylight - refer to City detail. Sleaving plan - irrigation, small utility. Ken has plan. Wayne at Wright- Hennepin Scott R. CPDC Westwood 04/28 note CPDC, Westwood Dave D. 04/28 John Carlson, Ken 04/28 Top soil stockpile. Blk 1, Lots 1 - 4. 4th Addition. 04/28 Seed and mulch site after grading completion. note Fehn 04/28 Review street condition - document damage. Curb 05/12 City sidewalk schedule - Urban Villa phase. Complete sidewalk front of single family model. SF Lots 2 and 3, block 3. Multi lots 12 - 17, Block 2. Week of 5/29. Start 6/11/04. Ken at Westwood Scott R. Dave H.lCPDC Tim H. 05/19 Survey services to verify location. Ongoing. note Westwood 05/19 Drop c.b. 581'-0" for dt drainage from lots 11 - 14, blk. Verify elevation at street storm. Don't need to do. Revised irrigation service location (2" copper) to include 1" blowout. Location 5'-0" from parking bay. Provide detail for Henne. Install 6/17. 05/19 Remove farmhouse and barn 1 st week of June. Westwood, Ken 05/19 Westwood Dennis Fehn OS/26 Soils from preinstall installation to be placed at future park area to include concrete washout - past power lines. OS/26 Draintile leads at CB 58 (drop 1 1/2) connection for 3 buildings. OS/26 Laketowne Drive wearcourse schedule Fall of 2004. OS/26 Traffic signage install week of June 14, 2004. OS/26 Preinstall inspection fees responsibility to be determined. Rottlund, SEH, City of Albertille. 06/16 Start street construction on 6/23/04. Curb following week. Wtih no rain, pave by July 2nd. lrrigationsleeves/d.t. leads. 06/16 Sidewalks poured 6/17/04 (by Models). CPDC Steve S. info note Scott R. Scott R., Dave D. MinutesTowneLakes (Iv)