2004-08-19 Pre Con Meeting .. MEYER-ROHLIN, INC. ENGINEERS-LAND SURVEYORS 1111 Hwy. 25 N., Buffalo, MN 55313 Fax 763-682-9492 Phone 763-682-1781 1-800-563-1781 Karston Cove Third Addition Grading & Street & Utility Improvement Projects August 19,2004 Meeting Minutes Mobile FROM: Bob Moberg SEH Larry Kruse City of Albertville Jimmy Diedrich LaTour Construction 612-366-5672 Bret Schoen Fehn Excavating 612-282-6543 Ron Olson Sprint, Inc. David Pattberg Woodside Comm. Henry Vloo Braun Intertec Greg Chapman Charter Communicat. Carl Johnson XCEL Energy / Joint Trench Design Nick Nowacki, Meyer-Rohlin, Inc. rV e..J 763-300-1361 612-366-1621 Phone 651-490-2147 763-497-3384 320-963-5993 763-497-2428 952-448-8368 952-448-3062 763-771-1017 763-757-4052 952-995-2238 952-995-2020 763-682-5982x20 682-1645 Fax 651-490-2150 651-497 -321 0 320-963-6017 TO: DATE: August 20,2004 LOCATION: Albertville City Hall Conference Room RE: Pre-construction Meeting Signup sheet Introductions Project Synopsis Access to Project -Only one construction access per side (North & South) shall be used. Rock entrance is a must and care should be taken to reduce the amount of material tracking onto 6lh Street NE. -When utility work is taking place near the street, the proper road closed signs and warning instruments shall be utilized. Bob will look into the possibility of closing that portion of 64th Street NE along the site during the entire construction process. -If road closure is possible, Fehn will lay fabric on the existing road and build a dirt berm across the street for equipment crossing. Street -Bob and Dave will investigate the timing for placement of the wear course on 6lh Street NE. If at all possible, wear course placement should be delayed until after construction of Karston Cove 3rd Addition, and possibly timed for completion during placement of the townhome area base course. Safety (Public & Workers) -Shall be the responsibility of the active job foreman and supervisor. Thore P. Meyer, Professional Engineer Robert Rohlin, Licensed Land Surveyor Construction Scheduling Contractor's Schedule -Fehn is planning to start some time at the end of next week. They will require 2-3 weeks of time to complete. -LaTour will begin work after Fehn's work is complete. Utility work will take 2-3 weeks and street work will take approximately 2 weeks. Completion slatedfor middle to late October at which time small utilities may begin their work. Allowable work hours & days 7am to 6pm M-S - Work will be allowed beyond 6pm to a reasonable time. The contractor shall be immediately informed of any complaints and appropriate measures will be taken. -Russel Bly of SEH will be inspecting for the city and shall be given as much notice as possible of any plans to work on Saturdays. Staked by Meyer-Rohlin, Inc. 48 hours notice -Craig Johnson is the new staking scheduler. Permits (as applicable) -A copy of all acquired permits will be forwarded to Bob and the City of Albertville. MPCA Sanitary Sewer-Permit mailed / waiting. MN HD Water Main-Permit acquired. MPCA Storm Water-Permit mailed on 8-16-04/ active on 8-25-04. MnDOT Access-N/A MnDOT Utility-N/A MnDOT Storm Water-N/A County Access-N/A County Utility-N/A County Storm Water-N/A MnDNR Water Appropriation-N/A MPCA Water Discharge-N/A Information from Contractor -Fehn & Latour shall send the following information to Meyer-Rohlin, City of Albertville, and SEH as soon as possible. Insurance Schedule Suppliers Subcontractors Forman Contacts (3) -Latour shall submit manhole shop drawing for review to Meyer-Rohlin. Following revisions a copy shall be sent to the City and SEH. -Latour shall also submit the following shop drawings for review to Meyer-Rohlin, SEH, and the City of Albertville. -Bituminous mix design. -Hydrants. -Water services (curb stops, corporations, etc.) Testing Requirements -Soils testing will be peiformed by Braun-Intertec. All testing shall be coordinated with Braun. Copies of all tests will be forwarded to Meyer-Rohlin, Woodside, SEH, and the City of Albertville. -All street subgrades will be test rolled. The necessity offurther test rolling (i.e. Class V) will be determined based upon subgrade test roll results. -Geotextile fabric will be used if soil corrections warrant it. -Allowance of zero air voids in compaction will be determined later if needed. Soils-Mineral Gradation -Required on Class V and select granular. Bituminous Gradation Sanitary Sewer Tests Air Mandrill Televising Water Main Bacteriological Pressure Conductivity -All hydrants shall be bagged until all tests have been completed and accepted by the City. -If the contractor requires any water is available at the hydrant at the Joint Powers building. Open Discussion -Record plans will be generated by Meyer-Rohlin. Any ties and information recorded by Russell Bly shall be provided to Meyer-Rohlin following completion of construction. .